5 year bid date report February 15, 2013 |
Previous | 31 of 34 | Next |
|
This page
All
Subset |
February 15, 2013
This report contains the construction projects from the new 5-Year Program. The report is sorted 7 different ways; 1) by project name,
3) by bid date, route and beginning milepost, 4) by TRACS number, 5) by route, beginning milepost and TRACS
6) by engineering district, route, beginning milepost and TRACS number and 7) by CPSID.
Several projects are on “special” status as indicated by a bid date in the year 2050. The special categories are listed below.
STATUS
02/25/2050 IGA/JPA PROJECTS WITHOUT SCHEDULE
05/25/2050 PROJECTS IN THE NEW 5-YEAR PROGRAM IN THE PROCESS OF BEING SCHEDULED.
06/25/2050 DESIGN PROJECTS IN THE 5-YEAR PROGRAM WITHOUT CORRESPONDING CONSTRUCTION PROJECT
08/25/2050 PROJECTS THAT ARE ON “HOLD” STATUS UNTIL THE PROBLEMS ARE RESOLVED AND A DECISION IS
MADE ON RESCHEDULING. PROJECT DEVELOPMENT SHOULD CONTINUE IF POSSIBLE.
09/25/2050 PROJECTS THAT HAVE BEEN DELETED FROM THE CURRENT 5-YEAR CONSTRUCTION PROGRAM. WE
WILL MAINTAIN THESE PROJECTS ON THE PRIMAVERA SYSTEM FOR RECORD. PROJECT DEVELOPMENT
IS TERMINATED FOR THESE PROJECTS .
ARIZONA DEPARTMENT OF TRANSPORTATION
PROJECT CATEGORIES
PROJECT CATEGORY
5-YEAR BID DATE REPORT
PROGRAM & PROJECT MANAGEMENT SECTION
AMEC AMEC LSD Logan Simpson Design
AZTC Aztec Engineering MB Michael Baker Jr., Inc.
BN Burgess & Niple MBD1 Michael Baker/Design One
BRW BRW MMLA MMLA, Inc.
BSA Bulduc, Smiley & Associates. Inc. OLSN Olsson & Associates
C&B Carter & Burgess PARS Parsons Transportation Group
CANN Cannon & Associates PBQD PBQD - Parsons Brinkerhoff Quade & Douglas
CDG Corral Dybas Group, Inc. PBSJ PBS&J
CH2M CH2M Hill PREM Premier Engineering Corporation
DIBL Dibble & Associates RBF RBF Consulting
DMJM DMJM+Harris RPOW Ritoch Powell & Associates
EEC EEC SCON Stanley Consultants
ENTR Entranco STEC Stantec Consulting, Inc.
ERTH Earth Tech SVER Sverdrup
GANN Gannett Fleming TBA To Be Assigned
HDR HDR Engineering TCOR Transcore
HUIT Huitt - Zollars TTI Tetra Tech, Inc.
JLK JLK Eingeers TYLN T. Y. Lin International
INCA Inca Engineering, Inc. URS URS
DESIGN FIRM ABBREVIATIONS
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 1 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
11714 BN1M 8 YU 2.0 IM - Y 16TH STREET LANDSCAPING JUN 14
43514 WZ1K 202L MA 0.0 RARF- E 17TH AVE TO 51ST AVE, SEGMENT 3 CONSTRUCT NEW FREEWAY TBD FY 15
HV1L 0000 MA WBG SL69001C TEA -WBG-0(201)D P 1962 HASSAYAMPA RIVER BRIDGE PEDESTRIAN/BICYCLE IMPROVEMENT FY 13
45314 EQ1M 202L MA 0.0 NH - E 24TH ST - 17TH AVE, SEGMENT 2 DESIGN NEW FREEWAY DESIGN FY 14
44612 WR1K 10 MA 151.5 IM - E 32ND ST - SR202L, SANTAN PHASE 1 CONSTRUCT LOCAL EXPRESS LANES DESIGN FY 17
WM1L 5013 MA 0.0 SR14401C 501-3(001)P E 32ND ST ( PHX) #741-536-B SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13
45309 FN1H 10 MA 96.2 H708301X Y 395TH AVE (BELMONT RD) CONSTRUCT TI IGA FY 14
12014 BR1M 10 MA 145.0 IM - E 3RD AVENUE TO 3RD STREET PUMP STATION IMPROVEMENTS TBD FY 14
12314 YD1L 10 MA 144.9 IM -010-C(209)T E 3RD AVENUE TO 3RD STREET, DECK PARK TUNNEL DRAINAGE IMPROVEMENTS TBD FY 14
WN1L 7018 MA 0.0 SR09701C 701-8(003)P E 40TH ST PHOENIX 741-539-W SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13
12916 DC1M 77 NA 384.0 STP - H 5 MILE WASH - JCT 377 CBC EXTENSION TBD FY 16
WL1L 940 MA 0.0 SR19201C 000-6(172)A E 5TH ST (TEMPE) 741-560-C AT-GRADE RAILROAD CROSSING DESIGN JUN 13
PL1K 0000 MA MMA SS89901C CM -MMA-0(228)A E 87TH AVENUE PAVING DIRT ROAD FY 13
CC1L 0000 MA MMA SS95701C CM -MMA-0(231)A E 88TH AVE: DEER VALLEY TO WILLIAMS RD PAVE UNPAVED ROAD FY 13
14714 QO1L 40 NA 303.0 IM - H ADAMANA TI DRAINAGE IMROVEMENTS TBD FY 14
40317 EP1M 101L MA 11.2 NH -888-A(217)T E AGUA FRIA I-10 TO I-17 CONSTRUCT FMS TBD FY 17
11207 QK1C 19 PM 58.7 NH - T AJO WAY TI (JCT SR 86) RECONSTRUCT TI TBD FY 17
CY1M 347 PN 172.0 347-A(209)T T ALTERRA TO CASA BLANCA RD, CITY OF MARICOPA DESIGN DESIGN FY 13
10312 LE1G 93 MO 101.8 H738801C NH -093-B(204)T K ANTELOPE WASH CONSTRUCT 4-LANE DIVIDED HIGHWAY FEB 13
13213 RN1K 88 MA 204.0 STP - E APACHE JCT - TORTILLA FLATS MILL 2" & 3" AC & CHIP SEAL JAN 14
15414 JG1K 77 PN 123.5 H796901C T ARAVAIPA CREEK BRIDGE, STR #399 BRIDGE REPLACEMENT AUG 13
13115 WT1L 40 YV 144.0 IM -089-B(214)T K ASHFORK RR BR - JCT SR 89, #807,#440, #1760,#1761 BRIDGE DECK REHABILITATION TBD FY 15
JP1L 0000 MA MMA SS97401C E ATIS ENHANCEMENTS REGIONWIDE ARTERIAL ATIS FY 13
20313 CX1M 210 PM 1.0 STP - T AVIATION CORRIDOR IN TUCSON SIGN REHABILITATION TBD FY 13
19613 EJ1L 95 MO 250.0 STP -095-D(207)T K AVIATION WAY - BULLHEAD CITY PARKWAY PE PH 1 & 2 TO CONSTRUCT CONCRETE MEDIAN DESIGN FY 13
16006 QT1F 101L MA 53.5 E BALBOA DRIVE CONSTRUCT MULTI-USE PATH BRIDGE OVER TH IGA FY 15
41015 NX1L 202L MA 0.0 E BASELINE - SALT RIVER, SEGMENT 6 CONSTRUCT NEW FREEWAY TBD FY 15
17514 MQ1J 180 AP 338.0 H752001C STP -180-B(204)A G BEAVER DAM - RANCH (EB & WB) 3" CIPR & FR AUG 13
ZJ1K 0000 MA SUR SS85401C CM -SUR-0(210)A E BELL RD-US 60 TO 114TH AVE CONSTRUCT MULTI-USE PATH FY 14
11913 TI1K 8 PN 170.0 IM - T BIANCO ROAD - JCT I-10 RR(5" TL, 3" PL) & AR-ACFC NOV 13
12913 RX1K 69 YV 271.6 H812201C P BIG BUG 4 TO POLAND JCT RR 3" TL, RR AR-ACFC FULL WIDTH MAR 13
18313 MI1K 89 YV 335.9 H797601C 089-B(204)T P BIG CHINO WASH BRIDGE #979 DECK REPLACEMENT / WIDENING JAN 13
12813 ZY1J 40 NA 303.1 H785901C IM -040-E(214)T H BIG LITHODENDRON-PETRIFIED FOREST NATIONAL PA PAVEMENT PRESERVATION MAR 13
MD1K 0000 NA PLS SS86401C HPP -PLS-0(201)A G BILLY CREEK BRIDGE @ PORTER MOUNTAIN ROAD CAPACITY ADDITIONS - MAJOR WIDENING FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 2 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
16714 FD1L 89 CN 523.9 NH - F BITTER SPRINGS INSTALL INTERSECTION LIGHTING TBD FY 14
12413 RW1K 17 YV 245.0 H812101C P BLACK CANYON HILL (NB) RR (5" TL, 3" PL) & AR-ACFC APR 13
NG1L 0000 MA PHX PHX-0(266)A E BLACK MOUNTAIN BLVD, SR 51/SR 101 NEW ROADWAY FY 14
XD1L 0000 YU YYU SB44501C BR -YYU-0(205)A Y BRIDGE REHABILITATION OLD HWY 80 & AVE 30 1/2 E BRIDGE REHABILITATION FY 14
LK1K 0000 MA TMP SS73401C CM -TMP-0(210)X E BROADWAY ROAD: RURAL TO MILL AVENUE PEDESTRIAN IMPROVEMENTS FY 15
12515 BZ1M 17 MA 198.0 IM - E BUCKEYE RD, GRANT,JEFFERSON & ADAMS ELECTRICAL REHABILITATION TBD FY 15
12415 VT1K 17 MA 195.0 E BUCKEYE RD,GRANT ST,ADAMS ST & JEFFERSON ST ELECTRICAL REHABILITATION TBD FY 15
19213 LC1J 92 CH 324.3 H716701C HSIP-092-A(200)T S BUFFALO SOLDIER TRAIL TO KACHINA TRAIL RAISED MEDIAN JUN 13
15015 DX1M 191 AP 418.0 STP - H BURNSIDE - CHINLE FENCING & CATTLE GUARDS TBD FY 15
16815 SL1K 264 AP 441.0 STP - H BURNSIDE - CROSS CANYON 2" AC & AR-ACFC TBD FY 15
15315 ED1M 264 AP 441.0 STP - H BURNSIDE - SUMMIT FENCE & CATTLE GUARD TBD FY 15
18814 YJ1K 999 SW 0.0 H821701C STP -999-A(351)T Y BURNT WELL AND EHRENBURG REST AREAS WATER,STRUCTURAL,MECH & ELECTRICAL REH NOV 13
15114 GN1J 70 GH 295.0 S BYLAS TWLTL & ROADWAY WIDENING JUN 14
43814 OB1L 303L MA 107.0 E CAMELBACK ROAD TO GLENDALE AVENUE CONSTRUCT LANDSCAPE JUN 14
PW1H 0000 PM TUC SS63201C TEA -TUC-0(203)B T CAMPBELL AVE - MAIN STREET MAIN STREET REVITALIZATION FY 13
10216 DO1M 93 MO 109.0 NH - K CANE SPRINGS PE PH 1 & 2 DESIGN FY 16
14414 EV1L 40 CN 218.7 H789001C IM - F CANYON PADRE BRIDGE, STR #1670 DECK REPLACEMENT APR 14
10413 TC1J 93 MO 116.0 K CARROW TO STEPHENS CONSTRUCT 4-LANE DIVIDED HIGHWAY TBD FY 16
10910 DJ1G 90 CH 323.5 H655501C S CENTRAL AVE TO MOSON RD, E OF SIERRA VISTA WIDEN TO 5 LANES TBD FY 14
17413 CP1M 40 AP 322.0 NH - H CHAMBERS PORT OF ENTRY PE PH 1 & 2 DESIGN FY 13
17414 DS1M 169 YV 4.8 STP -169-A(203)S P CHERRY ROAD CONSTRUCT TURN LANES / BOX EXTENSION TBD FY 14
12010 EB1E 191 AP 446.3 H543801C STP -191-E(205) H CHINLE - SOUTH ROADWAY WIDENING TBD FY 13
22910 YS1K 0000 CH DGS SS87401C DGS-0(200)A S CHINO ROAD NEW FACILITIES - CONSTRUCTION OF NEW ROA FY 14
17214 XL1L 95 LA 149.2 HSIP-095-C(216)A Y CIENEGA SPRINGS RD SB LEFT TURN LANE APR 14
10617 DI1M 87 CN 324.0 STP - P CLOVER CREEK ROCKFALL MITIGATION TBD FY 17
14112 AI1K 191 CH 61.5 H788301C 191-A(203)A S COCHISE POWER PLANT - JCT I-10 RR 2" AC + 3" AC + FR TBD FY 14
12516 LP1K 89A CN 538.0 STP - F COLORADO RIVER TO HOUSE ROCK (PHASE II) EXTEND PIPES AND CULVERTS TBD FY 16
13513 RT1K 180 CN 216.2 H811801C STP -180-(202)T F COLUMBUS AVENUE - SNOW BOWL RR 3" & AR-ACFC & TURN LANES NOV 13
XX1K 0000 MA CHN SS93201C E CONSOLIDATED CANAL MULTI-USE PATH PATHWAY/TRAIN IMPROVEMENTS FY 13
MB1K 0000 PN CLG SS87301C STP -CLG-0(200)A T COOLIDGE AVENUE DESIGN / RECONSTRUCTION FY 14
18113 NY1K 79 PN 101.8 H807501C BR -079-A(205)T T CORONADO WASH BRIDGE STRUCTURE #222 BRIDGE REPLACEMENT MAY 13
18214 SH1K 260 NA 321.4 NH -260-B(216)A G COTTONWOOD WASH - SHOW LOW RR 3" AC & AR-ACFC TBD FY 14
11312 CQ1J 10 PM 264.0 NH - T COUNTRY CLUB ROAD TI DESIGN TRAFFIC INTERCHANGE (PE PH 1) DESIGN FY 16
BA1L 0000 YU YYU SB43701C BR -YYU-0(201)T Y COUNTY 19TH ST BRIDGE OVER MAIN DRAIN (AVE F 1/2 BRIDGE REPLACEMENT FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 3 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
14413 RU1K 160 NA 358.1 H811901C F COUNTY LINE - BLACK MESA RR 3" & AR-ACFC FEB 13
40216 EN1M 60 MA 192.0 NH - E CRISMON RD - MERIDIAN RD DESIGN HOV/GPL DESIGN FY 16
10217 CD1M 40 MO 40.0 IM - K CROOKTON TO TRANSWESTERN SIGN REHABILITATION TBD FY 17
16914 AE1K 264 AP 459.0 H786301C STP - H CROSS CANYON - SUMMIT 2" AC & AR-ACFC TBD FY 14
16313 PY1E 40 YV 102.0 IM - K CROSS MT - JOLLY RD UPGRADE EXISTING ROCKFALL PROTECTION TBD FY 13
12814 NB1K 10 PM 283.6 H805201C IM -010-E(208)A T DAVIDSON CANYON - COUNTY LINE MILL AND REPLACE NOV 13
11815 NA1L 10 PM 284.4 IM -010-E(213)A T DAVIDSON CANYON WB BRIDGE, STR #598 SUPERSTRUCTURE REPLACEMENT TBD FY 15
10116 TE1J 89 YV 320.4 H803901C STP -089-B(203)A P DEEP WELL RANCH ROAD TO SOUTH CHINO VALLEY CONSTRUCT ROADWAY WIDENING AUG 13
18713 MS1K 89 YV 333.1 H791901C 089-B(208)T P DEL RIO RANCH BRIDGE #20046 BRIDGE REPLACEMENT JAN 13
PH1K 0000 MA MMA SS89301C STP -MMA-0(226)A E DOBSON ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 15
44814 TX1H 202L MA 47.8 CM -888-A(218)T E DOBSON ROAD TO I-10, MARICOPA CONSTRUCT FMS TBD FY 14
WJ1L 0000 MA 0.0 SR23201C E DOBSON ROAD, AAR/DOT NO. 741-649-G SYSTEM ENHANCEMENT-SAFETY IMPROVEMENT FY 14
JQ1L 0000 MA SUR SS95801C E DOVE VALLEY ROAD,18TH AVE-203RD AVE ROADWAY IMPROVEMENTS FY 13
12213 SQ1K 10 CH 318.8 H815101C IM -010-F(216)T S DRAGOON RD - WEST WILLCOX TI (WB) PAVEMENT PRESERVATION APR 13
15514 NH1L 77 GI 147.6 H832201C BR -077-A(207)A G DRIPPING SPRING BRIDGE #398 BRIDGE REPLACEMENT JUL 13
13614 SO1K 17 YV 269.2 IM -017-B(218)A P DUGAS TI - CHERRY ROAD RR (5" TL, 3" PL) & AR-ACFC DEC 13
13815 SR1K 75 GE 379.1 S DUNCAN BRIDGE - LITTLE SANDS WASH 3" AC & AR-ACFC TBD FY 15
UH1K 0000 MA SCT SS91301C CM -SCT-0(211)A E DYNAMITE BLVD - PIMA TO ALMA SCHOOL ROAD INSTALL CURB AND GUTTER FY 13
40016 EK1M 10 MA 129.5 IM - E DYSART RD - 83RD AVE DESIGN & CONSTRUCT FMS TBD FY 16
45613 UU1L 10 MA 129.5 RARF- E DYSART ROAD TO SR 101L (AUGA FRIA FWY) LANDSCAPE CONSTRUCTION JUN 13
GT1M 40 NA 289.0 040-D(227)T H E HOLBROOK TI OP EB#1369 & WB #1370 DESIGN BRIDGE REHABILITATION DESIGN FY 13
YT1L 169 YV 5.1 H853601C STP -169-A(204)T P E OLD CHERRY RD - W CHERRY CREEK RD PAVEMENT PRESERVATION (MICRO-SURFACING MAR 13
20013 YU1L 180 AP 426.0 STP - G EAGER ALPINE INSTALL DRAINAGE FACILITY JUN 13
10112 JW1K 10 PN 186.7 T EARLEY ROAD TO JCT I-8 ROAD WIDENING TBD FY 16
12613 RP1K 40 YV 146.2 F EAST ASHFORK TI - COUNTY LINE RR 3" & 2" AC & AR-ACFC TBD FY 13
12613 NQ1L 40 CN 146.0 H840201C IM - F EAST ASHFORK TI TO WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC APR 13
16413 IW1L 40 CN 180.8 IM -040-C(208)A F EAST OF PARKS ROCKFALL MITIGATION JUN 13
16515 ZA1L 60 PN 228.8 G EAST OF QUEEN CREEK TUNNEL ROCKFALL MITIGATION TBD FY 15
IX1L 180 NA 307.3 H831801C STP -180-B(205)T H EAST OF SR 77 NEAR HOLBROOK PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13
10317 CG1M 40 MO 81.0 IM - K EAST OF US 93 TI ROCKFALL MITIGATION TBD FY 17
16613 CK1M 40 NA 226.0 IM - H EAST WINSLOW TI PE PH 1 & 2 DESIGN FY 13
HC1J 10 LA 1.0 Y EHRENBERG EXIT 1 ROUNDABOUT JUN 13
15710 NN1F 10 LA 3 H616101C NH - Y EHRENBERG PORT OF ENTRY RECONSTRUCT EB PORT OF ENTRY TBD FY 16
45713 EU1M 303L MA 120.0 NH -303-A(215)T E EL MIRAGE RD DESIGN TI DESIGN FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 4 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
11616 GQ1G 82 SC 39.0 STP - T ELGIN TURNOFF EXTEND CMP'S, FLATTEN SLOPE & ELIMINATE G TBD FY 16
42115 ER1M 202L MA 0.0 IM - E ELLIOT RD - BASELINE RD, SEGMENT 5 DESIGN NEW FREEWAY DESIGN FY 15
14113 DK1M 89A YV 330.0 STP - P FAIN ROAD TO SR-169 CORRIDOR LOCATION REPORT FOR RTE EVALU DESIGN FY 13
18013 ZS1H 77 NA 367.0 STP - H FIVE MILE WASH BRIDGE PE PH 1 & 2 (WIDEN ROADWAY TO 4 LANES) DESIGN FY 13
14213 DN1M 89 CN 420.0 NH - F FLAGSTAFF CITY LIMITS - LENOX PARK FEASIBILITY REPORT FOR ACCESS MGT PLANNI DESIGN FY 13
17613 XI1J 60 GI 305.0 H778601C STP -060-E(211)A G FLYING V CANYON TO SQUAW DRESS RIDGE SLOPE STABILIZATION JUN 13
11814 SV1K 8 YU 13.7 H815801C IM - Y FOOTHILLS BLVD - DOME VALLEY RR (5" TL, 3" PL) & FR NOV 13
10416 NW1L 95 YU 34.0 H459901C NH -095-B(201) Y FORTUNA WASH BRIDGE CONSTRUCT NEW BRIDGE TBD FY 16
13413 RS1K 89A CN 609.3 F FREDONIA - STATE LINE RR 3" & AR-ACFC TBD FY 13
GX1M 86 PM 120.6 086-A-NFA T FRESNAL TO MP 123.9 DESIGN DESIGN FY 13
VS1L 101L MA 60.0 H848801C 101-C(201)A E GALVESTON DRAINAGE BASIN G (THUDE PARK) DRAINAGE IMPROVEMENT & PUMP STATION IGA FY 13
18414 EE1M 264 AP 446.0 STP - H GANADO SECTION WIDENING TO 3 LANES & TL TBD FY 14
XX1G 264 AP 446.0 264-A(212)T H GANADO WASH BRIDGE #1046 DESIGN BRIDGE REPLACEMENT DESIGN FY 14
12013 SW1K 10 LA 63.0 H815901C 010-A(217)T Y GAS LINE RD - COUNTY LINE RR (1/2" TL, 4" PL) & AR-ACFC FEB 13
14715 SF1K 180 AP 386.3 STP - G GENERATING STATION ROAD - JCT US 60 RR 3" & CHIP SEAL TBD FY 15
14913 YG1L 8 YU 125.0 Y GILA BEND TO I-10 SIGN REHABILITATION DESIGN FY 13
14315 SG1L 87 PN 148.0 BR - T GILA RIVER BRIDGE, STR #635 SCOUR RETROFIT DEC 14
OA1K 0000 MA MMA SS87901C STP -MMA-0(218)A E GILBERT ROAD BRIDGE OVER THE SALT RIVER CONSTRUCT BRIDGE FY 15
13715 KX1L 70 GI 259.0 H835901C G GILSON WASH BRIDGE, STR # 464 SCOUR RETOFIT TBD FY 15
45113 OC1L 303L MA 109.0 H860301C RARF- E GLENDALE AVE TO PEORIA AVE CONSTRUCT LANDSCAPE JUN 14
12816 CM1M 40 NA 297.0 IM - H GOODWATER - YELLOWHORSE PE PH 1 & 2 DESIGN FY 16
23213 BM1L 64 CN 234.5 H825801C F GRAND CANYON AIRPORT- FS RD 328 SHOULDER WIDENING TBD FY 15
13812 AH1K 89 CN 510.0 NH -089-D(202)A F GRAY SPOT WASH - NORTH RED HILL 3" AC + FR NOV 13
NF1L 191 GE 184.5 H841201C STP -191-C(215)T S GREY PEAK TO JUAN MILLER ROAD PAVEMENT PRESERVATION (DOUBLE CHIP SEAL APR 13
YQ1L 70 GH 347.0 H853801C S HAEKEL RD TO US 191 SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13
12416 BU1L 999 SW 0.0 H826301C STP - K HAVILAND & MARBLE CANYON REST AREAS STRUCTURAL REHABILITATION TBD FY 16
JN1M 89 YV 345.7 H863601C K HELL CANYON BRIDGE DECK REHABILITATION TBD FY 13
XA1L 89 YV 345.0 089-B(211)T K HELL CANYON BRIDGE #483 REPLACEMENT & WIENING TBD FY 14
14614 SJ1K 40 NA 290.2 H813101C IM -040-D(219)A H HOLBROOK - SUN VALLEY RR (5"TL, 3"PL) & AR-ACFC JUL 13
16913 CL1M 40 NA 290.0 IM - H HOLBROOK - SUN VALLEY FENCING AND CATTLE GUARDS TBD FY 13
13209 A6SP 87 NA 346.0 H717901C H HOMOLOVI RUINS STATE PARK CONSTRUCT ROAD TBD FY 14
GZ1L 0000 PM TUC HPP -TUC-0(241)A T HOUGHTON RD: UPRR TO I-10 - WIDENING ROADWAY WIDENING FY 16
BP1J 0000 PM TUC HPP -TUC-0(201)A T HOUGHTON ROAD WIDENING @ UPRR ROAD WIDENING OVER RAILROAD BRIDGE FY 16
UK1K 0000 PN PPN STP -PPN-0(205)A T HUNT HIGHWAY - SYSTEM PRESERVATION - ENGINEERING FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 5 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
12915 CF1M 40 MO 74.0 IM - K HWY 141 JCT TO SILVER SPRINGS ROAD (WB) RR (5"TL, 3" PL) + AR-ACFC + SHOULDERS TBD FY 15
41608 TY1H 202L MA 0.0 E I-10 EAST/SANTAN TI TO 51ST AVE DESIGN ROADWAY TBD FY 14
40017 ES1M 202L MA 0.0 IM - E I-10 MARICOPA - 24TH ST, SEGMENT 1 CONSTRUCT NEW FREEWAY TBD FY 17
45414 ET1M 202L MA 0.0 IM - E I-10 PAPAGO/ SR202L SYSTEM INTERCHANGE SEGMEN DESIGN NEW SYSTEM TI DESIGN FY 14
MZ1H 303L MA 5.0 NH -303-A(ASO) E I-10, MC 85 TO I-10 NEW 303 EXTENSION SOUTH TBD FY 14
14915 ZA1J 191 CH 331.0 STP - S I-10/ US 191 TI AT MP 331 CONSTRUCT IMPROVEMENTS TBD FY 15
45213 NU1L 303L MA 0.0 E I-10/303L TI, PHASE I (I-10 REALIGNMENT) CONSTRUCT LANDSCAPE TBD FY 14
40616 EV1M 303L MA 103.2 IM -303-A(216)S E I-10/303L TI, PHASE II CONSTRUCT NEW FREEWAY TBD FY 16
44909 FM1H 10 MA 105.0 H683801X I -010-A-901 Y I-10/DESERT CREEK TI (PRIVATE FUNDS) CONSTRUCT TI IGA FY 14
40313 DD1J 101L MA 23.5 E I-17 TO TATUM BLVD CONSTRUCT HOV LANE DESIGN FY 13
10816 GQ1J 17 MA 216.0 IM - E I-17 @ PEORIA AND UNION HILLS DRAINAGE GRATE IMPROVEMENTS TBD FY 16
23913 ZC1L 999 SW 0.0 HSIP-999-A(377)S F I-17 AND I-40, INLAID PAVEMENT MARKERS, SEGMENT I INLAID PAVEMENT MARKINGS TBD FY 13
11416 MW1L 74 MA 30.0 H840301C STP - E I-17 AND LAKE PLEASANT PKWY CONSTRUCT DRAINAGE IMPROVEMENTS TBD FY 16
13914 CC1M 19 SC 9.0 STP - T I-19 FRONTAGE ROAD, NB DRAINAGE REPAIR TBD FY 14
12714 AZ1M 10 PM 268.0 IM -010-D(215)T T I-19 TO CRAYCROFT ROAD IN TUCSON SIGN REHABILITATION AUG 13
11716 DJ1M 87 NA 346.0 STP - H I-40 TO JCT SR 264 CBC EXTENSIONS TBD FY 16
QP1J 40 MO 66.5 IM -040-B(208)A K I-40, BLAKE RANCH RD TI IMPROVEMENTS TBD FY 13
15413 HJ1J 8 YU 7.2 HSIP- Y I-8 AND ARABY ROAD PE PH 1 AND 2 DESIGN FY 13
KJ1K 8 MA 117.0 H800001C Y I-8 TO GILLESPIE CANAL REMOVE 3", REPLACE 2.5" & ACFC TBD FY 14
CX1G 0000 PM MRN SB41301C BR-MRN-0(014)A T INA BRIDGE OVER SANTA CRUZ BRIDGE REPLACEMENT FY 13
10015 QL1J 10 PM 247.0 H758301C T INA RD TO RUTHRAUFF RD RECONSTRUCTION FOR WIDENING TBD FY 15
10208 PJ1F 10 PM 248.0 NH -010-D T INA ROAD TI RECONSTRUCT TI & MAINLINE TBD FY 16
12415 HW1L 17 MA 202.3 IM - E INDIAN SCHOOL ROAD - PEORIA AVENUE SIGN REHABILITATION TBD FY 15
13814 MT1L 19 SC 0.3 IM -019-A(216)A T INTERNATIONAL BORDER - JCT B-19 RR AR-ACFC JUN 13
10012 KM1K 95 YU 0.0 H800301C STP -095-A(204)A Y INTERNATIONAL BORDER - JUAN SANCHEZ BLVD INFRASTRUCTURE IMPROVEMENTS FEB 13
13714 MS1L 19B SC 0.1 STP -B19-A(201)A T INTERNATIONAL BORDER - MARIPOSA/SR189 RR 2" AC DEC 13
PI1K 0000 MA MES SS89101C CM -MES-0(217)A E ITS TRAFFIC SIGNAL CONVERSIONS - PHASE 5 FIBER-OPTIC COMMUNICATIONS NET FY 13
14313 SB1K 87 GI 236.2 H812301C P JCT 188 - RYE RR 3" TL & AR-ACFC FULL WIDTH MAY 13
20713 EF1M 266 GH 104.0 STP - S JCT 191 - BONITA CHIP SEAL & GR RENEWAL JUN 13
17714 QC1L 191 AP 477.9 STP -191-E(213)T H JCT N12 TO JCT US-160 REPLACE FENCE AND CATTLE GUARDS JUN 14
13613 SC1K 191 CH 38.2 HSIP- S JCT SR 181 - PEARCE ROAD 3" AC & AR-ACFC MAY 13
16314 DM1M 89 YV 349.0 STP - P JCT SR 260 (COTTONWOOD) CONSTRUCT DUAL RIGHT TURN LANES TBD FY 14
XT1H 180 AP 402.0 G JCT SR 260 / US 180 & RODEO GROUNDS INTERSECTIO REALIGN INTERSECTION TBD FY 13
11710 RJ1C 160 NA 375.2 H512001C NH -160-A(201)T H JCT SR 564 - TSEGI, PH I CONSTRUCT DUAL PASSING LANES FEB 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 6 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
13913 QE1K 387 PN 0.0 STP - T JCT SR 84 / SR 287 TO SANTA CRUZ RIVER BRIDGE RR 4" TL, 3" PL & FOG COAT JUN 13
16614 HO1L 89 CN 403.0 STP - F JCT SR 89A / PLAZA WAY (FLAGSTAFF) DRAINAGE IMPROVEMENTS TBD FY 14
10512 CZ1J 89 YV 319.0 H851801C P JCT SR 89A TO DEEPWELL RANCH ROAD WIDEN THE SR 89 CORRIDOR TBD FY 16
16315 UZ1J 89A CN 525.0 STP - F JCT US 89 - COLORADO RIVER EXTEND PIPES AND CULVERTS TBD FY 15
14515 FP1L 89 CN 525.0 NH - F JCT US 89A - BIG CUT EP (PIPE) DROP-OFF MITIGATION TBD FY 15
14415 SP1K 89 YV 258.3 STP - P JCT US 93 - JCT SR 71 RR 3" & AR-ACFC TBD FY 15
OD1K 0000 MO CLC SS87801C STP -CLC-0(201)A F JOHNSON AVENUE PAVEMENT PRESERVATION FY 13
14815 SG1K 180 AP 407.0 STP - G JUAN CARILLO - FH275 RR 3" AC & AR-ACFC TBD FY 15
ZN1E 0000 PN PPN SB41001C BR -PPN-0-(169) G KELVIN BRIDGE - #8441 BRIDGE REPLACEMENT FY 13
HY1L 66 MO 56.4 H809401X SB -AZ09(002) K KINGMAN POWERHOUSE VISITOR CENTER IMPROVEMENTS IGA FY 13
PU1K 0000 PM TUC SS86501C STP -TUC-0(233)A T KOLB ROAD CONNECTION TO SABINO CANYON ROADWAY AND SIDEWALK IMPROVEMENTS FY 14
YM1L 202L MA 9.0 H854301C E L101 TO MCDOWELL ROAD SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13
YL1L 202L MA 9.0 H854201C E L101 TO MESA DRIVE SYSTEM PRESERVATION (RESTORATION/REHAB/ JUN 13
HB1M 10 PN 209.9 H861401C IM -010-D(217)T T LA PALMA RD TO PICACHO HWY DESIGN PAVEMENTPRESERVATION PROJECT DESIGN FY 13
10511 XQ1L 95 MO 182.0 K LAKE HAVASU STATE PARK (CONTACT POINT) PH II DESIGN PARKING DESIGN FY 15
13315 JL1K 40 NA 284.3 BR -040-D(223)A H LEROUX WASH BRIDGE EB #1772 & WB #1773 BRIDGE REPAIR TBD FY 15
16114 VM1K 87 CN 323.9 BR -087-C(203)A H LIMESTONE WASH BRIDGE # BRIDGE REPLACEMENT JUL 13
43208 ST1H 202L MA 44.0 CM - E LINDSAY ROAD TO GILBERT ROAD DESIGN & CONST MULTI-USE PATH TBD FY 13
12216 LY1C 260 GI 258.0 NH - P LION SPRINGS SECTION RECONSTRUCT TO A 4-LANE DIVIDED TBD FY 16
CD1L 260 AP 394.0 H826901C G LITTLE COLORADO RIVER BR (STR # 416) SYSTEM PRESERVATION - MINOR BRIDGE REHA TBD FY 16
17913 LX1G 75 GE 384.0 075-A(200)T S LITTLE SANDS WASH BANK PROTECTION AUG 13
OC1K 0000 MA MES SS87701C CM -MES-0(216)A E LOCAL AGENCY WIDE - FIBER-OPTIC COMMUNICATION FIBER OPTICS FY 13
14310 QQ1K 40 AP 358.5 H LUPTON TI DCR AND ENVIRONMENTAL STUDIES DESIGN FY 14
16713 KW1L 40 NA 271.0 H837201C BR - H MANILA WASH BRIDGES STR #851,852 & 2080 SCOUR RETROFIT MAR 13
15115 DY1M 191 AP 462.5 STP -191-E(212)T H MANY FARMS - APACHE CO. RD 508 FENCING WIDENING JUN 14
11112 CO1J 10 PM 236.4 T MARANA ROAD TO CORTARO ROAD DESIGN (RECONSTRUCT & WIDEN FRONTAGE R DESIGN FY 15
45913 EO1M 101L MA 6.0 STAN- E MARYLAND AVENUE CONSTRUCT DIRECT HOV RAMP (DESIGN BUILD) FEB 13
OB1K 0000 MA MMA SS88101C STP -MMA-0(217)A E MCKELLIPS ROAD - SR101L TO ALMA SCHOOL ROADWAY RECONSTRUCTION FY 15
PG1K 0000 MA MMA SS89401C STP -MMA-0(225)A E MCKELLIPS ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 16
19313 DP1M 93 MO 125.0 NH -093-B(211)T K MEDLIN CROSSOVER DESIGN AND CONSTRUCT NEW CROSSOVER DESIGN FY 13
10717 FF1M 92 CH 351.0 STP - S MELODY LANE - NACO RD WIDEN TO 3 LANES TBD FY 17
40613 NM1L 60 MA 194.0 NH -060-C(207)T E MERIDIAN ROAD. HALF TI CONSTRUCT TI TBD FY 14
11915 BU1M 10 CH 296.0 IM - T MESCAL ROAD TO JCT SR 90 RR(5" TL, 3" PL) + AR-ACFC TBD FY 15
13313 RR1K 89 CN 476.6 H811601C STP -089-D(203)T F MOENKOPI WASH - HIDDEN SPRINGS 2.5" AC OVERLAY AND 1/2" AR-ACFC NOV 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 7 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
13003 FR1C 8 YU 55.9 H206001C IM - Y MOHAWK REST AREA CONSTRUCT REST AREA TBD FY 15
14814 RE1L 60 MA 115.5 BR -060-B(209)T P MONARCH WASH BR, STR #204 & 759 SCOUR RETROFIT DEC 13
15613 RH1L 17 MA 238.6 BR - P MOORES GULCH BRIDGE SB #339 DESIGN BRIDGE REPLACEMENT DESIGN FY 13
10114 DU1M 191 GH 101.0 STP - S MP 100.7 TO SR 266 DESIGN PARALLEL ROADWAY DESIGN FY 14
18413 DF1M 83 SC 12.0 H850101C T MP 12 - MP 14 MILL AND PAVE TBD FY 13
10517 DD1M 79 PN 122.5 STP - T MP 122.5 EXTEND PIPES AND CULVERTS TBD FY 16
17114 IP1K 93 MO 17.4 HSIP- K MP 17.4 - MP 58.4 PE PH 1 & 2 DESIGN FY 14
17713 CZ1M 68 MO 20.0 STP - K MP 19, TURN LANES DESIGN & CONSTRUCT 3 EB TURN LANES DESIGN FY 13
14914 CU1M 60 GI 229.4 HSIP- G MP 229.4 - MP 232.91 SHOULDER WIDENING TBD FY 14
16513 DH1M 87 CN 268.1 HSIP- P MP 268.1 - MP 278 PE PH 1 & 2 DESIGN FY 13
15813 BX1M 69 YV 281.1 HX24201C HSIP-069-A(210)T P MP 281.1 - MP 289.7 MODIFY SIGNALS JUN 13
OR1K 60 GI 290.0 H808301C 060-E(206)T G MP 290, 296 AND 320 AT HAGEN HILL ROCKFALL CONTAINMENT FEB 13
17013 QD1L 40 NA 298.0 IM - H MP 298 UTILITY OVERPASS DESIGN OF CBC EXTENSION JAN 15
13615 CW1M 60 GI 302.0 STP -060-E(214)T G MP 302 - 311 RR 3" AC + AR-ACFC TBD FY 15
11715 BA1M 10 LA 42.0 IM - Y MP 42 TO HOVATTER ROAD RR(4" TL, 3" PL) + AR-ACFC TBD FY 15
11916 KZ1K 180 CN 216.1 STP - F NAVAJO RD - FLAGSTAFF CITY LIMITS WIDENING, C&G & DRAINAGE IMPROVEMENTS TBD FY 16
14015 YZ1L 77 GI 156.8 G NEAR SUMMIT ROCKFALL MITIGATION TBD FY 15
12315 BW1M 15 MO 0.0 IM - F NEVADA STATE LINE - MP 13 RR(4" TL, 3" PL) AR-ACFC TBD FY 15
13514 CF1L 17 MA 231.0 H826801C E NEW RIVER BRIDGES, STR # 1290 &1291 SCOUR RETROFIT JAN 14
15614 UB1J 77 AP 362.1 STP -077-B(208)A H NORTH SNOWFLAKE BOX CULVERT EXTENSION TBD FY 14
16414 IS1J 89 CN 385.1 H741801C A89-B(204)A F OAK CREEK CANYON CREEK BANK PROTECTION TBD FY 14
11008 EX1F 60 PN 230.0 STP -060-D(211)A G OAK FLAT - MIAMI CONSTRUCT PASSING/CLIMBING LANE FEB 14
BB1L 0000 MA MMA SS83001C CM -MMA-0(214)A E OLIVE AVE: LITCHFIELD ROAD TO LOOP 101 INSTALL FIBER OPTIC CONDUIT FY 13
10311 CY1J 77 PN 100.0 H739101C T ORACLE STATE PARK CONSTRUCT PARKING TBD FY 14
16814 HG1L 89 CN 551.0 NH - F PAGE MAINTENANCE YARD WIDENING FOR TURN LANES TBD FY 14
11116 YF1K 40 SW 235.0 H821401C STP - H PAINTED CLIFFS & METEOR CRATER REST AREAS SYSTEM PRESERVATION - RESTORATION/REHAB TBD FY 16
12715 SU1K 19 SC 16.0 IM - T PALO PARADO - CHAVEZ SLIDING TI RR (4" TL, 3" PL) + FR TBD FY 15
WU1J 0000 PM TUC SS73001C STP -TUC-0(226)A T PANTANO BOULEVARD PAVEMENT RECONSTRUCTION FY 13
15214 DR1M 169 MA 4.0 STP -169-A(205)S P PASSING LANES CONSTRUCT TURN AND PASSING LANES TBD FY 14
HZ1L 0000 MA SCT SS96701C E PAVEMENT PRESERVATION PHASE 3 PAVEMENT PRESERVATION FY 13
45112 WB1L 303L MA 112.0 E PEORIA AVE - WADDELL RD LANDSCAPE CONSTRUCTION JUN 13
JE1L 89 YV 328.0 H833001C P PERKINSVILLE RD ROUNDABOUT SYSTEM ENHANCEMENT - ENGINEERING DESIGN FY 13
40913 CM1J 10 MA 122.0 H770901C NH - E PERRYVILLE ROAD TI CONSTRUCT TI APR 13
15913 WC1L 74 MA 22.4 STP -074-A(204)T E PICACHO WASH TRAIL TO JCT I-17 RR(5" TL, 3" PL) + AR ACFC SEP 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 8 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
14513 PA1K 260 NA 310.0 H801201C NH -260-B(209)A G PIERCE WASH BRIDGE (STR # 1373) SCOUR RETROFIT JAN 13
80899 S9SP 101L MA 73.0 H387501C RARF-101-B E PIMA ROAD EXTENSION, JPA CONSTRUCT ROADWAY IGA FY 14
12713 RQ1K 40 CN 158.6 F PINE SPRINGS - WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC TBD FY 13
19214 HM1L 77 PN 105.4 H826701C HSIP- T POWER LINE - SAN MANUEL ROAD DESIGN SHOULDER WIDENING DESIGN FY 14
12716 FG1M 202L MA 0.0 NH - E PUMP STATION FLOOD EROSION CONTROL TBD FY 16
16514 SE1K 89A CN 386.6 STP -A89-B(210)A F PUMPHOUSE WASH - OVERLOOK RR (3"AC, 2.5" AC + AR-ACFC) FULL WIDTH DEC 13
14114 SM1K 40 MO 57.0 IM -040-B(213)A K RATTLESNAKE WASH - JCT US 93 RR(5" TL, 3" PL) & AR-ACFC TBD FY 14
13016 TL1L 101L MA 50.7 NH - E RED MOUNTAIN - CHANDLER BLVD SIGN REHABILITATION TBD FY 16
15208 NSSP 89A YV 365.0 F RED ROCK STATE PARK DESIGN DESIGN FY 13
12016 IS1L 191 GH 120.3 STP - S RELATION ST TO JCT US70 INTERSECTION IMPROVEMENT TBD FY 16
KQ1H 0000 MA MMA STP -QCR-0(001)A E RIGGS RD,ELLSWORTH TO MERIDIAN CONSTRUCT NEW ROADWAY FY 13
GP1M 191 AP 247.8 191-C(216)A G RIGHT OF WAY FENCE IN BOTH DIRECTIONS RIGHT OF WAY FENCING DESIGN FY 13
GO1M 260 AP 385.5 260-C(205)A G RIGHT OF WAY FENCING TWO LOCATIONS EAST BOUN RIGHT OF WAY FENCING DESIGN FY 13
20613 MQ1L 260 NA 282.5 HSIP- P RIM RD TO GIBSON RD, SEGMENTS 1, 2 & 3 SHOULDER WIDENING PROGRAM, PE PH 1 & 2 DESIGN FY 13
19414 HS1L 89 YV 330.0 H827801C P ROAD 4 NORTH CONSTRUCT ROUNDABOUT APR 14
11414 CU1J 17 YV 232.0 P ROCK SPRINGS TO CORDES JUNCTION PE PH2 (WIDEN ROADWAY) DESIGN FY 14
20213 OT1F 188 GI 254.0 STP - G ROOSEVELT - JAKES CORNER INSTALL DRAINAGE FACILITY CBC TBD FY 13
18514 EG1M 288 GI 260 STP - G ROOSEVELT - YOUNG CBC EXTENSION OCT 13
17814 SK1K 191 AP 482.0 H813201C STP - H ROUND ROCK - JCT. US 160 3" AC & AR-ACFC FEB 14
14514 EE1K 40 NA 254.6 IM -040-D(213)A H RUBY WASH BRIDGE - E WINSLOW TI OP BRIDGE REHABILITATION JUL 13
22413 YC1L 64 CN 0.0 H817202C FA - F RURAL INTELLIGENT TRANSPORTATION SYSTEMS - PH CONSTRUCT FEB 13
10015 VH1L 10 PM 252.0 NH - T RUTHRAFF ROAD TI RECONSTRUCTION FOR WIDENING TBD FY 15
ZP1K 0000 YU YYU SS86101C STP - Y S. FRONTAGE ROAD - AVENUE 9E TO AVENUE13E PAVEMENT PRESERVATION FY 13
15615 YC1K 999 SW 0.0 H821301C STP - T SACATON & CANOA RANCH REST AREAS WATER/WASTEWATER, STRUC & ELECTICAL RE TBD FY 15
40415 UF1H 202L MA 0.0 RARF- E SALT RIVER - BUCKEYE ROAD SEGMENT 8 CONSTRUCT NEW FREEWAY TBD FY 17
41115 WW1K 202L MA 0.0 E SALT RIVER BRIDGE, SEGMENT 7 CONSTRUCT NEW FREEWAY TBD FY 16
15014 BT1L 60 GI 292.0 H826201C 060-E(207)A G SALT RIVER CANYON REST AREA REPLACE COMPOSTING TOILETS & STRUCTURA DEC 13
BX1L 0000 MA TMP SS95301C CM -TMP-0(217)A E SALT RIVER MUP: I-10/TEMPE DRAIN TO PRIEST DRIVE PATHWAY IMPROVEMENTS FY 13
ZS1J 0000 MA PHX CM -PHX-0(223)A E SALT RIVER PATHWAY - 24TH ST TO I-10 TEMPE DRAIN PATHWAY IMPROVEMENTS FY 13
14615 JR1L 92 CH 340.5 BR -092-A(203)A S SAN PEDRO RIVER BRIDGE #449 BRIDGE REPLACEMENT TBD FY 15
12015 WD1L 10 CH 306.7 IM -010-F(219)A S SAN PEDRO RIVER BRIDGE EB #1530 & WB #1531 DECK REPLACEMENT & SCOUR RETROFIT TBD FY 15
10716 BV1M 10 CH 383.0 IM - S SAN SIMON PORT OF ENTRY PE PH 1 & 2 DESIGN FY 16
12215 YI1K 10 CH 388.0 H821601C IM - S SAN SIMON REST AREA NEW WELL,WATER PUMPS,STRUC,ELECT,MECH TBD FY 15
15513 KV1L 10 CH 381.0 H837101C BR - S SAN SIMON RIVER BR (STR #1167,1168 & 230) SCOUR RETROFIT MAR 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 9 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
WQ1L 19 PM 59.0 H771401C T SAN XAVIER PEDESTRIAN BRIDGE PEDESTRIAN BRIDGE IMPROVEMENTS NOV 13
12116 DW1M 191 AP 345.0 STP - H SANDERS - WITCH WELLS FENCING & CATTLE GUARDS TBD FY 16
23701 ZY1D 40 AP 340.0 H552601C 040-E(001) H SANDERS PORT OF ENTRY RECONSTRUCT POE TBD FY 15
11914 CG1L 8 PN 163.0 H827001C T SANTA ROSA WASH BRIDGES, STR # 1092 & 1093 SCOUR RETROFIT MAR 14
10117 BY1M 15 MO 0.0 F SCENIC TO STATE LINE PE PH 1 & 2 DESIGN FY 13
GQ1M 180 AP 403.5 180-C(201)A G SEVERAL LOCATIONS ON US180 SYSTEM PRESERVATION - ENGINEERING DESIGN FY 13
43414 WY1K 101L MA 41.0 H848401C E SHEA BLVD TO CHAPARRAL ROAD CONSTRUCT GPL MAR 14
10612 QP1C 60 NA 342.0 H510701C G SHOW LOW TO LITTLE MORMON LAKE WIDEN ROADWAY JUL 14
10313 GS1H 60 PN 222.0 STP -060-D(208)A G SILVER KING SECTION & SUPERIOR STREETS RECONSTRUCT TO 4 LANE RDWY W/CNT TURN L TBD FY 15
QM1L 0000 CN FLA SZ01901C STP -FLA-0(213)D F SITGREAVES ST, MILTON TO SANTE FE CONSTRUCTION OF ADA RAMPS FY 13
40115 WU1K 10 MA 0.0 E SKY HARBOR WEST AIRPORT ACCESS CONSTRUCT ACCESS RAMPS TBD FY 15
16615 XT1K 87 GI 226.0 H820701C NH - P SLATE CREEK ROAD REPAIR TBD FY 15
XZ1K 0000 YU SOM Y SOMERTON CANAL MUP:US95 TO COUNTY 17TH STRE SYSTEM ENHANCEMENT - ENGINEERING FY 14
13515 CQ1M 60 MA 189.0 STP - E SOSSAMAN - MERIDIAN DRAINAGE IMPROVEMENTS TBD FY 15
11515 QQ1H 89 CN 452.6 H705601C NH - F SOUTH OF GRAY MOUNTAIN PASSING LANES (NB AND SB) TBD FY 15
16215 DL1M 89A YV 343.0 STP - P SOUTH OF JEROME ROCKFALL MITIGATION TBD FY 15
12815 CE1M 40F MO 47.8 IM -999-A(398)T K SOUTH OF KINGMAN ROCKFALL MITIGATION TBD FY 15
10916 CB1M 17 YV 292.0 IM - P SOUTH OF MCGUIREVILLE ROCKFALL MITIGATION TBD FY 16
FK1M 93 YV 185.3 093-B(210)T P SOUTH OF SR71 - NORTH OF SR89 DESIGN ROADWAY WIDENING DESIGN FY 13
12316 EH1M 288 GI 289.0 STP - G SOUTH OF YOUNG ROCKFALL MITIGATION TBD FY 16
UU1K 0000 PM TUC T SPEEDWAY BLVD UNDERPASS @ UPRR ROADWAY RECONSTRUCTION FY 13
41213 YR1K 202L MA 9.0 RARF- E SR 101 TO GILBERT ROAD DESIGN GENERAL PURPOSE LANES DESIGN FY 14
45313 TR1H 17 MA 215.0 H844501C CM -017-A(230)A E SR 101L (AGUA FRIA) TO ANTHEM WAY CONSTRUCT FMS MAY 13
OP1L 101L MA 23.0 E SR 101L PIMA (I-17-PRINCESS DR) GP LANES DCR/ED CAPACITY ADDITIONS - ENGINEERING TBD FY 14
41814 WX1K 60 MA 148.9 E SR 101L, AGUA FRIA TO VAN BUREN STREET, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 14
12615 CA1M 17 YV 279.6 IM - P SR 169 TO MIDDLE VERDE ROAD RR(5" TL, 3" PL) + AR-ACFC TBD FY 15
LL1L 999 CH 0.0 H832801C STP -999-A(328)T S SR 186 & B-10, COCHISE COUNTY WIDE PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13
12407 FX1C 10 MA 161.2 H505101C E SR 202L (SANTAN) TO RIGGS ROAD CONST HOV & GEN PURPOSE LANE TBD FY 15
16715 EA1M 260 YV 220.0 STP - P SR 260 AT INDUSTRIAL DRIVE IN CAMP VERDE ROUNDABOUT DEC 14
BK1M 260 YV 218.9 P SR 260; INDUSTRIAL DR - HOMESTEAD PKWY DESIGN DESIGN FY 13
10114 MG1E 191 GH 100.7 S SR 266 TO ARTESIA DESIGN PARALLEL ROADWAY DESIGN FY 14
16512 DV1M 191 GH 104.0 STP - S SR 266 TO US 70 (REALIGNMENT) SCOPING DESIGN FY 13
15515 JC1H 286 PM 20.0 H690701C STP - T SR 286 (SASABE - ROBLES RANCH HWY) REPAIR HEADCUTTING PROBLEMS AT LW WATE TBD FY 15
43016 JJ1H 60 MA 139.0 HES -060-B(ATZ) E SR 303L TO SR 101L, AGUA FRIA, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 16
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 10 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
JG1H 801 MA 0.0 E SR 303L TO SR 202L STUDY TBD FY 14
IZ1K 303L MA 3.8 E SR 303L, RIGGS RD - SR 801 SYSTEM ENHANCEMENT-ENGINEERING TBD FY 14
YH1H 801 MA 0.0 E SR 801, SR 85 TO SR 303L NEW ROADWAY CONSTRUCTION TBD FY 14
12113 IP1L 10 MA 112.8 IM -010-A(216)A E SR 85 - VERRADO (EB) RR(4"TL, 3" PL) & AR-ACFC FEB 14
12214 VX1J 10 MA 105.0 H775001C IM - E SR 85 TO DYSART (VERRADO WAY TO 85) SIGN REHABILITATION JUL 13
14013 RO1K 587 PN 218.8 H811301C E SR 87 - JCT I-10 RR 3" & AR-ACFC MAY 13
GG1M 87 GI 252.0 087-B(218)A P SR 87 / SR 260 SAFETY IMPROVEMENT ACCESS CONTROL, SIGNING UPGRADES, ADA, M DESIGN FY 13
17610 SX1J 10 PN 208.8 H769601C STP -010-D(205)A T SR 87 TI TO TOWN OF PICACHO CAPACITY ADDITIONS - ENGINEERING TBD FY 13
25113 FS1M 89 YV 327.0 STP -089-B(213)T P SR 89 @ ROAD 1 NORTH IN CHINO VALLEY DESIGN DESIGN FY 13
10810 IV1A 89A CN 399.0 H413401C STP -A89-B(009)A F SR 89A JW POWELL BLVD CONSTRUCT INTERSECTION IMPROVEMENTS JUN 13
16914 VY1L 90 CH 321.0 H849701C HSIP-090-A(205)A S SR 92 - GIULIO CESARE AVENUE LIGHTING MAR 14
17014 HL1L 92 CH 322.1 H826501C HSIP- S SR 92 @ FOOTHILLS DR INTERSECTION IMPROVEMENTS JAN 14
HH1M 95 MO 239.0 095-D(208)T K SR 95 @ VALENCIA ROAD DESIGN DESIGN FY 13
19413 WY1L 95 LA 142.0 NH - Y SR 95 AT MOHAVE ROAD PE PH 1 & 2 DESIGN FY 13
VX1L 101L MA 46.0 E SR101L, CHAPARRAL ROAD TO SR202L GP LANES DESIGN FY 13
10412 DA1J 89 CN 464.5 H791501C NH -089-D(201)T F SR-64 TO LITTLE COLORADO RIVER CONSTRUCT 4-LANE URBAN, SR64 INTERSECTIO JAN 13
14115 GP1G 82 SC 40.5 STP - T SR-82 AT MP 40.6 EXTEND CBC & ELIMINATE GUARDRAIL TBD FY 15
15914 GR1G 82 SC 36.5 STP - T SR-82, MP 36.5 - 36.9 EXTEND 2 CBC'S AND ELIMINATE GUARDRAIL TBD FY 14
FO1M 87 MA 177.8 087-B(220)T E SR87 @ MCDOWELL RD DESIGN SIGNAL IMPROVEMENT DESIGN FY 13
19314 NC1H 88 MA 203.4 H700501C HSIP- E SR88, APACHE TRAIL GOLDFIELD TO CANYON LAKE SPOT SAFETY IMPROVEMENTS JUN 14
SL1L 95 MO 239.5 095-D(204)T K STATE ROUTE 95 @ STERLING RD DESIGN INTERSECTION IMPROVEMENT DESIGN FY 13
12914 EI1M 999 SW 0.0 HSIP- X STATEWIDE GUARDRAIL DELINEATORS TBD FY 14
16115 XX1L 999 SW 0.0 FA -999-A(383)T E STATEWIDE DYNAMIC MESSAGE SIGN PHASE 10 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 15
10917 EJ1M 999 SW 0.0 FA - X STATEWIDE DYNAMIC MESSAGE SIGN PHASE 11 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 17
21513 XV1K 999 SW 0.0 H820601C HSIP- E STATEWIDE TREE THINNING TREE REMOVAL FROM CLEAR ZONE, PE PH 1 & 2 DESIGN FY 13
13415 CN1M 40 NA 297.0 IM - H SUN VALLEY ROAD - WASHBOARD ROAD RR (5" TL, 3" PL) + 2"AC + FC JAN 15
YJ1L 69 YV 292.1 H854001C NH -069-A(211)T P SUNRISE BLVD TO PRESCOTT CANYON DR PAVEMENT PRESERVATION (AR-ACFC) MAR 13
16214 JD1L 88 PN 196.0 H830801C HSIP- E SUPERSTITION BLVD CONSTRUCT ROUNDABOUT JUN 14
11413 AY1G 77 PM 82.0 H669401C 077-A(204)T T TANGERINE RD TO PINAL COUNTY LINE WIDENING TO 6 LANES - CONSTRUCTION JUN 13
12115 YB1K 10 CH 320.5 H821101C IM - S TEXAS CANYON REST AREA WATER, STRUCTURAL, MECHANICAL & ELECTRI TBD FY 15
GA1L 0000 NA WIN SL71101C TEA -WIN-0(203)A H THE STATION AT LA POSADA REHAB OF STATION AND LANDSCAPE FY 14
44913 OE1L 303L MA 105.0 H850401C RARF- E THOMAS ROAD TO CAMELBACK ROAD CONSTRUCT LANDSCAPE TBD FY 14
17914 DZ1M 260 YV 211.2 STP - P THOUSAND TRAILS ROAD NEW TAPERS TO STANDARD TBD FY 14
10616 XD1K 260 YV 218.5 STP - P THOUSAND TRAILS TO I-17 CONSTRUCT INTERIM IMPROVEMENTS TBD FY 16
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 11 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
18213 DE1M 80 CH 317.0 STP - S TOMBSTONE REMOVE PEDESTRIAN BRIDGE TBD FY 13
15714 WH1K 80 CH 316.5 H800402C HSIP- S TOMBSTONE, MP 316.5 TO MP 318.0 LIGHTING AND SIDEWALKS MAR 15
17314 FN1L 160 CN 343.4 NH -160-A(203)A F TONALEA INSTALL INTERSECTION LIGHTING TBD FY 14
VK1J 0000 GI GGI HPP -GGI-0(204)A G TONTO CREEK BRIDGE DESIGN BRIDGE APPROACHES FY 13
13409 TQ1H 87 GI 263.0 H718301C P TONTO NATURAL BRIDGE STATE PARK CONSTRUCT NEW ROAD TBD FY 13
GU1M 86 PM 114.7 086-A(211)T T TOWN OF SELLS PEDESTRIAN BRIDGES CONSTRUCT PEDESTRIAN BRIDGE TBD FY 15
14215 KI1L 86 PM 115.8 T TOWN OF SELLS TO FRESNAL WIDEN SHOULDERS AND CULVERT EXTENSIONS TBD FY 15
XY1K 0000 MA QCR SS87601C CM -QCR-0(207)A E TOWNWIDE - ITS DEVELOPMENT SYSTEM ENHANCEMENT - TRAFFIC MGMT AND E FY 13
PK1K 0000 MA GDY SS89601C CM -GDY-0(203)A E TRAFFIC SIGNAL SYSTEM ITS BACKBONE & COMMUNICATION FY 13
14214 CJ1M 40 CN 185.0 IM - F TRANSWESTERN - LEUPP JCT PE PH 1 & 2 DESIGN FY 14
EP1K 0000 PM TUC SS73601C TUC-0(227)A T TUCSON BOULEVARD MULTI-USE PATH MULTI-USE PATH FY 13
11016 KH1L 40 CN 218.7 IM - F TWIN ARROWS TI, EB OFF-RAMP RAMP REMOVAL, RECONSTR & ACCESS CTRL M TBD FY 16
WK1L 940 MA 0.0 SR19101C STP -000-6(171)T E UNIVERSITY DR (TEMPE) 741-561J AT-GRADE RAILROAD CROSSING DESIGN AUG 13
JN1L 0000 MA MMA SS97201C E UPGRADE RADS REGIONWIDE SYSTEM UPGRADE FY 13
13214 RC1L 10 CH 333.0 IM -010-F(218)A S US 191 TO EAST WILLCOX TI RR (5" TL, 3" PL) & AR-ACFC JAN 14
18314 HR1L 264 AP 441.1 H824601C HSIP- H US 191 TO SAWMILL ROAD SEGMENT 1 SHOULDER WIDENING PROGRAM PE PH 1 & PH 2 DESIGN FY 14
QJ1L 60 NA 341.0 HX23901C G US 60 & 9TH PLACE, SHOW LOW TRAFFIC SIGNAL FEB 14
UV1L 60 MA 144.0 E US 60 / BELL ROAD TI DCR AND ENVIRONMENTAL ASSESSMENT TBD FY 14
IN1M 60 MA 109.9 060-A(207)S P US 60 @ APACHE STREET IN WICKENBURG DESIGN DESIGN FY 13
43015 EW1M 303L MA 0.0 RARF- E US 60 GRAND AVE / SR 303L TI, INTERIM LANDSCAPE CONSTRUCTION TBD FY 15
43914 XE1K 303L MA 118.0 H814501C E US 60 GRAND AVE / SR 303L TI, INTERIM CONSTRUCT INTERIM TI DEC 12
KK1L 93 MO 139.0 HPP -093-B(209) K US 93, SB BURRO CREEK BRIDGE SYSTEM PRESERVATION - ENGINEERING TBD FY 14
HS1K 0000 YU 0.0 SL64401C TEA -SOM-0(200)A Y US 96 BETWEEN SOMERTON AND BINGHAM AVENUES SYSTEM ENHANCEMENT-OTHER ENHANCEMENT FY 14
GA1M 191 GE 226 H843901C G US-191, GLOBE DISTRICT, WALLOW FIRE, SIGN REPAIR SYSTEM PRESERVATION (RESTORATION/REHAB/ DESIGN FY 13
NL1L 60 MA 143.0 E US60/THUNDEBIRD ROAD INTERSECTION RECONSTRUCT TI TBD FY 14
MO1K 95 YU 0.6 H801701C Y US95, 'A' ST TO JUAN SANCHEZ BLVD, SAN LUIS ROAD & PEDESTRIAN ENHANCEMENTS FEB 13
41215 XC1K 202L MA 43.0 CM - E VAL VISTA DR. - DOBSON RD CONSTRUCT FMS TBD FY 15
11508 AZ1G 86 PM 159.5 H680601C STP -086-A(210)T T VALENCIA RD - KINNEY RD CONSTRUCT ROADWAY WIDENING TO 4 LANES TBD FY 14
JM1L 0000 PM PPM SS97501C T VALENCIA ROAD: WADE RD TO MARK RD WIDEN ROADWAY FY 13
20513 EB1M 260 GI 262.0 NH - P VARIOUS BRIDGE APPROACHES REPAIR BRIDGE APPROACHES TBD FY 13
13915 RW1L 75 GE 387.0 BR - S VARIOUS BRIDGES (STR #S 861,202,242,983,243,251) SCOUR RETROFIT DEC 14
15815 QH1L 999 MA 0.0 STP - E VARIOUS LOCATIONS DRAINAGE TUNNEL IMPROVEMENTS TBD FY 15
22013 VX1K 999 MA 0.0 NH -999-A(215)T E VARIOUS LOCATIONS ON SR 101L AND I-17 PUMP STATION IMPROVEMENTS JAN 13
HP1L 0000 MA TMP SS96401C E VARIOUS LOCATIONS:WIRELESS COMMUNICATIONS & PROCUREMENT AND INSTALLATION FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
1ST SORT: PROJECT NAME Page 12 of 12
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
HT1M 17 YV 287.0 017-B( )T P VERDE RIVER BRIDGE NB #1731 DESIGN BRIDGE REHABILITATION DESIGN FY 13
ZE1L 17 YV 287.0 017-B(224)S P VERDE RIVER BRIDGES NB & SB #1731 & #505 DESIGN DEC 15
24013 BH1M 15 MO 15.0 H857401C 015-A(208)S F VIRGIN RIVER BRIDGE #6 (STR #1619) CMAR BRIDGE REHABILITATION CONSTRUCTION TBD FY 13
45212 OF1L 303L MA 114.0 RARF- E WADDELL ROAD TO MOUNTAIN VEIW ROAD CONSTRUCT LANDSCAPE JUN 13
14314 SD1K 40 CN 204.0 IM - F WALNUT CANYON - TWIN ARROWS RR 3" & 2" AC & AR-ACFC DEC 13
44811 ZN1J 85 MA 153.2 H800601C NH - E WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE TBD FY 14
HU1M 66 CN 91.0 066-A( )T K WASH BR #141 & TRUXTON WASH BR #142 DESIGN BRIDGE REHABILITATION DESIGN FY 13
11614 BM1M 8 YU 1.0 IM - Y WB OFF RAMP & GISS PARKWAY INTERSECTION INTERSECTION IMPROVEMENTS JUN 14
12513 IG1K 40 YV 132.1 H785701C K WEIGH STATION TO ASH FORK (WB) RR (5" TL, 3" PL) + FR FEB 13
NK1L 85 PM 42.0 T WELCOME ST. TO MP 42.5 SYSTEM PRESERVATION - ENGINEERING TBD FY 14
11216 CV1M 60 PN 232.0 STP - G WEST OF PINTO CREEK BRIDGE ROCKFALL MITIGATION TBD FY 16
11615 XP1L 10 LA 17.5 IM - Y WEST QUARTZSITE TI INTERSECTION IMPROVEMENTS TBD FY 15
JO1L 0000 MA MMA SS97301C E WEST VALLEY DMS INSTALL ARTERIAL DMS FY 13
ZI1L 80 CH 364.0 S WHITE WATER DRAW BRIDGE #1626 DESIGN DEC 15
13113 FF1G 73 NA 342.3 STP - G WHITERIVER TO COAL MINE CANYON 2" AC + FR FEB 14
ZV1L 0000 YU SLS CBI -SLS-0(201)A Y WIDENING AVE E FROM COUNTY 25TH STREET TO SR1 SYSTEM ENHANCEMENT (ENGINEERING) FY 14
12514 BT1M 10 MA 164.0 IM - E WILD HORSE PASS - RIGGS RR(5" TL - 3" PL) + AR-ACFC TBD FY 14
12414 FY1L 10 MA 162.0 IM -010-C(204)T E WILD HORSE PASS TO SR 347 (QUEEN CREEK ROAD) ROADWAY WIDENING TBD FY 14
17614 ST1K 186 CH 328.2 STP -186-A(200)A S WILLCOX TO KANSAS SETTLEMENT R & R 3" AC & CHIP SEAL APR 14
HV1M 40 MO 83.0 040-B(220)T K WILLOW CREEK BRIDGE NO 2 EB (#1593) DESIGN BRIDGE REHABILITATION DESIGN FY 13
13015 CI1M 40 MO 87.0 IM -040-B(217)T K WILLOW RANCH ROAD TO MP 92, EB RR (5" TL, 3" PL) + AR-ACFC WITH SHOULDERS E TBD FY 15
10417 CH1M 40 MO 83.0 IM - K WILLOW SPRINGS ROCKFALL MITIGATION TBD FY 17
11514 QN1C 40 AP 357.5 NH - H WINDOW ROCK TI PE PH 1 DESIGN FY 14
19514 DT1M 188 GI 240.0 STP - G WINDY HILL INSTALL DRAINAGE FACILITY CBC SEP 13
10017 XT1L 8 YU 0.0 IM - Y YUMA PORT OF ENTRY PE PH2 DESIGN FY 17
ZQ1F 0000 MA GDY SS54401C STP-GDY-0(008)A E YUMA RD @ BULLARD WASH CONST BOX CULVERTS FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 1 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
XZ1K 0000 YU SOM Y SOMERTON CANAL MUP:US95 TO COUNTY 17TH STRE SYSTEM ENHANCEMENT - ENGINEERING FY 14
JM1L 0000 PM PPM SS97501C T VALENCIA ROAD: WADE RD TO MARK RD WIDEN ROADWAY FY 13
OP1L 101L MA 23.0 E SR 101L PIMA (I-17-PRINCESS DR) GP LANES DCR/ED CAPACITY ADDITIONS - ENGINEERING TBD FY 14
NL1L 60 MA 143.0 E US60/THUNDEBIRD ROAD INTERSECTION RECONSTRUCT TI TBD FY 14
41814 WX1K 60 MA 148.9 E SR 101L, AGUA FRIA TO VAN BUREN STREET, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 14
43414 WY1K 101L MA 41.0 H848401C E SHEA BLVD TO CHAPARRAL ROAD CONSTRUCT GPL MAR 14
14413 RU1K 160 NA 358.1 H811901C F COUNTY LINE - BLACK MESA RR 3" & AR-ACFC FEB 13
14310 QQ1K 40 AP 358.5 H LUPTON TI DCR AND ENVIRONMENTAL STUDIES DESIGN FY 14
NK1L 85 PM 42.0 T WELCOME ST. TO MP 42.5 SYSTEM PRESERVATION - ENGINEERING TBD FY 14
YM1L 202L MA 9.0 H854301C E L101 TO MCDOWELL ROAD SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13
YQ1L 70 GH 347.0 H853801C S HAEKEL RD TO US 191 SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13
11112 CO1J 10 PM 236.4 T MARANA ROAD TO CORTARO ROAD DESIGN (RECONSTRUCT & WIDEN FRONTAGE R DESIGN FY 15
16006 QT1F 101L MA 53.5 E BALBOA DRIVE CONSTRUCT MULTI-USE PATH BRIDGE OVER TH IGA FY 15
16515 ZA1L 60 PN 228.8 G EAST OF QUEEN CREEK TUNNEL ROCKFALL MITIGATION TBD FY 15
UV1L 60 MA 144.0 E US 60 / BELL ROAD TI DCR AND ENVIRONMENTAL ASSESSMENT TBD FY 14
12513 IG1K 40 YV 132.1 H785701C K WEIGH STATION TO ASH FORK (WB) RR (5" TL, 3" PL) + FR FEB 13
UU1K 0000 PM TUC T SPEEDWAY BLVD UNDERPASS @ UPRR ROADWAY RECONSTRUCTION FY 13
JE1L 89 YV 328.0 H833001C P PERKINSVILLE RD ROUNDABOUT SYSTEM ENHANCEMENT - ENGINEERING DESIGN FY 13
10512 CZ1J 89 YV 319.0 H851801C P JCT SR 89A TO DEEPWELL RANCH ROAD WIDEN THE SR 89 CORRIDOR TBD FY 16
JO1L 0000 MA MMA SS97301C E WEST VALLEY DMS INSTALL ARTERIAL DMS FY 13
XT1H 180 AP 402.0 G JCT SR 260 / US 180 & RODEO GROUNDS INTERSECTIO REALIGN INTERSECTION TBD FY 13
13209 A6SP 87 NA 346.0 H717901C H HOMOLOVI RUINS STATE PARK CONSTRUCT ROAD TBD FY 14
10311 CY1J 77 PN 100.0 H739101C T ORACLE STATE PARK CONSTRUCT PARKING TBD FY 14
HZ1L 0000 MA SCT SS96701C E PAVEMENT PRESERVATION PHASE 3 PAVEMENT PRESERVATION FY 13
JP1L 0000 MA MMA SS97401C E ATIS ENHANCEMENTS REGIONWIDE ARTERIAL ATIS FY 13
14015 YZ1L 77 GI 156.8 G NEAR SUMMIT ROCKFALL MITIGATION TBD FY 15
XX1K 0000 MA CHN SS93201C E CONSOLIDATED CANAL MULTI-USE PATH PATHWAY/TRAIN IMPROVEMENTS FY 13
MO1K 95 YU 0.6 H801701C Y US95, 'A' ST TO JUAN SANCHEZ BLVD, SAN LUIS ROAD & PEDESTRIAN ENHANCEMENTS FEB 13
12413 RW1K 17 YV 245.0 H812101C P BLACK CANYON HILL (NB) RR (5" TL, 3" PL) & AR-ACFC APR 13
10112 JW1K 10 PN 186.7 T EARLEY ROAD TO JCT I-8 ROAD WIDENING TBD FY 16
JG1H 801 MA 0.0 E SR 303L TO SR 202L STUDY TBD FY 14
YH1H 801 MA 0.0 E SR 801, SR 85 TO SR 303L NEW ROADWAY CONSTRUCTION TBD FY 14
10612 QP1C 60 NA 342.0 H510701C G SHOW LOW TO LITTLE MORMON LAKE WIDEN ROADWAY JUL 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 2 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
13413 RS1K 89A CN 609.3 F FREDONIA - STATE LINE RR 3" & AR-ACFC TBD FY 13
12713 RQ1K 40 CN 158.6 F PINE SPRINGS - WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC TBD FY 13
12613 RP1K 40 YV 146.2 F EAST ASHFORK TI - COUNTY LINE RR 3" & 2" AC & AR-ACFC TBD FY 13
JN1M 89 YV 345.7 H863601C K HELL CANYON BRIDGE DECK REHABILITATION TBD FY 13
12913 RX1K 69 YV 271.6 H812201C P BIG BUG 4 TO POLAND JCT RR 3" TL, RR AR-ACFC FULL WIDTH MAR 13
23213 BM1L 64 CN 234.5 H825801C F GRAND CANYON AIRPORT- FS RD 328 SHOULDER WIDENING TBD FY 15
11414 CU1J 17 YV 232.0 P ROCK SPRINGS TO CORDES JUNCTION PE PH2 (WIDEN ROADWAY) DESIGN FY 14
VX1L 101L MA 46.0 E SR101L, CHAPARRAL ROAD TO SR202L GP LANES DESIGN FY 13
HC1J 10 LA 1.0 Y EHRENBERG EXIT 1 ROUNDABOUT JUN 13
HP1L 0000 MA TMP SS96401C E VARIOUS LOCATIONS:WIRELESS COMMUNICATIONS & PROCUREMENT AND INSTALLATION FY 13
KJ1K 8 MA 117.0 H800001C Y I-8 TO GILLESPIE CANAL REMOVE 3", REPLACE 2.5" & ACFC TBD FY 14
QJ1L 60 NA 341.0 HX23901C G US 60 & 9TH PLACE, SHOW LOW TRAFFIC SIGNAL FEB 14
13514 CF1L 17 MA 231.0 H826801C E NEW RIVER BRIDGES, STR # 1290 &1291 SCOUR RETROFIT JAN 14
13715 KX1L 70 GI 259.0 H835901C G GILSON WASH BRIDGE, STR # 464 SCOUR RETOFIT TBD FY 15
19414 HS1L 89 YV 330.0 H827801C P ROAD 4 NORTH CONSTRUCT ROUNDABOUT APR 14
45112 WB1L 303L MA 112.0 E PEORIA AVE - WADDELL RD LANDSCAPE CONSTRUCTION JUN 13
JQ1L 0000 MA SUR SS95801C E DOVE VALLEY ROAD,18TH AVE-203RD AVE ROADWAY IMPROVEMENTS FY 13
43814 OB1L 303L MA 107.0 E CAMELBACK ROAD TO GLENDALE AVENUE CONSTRUCT LANDSCAPE JUN 14
WQ1L 19 PM 59.0 H771401C T SAN XAVIER PEDESTRIAN BRIDGE PEDESTRIAN BRIDGE IMPROVEMENTS NOV 13
10117 BY1M 15 MO 0.0 F SCENIC TO STATE LINE PE PH 1 & 2 DESIGN FY 13
45213 NU1L 303L MA 0.0 E I-10/303L TI, PHASE I (I-10 REALIGNMENT) CONSTRUCT LANDSCAPE TBD FY 14
40313 DD1J 101L MA 23.5 E I-17 TO TATUM BLVD CONSTRUCT HOV LANE DESIGN FY 13
CD1L 260 AP 394.0 H826901C G LITTLE COLORADO RIVER BR (STR # 416) SYSTEM PRESERVATION - MINOR BRIDGE REHA TBD FY 16
12415 VT1K 17 MA 195.0 E BUCKEYE RD,GRANT ST,ADAMS ST & JEFFERSON ST ELECTRICAL REHABILITATION TBD FY 15
14215 KI1L 86 PM 115.8 T TOWN OF SELLS TO FRESNAL WIDEN SHOULDERS AND CULVERT EXTENSIONS TBD FY 15
10910 DJ1G 90 CH 323.5 H655501C S CENTRAL AVE TO MOSON RD, E OF SIERRA VISTA WIDEN TO 5 LANES TBD FY 14
18413 DF1M 83 SC 12.0 H850101C T MP 12 - MP 14 MILL AND PAVE TBD FY 13
15114 GN1J 70 GH 295.0 S BYLAS TWLTL & ROADWAY WIDENING JUN 14
10114 MG1E 191 GH 100.7 S SR 266 TO ARTESIA DESIGN PARALLEL ROADWAY DESIGN FY 14
41115 WW1K 202L MA 0.0 E SALT RIVER BRIDGE, SEGMENT 7 CONSTRUCT NEW FREEWAY TBD FY 16
41608 TY1H 202L MA 0.0 E I-10 EAST/SANTAN TI TO 51ST AVE DESIGN ROADWAY TBD FY 14
ZI1L 80 CH 364.0 S WHITE WATER DRAW BRIDGE #1626 DESIGN DEC 15
JN1L 0000 MA MMA SS97201C E UPGRADE RADS REGIONWIDE SYSTEM UPGRADE FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 3 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
YL1L 202L MA 9.0 H854201C E L101 TO MESA DRIVE SYSTEM PRESERVATION (RESTORATION/REHAB/ JUN 13
GA1M 191 GE 226 H843901C G US-191, GLOBE DISTRICT, WALLOW FIRE, SIGN REPAIR SYSTEM PRESERVATION (RESTORATION/REHAB/ DESIGN FY 13
45309 FN1H 10 MA 96.2 H708301X Y 395TH AVE (BELMONT RD) CONSTRUCT TI IGA FY 14
BK1M 260 YV 218.9 P SR 260; INDUSTRIAL DR - HOMESTEAD PKWY DESIGN DESIGN FY 13
10511 XQ1L 95 MO 182.0 K LAKE HAVASU STATE PARK (CONTACT POINT) PH II DESIGN PARKING DESIGN FY 15
WJ1L 0000 MA 0.0 SR23201C E DOBSON ROAD, AAR/DOT NO. 741-649-G SYSTEM ENHANCEMENT-SAFETY IMPROVEMENT FY 14
10413 TC1J 93 MO 116.0 K CARROW TO STEPHENS CONSTRUCT 4-LANE DIVIDED HIGHWAY TBD FY 16
14313 SB1K 87 GI 236.2 H812301C P JCT 188 - RYE RR 3" TL & AR-ACFC FULL WIDTH MAY 13
41015 NX1L 202L MA 0.0 E BASELINE - SALT RIVER, SEGMENT 6 CONSTRUCT NEW FREEWAY TBD FY 15
15414 JG1K 77 PN 123.5 H796901C T ARAVAIPA CREEK BRIDGE, STR #399 BRIDGE REPLACEMENT AUG 13
IZ1K 303L MA 3.8 E SR 303L, RIGGS RD - SR 801 SYSTEM ENHANCEMENT-ENGINEERING TBD FY 14
13409 TQ1H 87 GI 263.0 H718301C P TONTO NATURAL BRIDGE STATE PARK CONSTRUCT NEW ROAD TBD FY 13
10015 QL1J 10 PM 247.0 H758301C T INA RD TO RUTHRAUFF RD RECONSTRUCTION FOR WIDENING TBD FY 15
40115 WU1K 10 MA 0.0 E SKY HARBOR WEST AIRPORT ACCESS CONSTRUCT ACCESS RAMPS TBD FY 15
43914 XE1K 303L MA 118.0 H814501C E US 60 GRAND AVE / SR 303L TI, INTERIM CONSTRUCT INTERIM TI DEC 12
13815 SR1K 75 GE 379.1 S DUNCAN BRIDGE - LITTLE SANDS WASH 3" AC & AR-ACFC TBD FY 15
14013 RO1K 587 PN 218.8 H811301C E SR 87 - JCT I-10 RR 3" & AR-ACFC MAY 13
14913 YG1L 8 YU 125.0 Y GILA BEND TO I-10 SIGN REHABILITATION DESIGN FY 13
15208 NSSP 89A YV 365.0 F RED ROCK STATE PARK DESIGN DESIGN FY 13
11914 CG1L 8 PN 163.0 H827001C T SANTA ROSA WASH BRIDGES, STR # 1092 & 1093 SCOUR RETROFIT MAR 14
12407 FX1C 10 MA 161.2 H505101C E SR 202L (SANTAN) TO RIGGS ROAD CONST HOV & GEN PURPOSE LANE TBD FY 15
CX1G 0000 PM MRN SB41301C BR-MRN-0(014)A T INA BRIDGE OVER SANTA CRUZ BRIDGE REPLACEMENT FY 13
23701 ZY1D 40 AP 340.0 H552601C 040-E(001) H SANDERS PORT OF ENTRY RECONSTRUCT POE TBD FY 15
ZQ1F 0000 MA GDY SS54401C STP-GDY-0(008)A E YUMA RD @ BULLARD WASH CONST BOX CULVERTS FY 13
WL1L 940 MA 0.0 SR19201C 000-6(172)A E 5TH ST (TEMPE) 741-560-C AT-GRADE RAILROAD CROSSING DESIGN JUN 13
12013 SW1K 10 LA 63.0 H815901C 010-A(217)T Y GAS LINE RD - COUNTY LINE RR (1/2" TL, 4" PL) & AR-ACFC FEB 13
24013 BH1M 15 MO 15.0 H857401C 015-A(208)S F VIRGIN RIVER BRIDGE #6 (STR #1619) CMAR BRIDGE REHABILITATION CONSTRUCTION TBD FY 13
HT1M 17 YV 287.0 017-B( )T P VERDE RIVER BRIDGE NB #1731 DESIGN BRIDGE REHABILITATION DESIGN FY 13
ZE1L 17 YV 287.0 017-B(224)S P VERDE RIVER BRIDGES NB & SB #1731 & #505 DESIGN DEC 15
HV1M 40 MO 83.0 040-B(220)T K WILLOW CREEK BRIDGE NO 2 EB (#1593) DESIGN BRIDGE REHABILITATION DESIGN FY 13
GT1M 40 NA 289.0 040-D(227)T H E HOLBROOK TI OP EB#1369 & WB #1370 DESIGN BRIDGE REHABILITATION DESIGN FY 13
IN1M 60 MA 109.9 060-A(207)S P US 60 @ APACHE STREET IN WICKENBURG DESIGN DESIGN FY 13
OR1K 60 GI 290.0 H808301C 060-E(206)T G MP 290, 296 AND 320 AT HAGEN HILL ROCKFALL CONTAINMENT FEB 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 4 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
15014 BT1L 60 GI 292.0 H826201C 060-E(207)A G SALT RIVER CANYON REST AREA REPLACE COMPOSTING TOILETS & STRUCTURA DEC 13
HU1M 66 CN 91.0 066-A( )T K WASH BR #141 & TRUXTON WASH BR #142 DESIGN BRIDGE REHABILITATION DESIGN FY 13
17913 LX1G 75 GE 384.0 075-A(200)T S LITTLE SANDS WASH BANK PROTECTION AUG 13
11413 AY1G 77 PM 82.0 H669401C 077-A(204)T T TANGERINE RD TO PINAL COUNTY LINE WIDENING TO 6 LANES - CONSTRUCTION JUN 13
GU1M 86 PM 114.7 086-A(211)T T TOWN OF SELLS PEDESTRIAN BRIDGES CONSTRUCT PEDESTRIAN BRIDGE TBD FY 15
GX1M 86 PM 120.6 086-A-NFA T FRESNAL TO MP 123.9 DESIGN DESIGN FY 13
GG1M 87 GI 252.0 087-B(218)A P SR 87 / SR 260 SAFETY IMPROVEMENT ACCESS CONTROL, SIGNING UPGRADES, ADA, M DESIGN FY 13
FO1M 87 MA 177.8 087-B(220)T E SR87 @ MCDOWELL RD DESIGN SIGNAL IMPROVEMENT DESIGN FY 13
18313 MI1K 89 YV 335.9 H797601C 089-B(204)T P BIG CHINO WASH BRIDGE #979 DECK REPLACEMENT / WIDENING JAN 13
18713 MS1K 89 YV 333.1 H791901C 089-B(208)T P DEL RIO RANCH BRIDGE #20046 BRIDGE REPLACEMENT JAN 13
XA1L 89 YV 345.0 089-B(211)T K HELL CANYON BRIDGE #483 REPLACEMENT & WIENING TBD FY 14
FK1M 93 YV 185.3 093-B(210)T P SOUTH OF SR71 - NORTH OF SR89 DESIGN ROADWAY WIDENING DESIGN FY 13
SL1L 95 MO 239.5 095-D(204)T K STATE ROUTE 95 @ STERLING RD DESIGN INTERSECTION IMPROVEMENT DESIGN FY 13
HH1M 95 MO 239.0 095-D(208)T K SR 95 @ VALENCIA ROAD DESIGN DESIGN FY 13
VS1L 101L MA 60.0 H848801C 101-C(201)A E GALVESTON DRAINAGE BASIN G (THUDE PARK) DRAINAGE IMPROVEMENT & PUMP STATION IGA FY 13
GQ1M 180 AP 403.5 180-C(201)A G SEVERAL LOCATIONS ON US180 SYSTEM PRESERVATION - ENGINEERING DESIGN FY 13
14112 AI1K 191 CH 61.5 H788301C 191-A(203)A S COCHISE POWER PLANT - JCT I-10 RR 2" AC + 3" AC + FR TBD FY 14
GP1M 191 AP 247.8 191-C(216)A G RIGHT OF WAY FENCE IN BOTH DIRECTIONS RIGHT OF WAY FENCING DESIGN FY 13
GO1M 260 AP 385.5 260-C(205)A G RIGHT OF WAY FENCING TWO LOCATIONS EAST BOUN RIGHT OF WAY FENCING DESIGN FY 13
XX1G 264 AP 446.0 264-A(212)T H GANADO WASH BRIDGE #1046 DESIGN BRIDGE REPLACEMENT DESIGN FY 14
CY1M 347 PN 172.0 347-A(209)T T ALTERRA TO CASA BLANCA RD, CITY OF MARICOPA DESIGN DESIGN FY 13
WM1L 5013 MA 0.0 SR14401C 501-3(001)P E 32ND ST ( PHX) #741-536-B SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13
WN1L 7018 MA 0.0 SR09701C 701-8(003)P E 40TH ST PHOENIX 741-539-W SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13
16414 IS1J 89 CN 385.1 H741801C A89-B(204)A F OAK CREEK CANYON CREEK BANK PROTECTION TBD FY 14
14315 SG1L 87 PN 148.0 BR - T GILA RIVER BRIDGE, STR #635 SCOUR RETROFIT DEC 14
15613 RH1L 17 MA 238.6 BR - P MOORES GULCH BRIDGE SB #339 DESIGN BRIDGE REPLACEMENT DESIGN FY 13
16713 KW1L 40 NA 271.0 H837201C BR - H MANILA WASH BRIDGES STR #851,852 & 2080 SCOUR RETROFIT MAR 13
13915 RW1L 75 GE 387.0 BR - S VARIOUS BRIDGES (STR #S 861,202,242,983,243,251) SCOUR RETROFIT DEC 14
15513 KV1L 10 CH 381.0 H837101C BR - S SAN SIMON RIVER BR (STR #1167,1168 & 230) SCOUR RETROFIT MAR 13
13315 JL1K 40 NA 284.3 BR -040-D(223)A H LEROUX WASH BRIDGE EB #1772 & WB #1773 BRIDGE REPAIR TBD FY 15
14814 RE1L 60 MA 115.5 BR -060-B(209)T P MONARCH WASH BR, STR #204 & 759 SCOUR RETROFIT DEC 13
15514 NH1L 77 GI 147.6 H832201C BR -077-A(207)A G DRIPPING SPRING BRIDGE #398 BRIDGE REPLACEMENT JUL 13
18113 NY1K 79 PN 101.8 H807501C BR -079-A(205)T T CORONADO WASH BRIDGE STRUCTURE #222 BRIDGE REPLACEMENT MAY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 5 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
16114 VM1K 87 CN 323.9 BR -087-C(203)A H LIMESTONE WASH BRIDGE # BRIDGE REPLACEMENT JUL 13
14615 JR1L 92 CH 340.5 BR -092-A(203)A S SAN PEDRO RIVER BRIDGE #449 BRIDGE REPLACEMENT TBD FY 15
ZN1E 0000 PN PPN SB41001C BR -PPN-0-(169) G KELVIN BRIDGE - #8441 BRIDGE REPLACEMENT FY 13
BA1L 0000 YU YYU SB43701C BR -YYU-0(201)T Y COUNTY 19TH ST BRIDGE OVER MAIN DRAIN (AVE F 1/2 BRIDGE REPLACEMENT FY 13
XD1L 0000 YU YYU SB44501C BR -YYU-0(205)A Y BRIDGE REHABILITATION OLD HWY 80 & AVE 30 1/2 E BRIDGE REHABILITATION FY 14
ZV1L 0000 YU SLS CBI -SLS-0(201)A Y WIDENING AVE E FROM COUNTY 25TH STREET TO SR1 SYSTEM ENHANCEMENT (ENGINEERING) FY 14
43208 ST1H 202L MA 44.0 CM - E LINDSAY ROAD TO GILBERT ROAD DESIGN & CONST MULTI-USE PATH TBD FY 13
41215 XC1K 202L MA 43.0 CM - E VAL VISTA DR. - DOBSON RD CONSTRUCT FMS TBD FY 15
45313 TR1H 17 MA 215.0 H844501C CM -017-A(230)A E SR 101L (AGUA FRIA) TO ANTHEM WAY CONSTRUCT FMS MAY 13
44814 TX1H 202L MA 47.8 CM -888-A(218)T E DOBSON ROAD TO I-10, MARICOPA CONSTRUCT FMS TBD FY 14
PK1K 0000 MA GDY SS89601C CM -GDY-0(203)A E TRAFFIC SIGNAL SYSTEM ITS BACKBONE & COMMUNICATION FY 13
OC1K 0000 MA MES SS87701C CM -MES-0(216)A E LOCAL AGENCY WIDE - FIBER-OPTIC COMMUNICATION FIBER OPTICS FY 13
PI1K 0000 MA MES SS89101C CM -MES-0(217)A E ITS TRAFFIC SIGNAL CONVERSIONS - PHASE 5 FIBER-OPTIC COMMUNICATIONS NET FY 13
BB1L 0000 MA MMA SS83001C CM -MMA-0(214)A E OLIVE AVE: LITCHFIELD ROAD TO LOOP 101 INSTALL FIBER OPTIC CONDUIT FY 13
PL1K 0000 MA MMA SS89901C CM -MMA-0(228)A E 87TH AVENUE PAVING DIRT ROAD FY 13
CC1L 0000 MA MMA SS95701C CM -MMA-0(231)A E 88TH AVE: DEER VALLEY TO WILLIAMS RD PAVE UNPAVED ROAD FY 13
ZS1J 0000 MA PHX CM -PHX-0(223)A E SALT RIVER PATHWAY - 24TH ST TO I-10 TEMPE DRAIN PATHWAY IMPROVEMENTS FY 13
XY1K 0000 MA QCR SS87601C CM -QCR-0(207)A E TOWNWIDE - ITS DEVELOPMENT SYSTEM ENHANCEMENT - TRAFFIC MGMT AND E FY 13
UH1K 0000 MA SCT SS91301C CM -SCT-0(211)A E DYNAMITE BLVD - PIMA TO ALMA SCHOOL ROAD INSTALL CURB AND GUTTER FY 13
ZJ1K 0000 MA SUR SS85401C CM -SUR-0(210)A E BELL RD-US 60 TO 114TH AVE CONSTRUCT MULTI-USE PATH FY 14
LK1K 0000 MA TMP SS73401C CM -TMP-0(210)X E BROADWAY ROAD: RURAL TO MILL AVENUE PEDESTRIAN IMPROVEMENTS FY 15
BX1L 0000 MA TMP SS95301C CM -TMP-0(217)A E SALT RIVER MUP: I-10/TEMPE DRAIN TO PRIEST DRIVE PATHWAY IMPROVEMENTS FY 13
22910 YS1K 0000 CH DGS SS87401C DGS-0(200)A S CHINO ROAD NEW FACILITIES - CONSTRUCTION OF NEW ROA FY 14
10917 EJ1M 999 SW 0.0 FA - X STATEWIDE DYNAMIC MESSAGE SIGN PHASE 11 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 17
22413 YC1L 64 CN 0.0 H817202C FA - F RURAL INTELLIGENT TRANSPORTATION SYSTEMS - PH CONSTRUCT FEB 13
16115 XX1L 999 SW 0.0 FA -999-A(383)T E STATEWIDE DYNAMIC MESSAGE SIGN PHASE 10 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 15
43016 JJ1H 60 MA 139.0 HES -060-B(ATZ) E SR 303L TO SR 101L, AGUA FRIA, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 16
KK1L 93 MO 139.0 HPP -093-B(209) K US 93, SB BURRO CREEK BRIDGE SYSTEM PRESERVATION - ENGINEERING TBD FY 14
VK1J 0000 GI GGI HPP -GGI-0(204)A G TONTO CREEK BRIDGE DESIGN BRIDGE APPROACHES FY 13
MD1K 0000 NA PLS SS86401C HPP -PLS-0(201)A G BILLY CREEK BRIDGE @ PORTER MOUNTAIN ROAD CAPACITY ADDITIONS - MAJOR WIDENING FY 13
BP1J 0000 PM TUC HPP -TUC-0(201)A T HOUGHTON ROAD WIDENING @ UPRR ROAD WIDENING OVER RAILROAD BRIDGE FY 16
GZ1L 0000 PM TUC HPP -TUC-0(241)A T HOUGHTON RD: UPRR TO I-10 - WIDENING ROADWAY WIDENING FY 16
12914 EI1M 999 SW 0.0 HSIP- X STATEWIDE GUARDRAIL DELINEATORS TBD FY 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 6 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
16513 DH1M 87 CN 268.1 HSIP- P MP 268.1 - MP 278 PE PH 1 & 2 DESIGN FY 13
18314 HR1L 264 AP 441.1 H824601C HSIP- H US 191 TO SAWMILL ROAD SEGMENT 1 SHOULDER WIDENING PROGRAM PE PH 1 & PH 2 DESIGN FY 14
19314 NC1H 88 MA 203.4 H700501C HSIP- E SR88, APACHE TRAIL GOLDFIELD TO CANYON LAKE SPOT SAFETY IMPROVEMENTS JUN 14
15714 WH1K 80 CH 316.5 H800402C HSIP- S TOMBSTONE, MP 316.5 TO MP 318.0 LIGHTING AND SIDEWALKS MAR 15
17114 IP1K 93 MO 17.4 HSIP- K MP 17.4 - MP 58.4 PE PH 1 & 2 DESIGN FY 14
14914 CU1M 60 GI 229.4 HSIP- G MP 229.4 - MP 232.91 SHOULDER WIDENING TBD FY 14
15413 HJ1J 8 YU 7.2 HSIP- Y I-8 AND ARABY ROAD PE PH 1 AND 2 DESIGN FY 13
13613 SC1K 191 CH 38.2 HSIP- S JCT SR 181 - PEARCE ROAD 3" AC & AR-ACFC MAY 13
20613 MQ1L 260 NA 282.5 HSIP- P RIM RD TO GIBSON RD, SEGMENTS 1, 2 & 3 SHOULDER WIDENING PROGRAM, PE PH 1 & 2 DESIGN FY 13
21513 XV1K 999 SW 0.0 H820601C HSIP- E STATEWIDE TREE THINNING TREE REMOVAL FROM CLEAR ZONE, PE PH 1 & 2 DESIGN FY 13
16214 JD1L 88 PN 196.0 H830801C HSIP- E SUPERSTITION BLVD CONSTRUCT ROUNDABOUT JUN 14
17014 HL1L 92 CH 322.1 H826501C HSIP- S SR 92 @ FOOTHILLS DR INTERSECTION IMPROVEMENTS JAN 14
19214 HM1L 77 PN 105.4 H826701C HSIP- T POWER LINE - SAN MANUEL ROAD DESIGN SHOULDER WIDENING DESIGN FY 14
15813 BX1M 69 YV 281.1 HX24201C HSIP-069-A(210)T P MP 281.1 - MP 289.7 MODIFY SIGNALS JUN 13
16914 VY1L 90 CH 321.0 H849701C HSIP-090-A(205)A S SR 92 - GIULIO CESARE AVENUE LIGHTING MAR 14
19213 LC1J 92 CH 324.3 H716701C HSIP-092-A(200)T S BUFFALO SOLDIER TRAIL TO KACHINA TRAIL RAISED MEDIAN JUN 13
17214 XL1L 95 LA 149.2 HSIP-095-C(216)A Y CIENEGA SPRINGS RD SB LEFT TURN LANE APR 14
23913 ZC1L 999 SW 0.0 HSIP-999-A(377)S F I-17 AND I-40, INLAID PAVEMENT MARKERS, SEGMENT I INLAID PAVEMENT MARKINGS TBD FY 13
44909 FM1H 10 MA 105.0 H683801X I -010-A-901 Y I-10/DESERT CREEK TI (PRIVATE FUNDS) CONSTRUCT TI IGA FY 14
14314 SD1K 40 CN 204.0 IM - F WALNUT CANYON - TWIN ARROWS RR 3" & 2" AC & AR-ACFC DEC 13
45414 ET1M 202L MA 0.0 IM - E I-10 PAPAGO/ SR202L SYSTEM INTERCHANGE SEGMEN DESIGN NEW SYSTEM TI DESIGN FY 14
11715 BA1M 10 LA 42.0 IM - Y MP 42 TO HOVATTER ROAD RR(4" TL, 3" PL) + AR-ACFC TBD FY 15
16313 PY1E 40 YV 102.0 IM - K CROSS MT - JOLLY RD UPGRADE EXISTING ROCKFALL PROTECTION TBD FY 13
10317 CG1M 40 MO 81.0 IM - K EAST OF US 93 TI ROCKFALL MITIGATION TBD FY 17
42115 ER1M 202L MA 0.0 IM - E ELLIOT RD - BASELINE RD, SEGMENT 5 DESIGN NEW FREEWAY DESIGN FY 15
10217 CD1M 40 MO 40.0 IM - K CROOKTON TO TRANSWESTERN SIGN REHABILITATION TBD FY 17
10417 CH1M 40 MO 83.0 IM - K WILLOW SPRINGS ROCKFALL MITIGATION TBD FY 17
12915 CF1M 40 MO 74.0 IM - K HWY 141 JCT TO SILVER SPRINGS ROAD (WB) RR (5"TL, 3" PL) + AR-ACFC + SHOULDERS TBD FY 15
40017 ES1M 202L MA 0.0 IM - E I-10 MARICOPA - 24TH ST, SEGMENT 1 CONSTRUCT NEW FREEWAY TBD FY 17
12816 CM1M 40 NA 297.0 IM - H GOODWATER - YELLOWHORSE PE PH 1 & 2 DESIGN FY 16
40016 EK1M 10 MA 129.5 IM - E DYSART RD - 83RD AVE DESIGN & CONSTRUCT FMS TBD FY 16
12615 CA1M 17 YV 279.6 IM - P SR 169 TO MIDDLE VERDE ROAD RR(5" TL, 3" PL) + AR-ACFC TBD FY 15
10916 CB1M 17 YV 292.0 IM - P SOUTH OF MCGUIREVILLE ROCKFALL MITIGATION TBD FY 16
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 7 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
10017 XT1L 8 YU 0.0 IM - Y YUMA PORT OF ENTRY PE PH2 DESIGN FY 17
12315 BW1M 15 MO 0.0 IM - F NEVADA STATE LINE - MP 13 RR(4" TL, 3" PL) AR-ACFC TBD FY 15
11016 KH1L 40 CN 218.7 IM - F TWIN ARROWS TI, EB OFF-RAMP RAMP REMOVAL, RECONSTR & ACCESS CTRL M TBD FY 16
12115 YB1K 10 CH 320.5 H821101C IM - S TEXAS CANYON REST AREA WATER, STRUCTURAL, MECHANICAL & ELECTRI TBD FY 15
16613 CK1M 40 NA 226.0 IM - H EAST WINSLOW TI PE PH 1 & 2 DESIGN FY 13
12613 NQ1L 40 CN 146.0 H840201C IM - F EAST ASHFORK TI TO WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC APR 13
17013 QD1L 40 NA 298.0 IM - H MP 298 UTILITY OVERPASS DESIGN OF CBC EXTENSION JAN 15
16913 CL1M 40 NA 290.0 IM - H HOLBROOK - SUN VALLEY FENCING AND CATTLE GUARDS TBD FY 13
13415 CN1M 40 NA 297.0 IM - H SUN VALLEY ROAD - WASHBOARD ROAD RR (5" TL, 3" PL) + 2"AC + FC JAN 15
14714 QO1L 40 NA 303.0 IM - H ADAMANA TI DRAINAGE IMROVEMENTS TBD FY 14
11814 SV1K 8 YU 13.7 H815801C IM - Y FOOTHILLS BLVD - DOME VALLEY RR (5" TL, 3" PL) & FR NOV 13
12215 YI1K 10 CH 388.0 H821601C IM - S SAN SIMON REST AREA NEW WELL,WATER PUMPS,STRUC,ELECT,MECH TBD FY 15
12715 SU1K 19 SC 16.0 IM - T PALO PARADO - CHAVEZ SLIDING TI RR (4" TL, 3" PL) + FR TBD FY 15
14214 CJ1M 40 CN 185.0 IM - F TRANSWESTERN - LEUPP JCT PE PH 1 & 2 DESIGN FY 14
12514 BT1M 10 MA 164.0 IM - E WILD HORSE PASS - RIGGS RR(5" TL - 3" PL) + AR-ACFC TBD FY 14
11915 BU1M 10 CH 296.0 IM - T MESCAL ROAD TO JCT SR 90 RR(5" TL, 3" PL) + AR-ACFC TBD FY 15
10716 BV1M 10 CH 383.0 IM - S SAN SIMON PORT OF ENTRY PE PH 1 & 2 DESIGN FY 16
12415 HW1L 17 MA 202.3 IM - E INDIAN SCHOOL ROAD - PEORIA AVENUE SIGN REHABILITATION TBD FY 15
13003 FR1C 8 YU 55.9 H206001C IM - Y MOHAWK REST AREA CONSTRUCT REST AREA TBD FY 15
12014 BR1M 10 MA 145.0 IM - E 3RD AVENUE TO 3RD STREET PUMP STATION IMPROVEMENTS TBD FY 14
12214 VX1J 10 MA 105.0 H775001C IM - E SR 85 TO DYSART (VERRADO WAY TO 85) SIGN REHABILITATION JUL 13
44612 WR1K 10 MA 151.5 IM - E 32ND ST - SR202L, SANTAN PHASE 1 CONSTRUCT LOCAL EXPRESS LANES DESIGN FY 17
12515 BZ1M 17 MA 198.0 IM - E BUCKEYE RD, GRANT,JEFFERSON & ADAMS ELECTRICAL REHABILITATION TBD FY 15
10816 GQ1J 17 MA 216.0 IM - E I-17 @ PEORIA AND UNION HILLS DRAINAGE GRATE IMPROVEMENTS TBD FY 16
11913 TI1K 8 PN 170.0 IM - T BIANCO ROAD - JCT I-10 RR(5" TL, 3" PL) & AR-ACFC NOV 13
14414 EV1L 40 CN 218.7 H789001C IM - F CANYON PADRE BRIDGE, STR #1670 DECK REPLACEMENT APR 14
11615 XP1L 10 LA 17.5 IM - Y WEST QUARTZSITE TI INTERSECTION IMPROVEMENTS TBD FY 15
11714 BN1M 8 YU 2.0 IM - Y 16TH STREET LANDSCAPING JUN 14
11614 BM1M 8 YU 1.0 IM - Y WB OFF RAMP & GISS PARKWAY INTERSECTION INTERSECTION IMPROVEMENTS JUN 14
12113 IP1L 10 MA 112.8 IM -010-A(216)A E SR 85 - VERRADO (EB) RR(4"TL, 3" PL) & AR-ACFC FEB 14
12414 FY1L 10 MA 162.0 IM -010-C(204)T E WILD HORSE PASS TO SR 347 (QUEEN CREEK ROAD) ROADWAY WIDENING TBD FY 14
12314 YD1L 10 MA 144.9 IM -010-C(209)T E 3RD AVENUE TO 3RD STREET, DECK PARK TUNNEL DRAINAGE IMPROVEMENTS TBD FY 14
12714 AZ1M 10 PM 268.0 IM -010-D(215)T T I-19 TO CRAYCROFT ROAD IN TUCSON SIGN REHABILITATION AUG 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 8 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
HB1M 10 PN 209.9 H861401C IM -010-D(217)T T LA PALMA RD TO PICACHO HWY DESIGN PAVEMENTPRESERVATION PROJECT DESIGN FY 13
12814 NB1K 10 PM 283.6 H805201C IM -010-E(208)A T DAVIDSON CANYON - COUNTY LINE MILL AND REPLACE NOV 13
11815 NA1L 10 PM 284.4 IM -010-E(213)A T DAVIDSON CANYON WB BRIDGE, STR #598 SUPERSTRUCTURE REPLACEMENT TBD FY 15
12213 SQ1K 10 CH 318.8 H815101C IM -010-F(216)T S DRAGOON RD - WEST WILLCOX TI (WB) PAVEMENT PRESERVATION APR 13
13214 RC1L 10 CH 333.0 IM -010-F(218)A S US 191 TO EAST WILLCOX TI RR (5" TL, 3" PL) & AR-ACFC JAN 14
12015 WD1L 10 CH 306.7 IM -010-F(219)A S SAN PEDRO RIVER BRIDGE EB #1530 & WB #1531 DECK REPLACEMENT & SCOUR RETROFIT TBD FY 15
13614 SO1K 17 YV 269.2 IM -017-B(218)A P DUGAS TI - CHERRY ROAD RR (5" TL, 3" PL) & AR-ACFC DEC 13
13814 MT1L 19 SC 0.3 IM -019-A(216)A T INTERNATIONAL BORDER - JCT B-19 RR AR-ACFC JUN 13
QP1J 40 MO 66.5 IM -040-B(208)A K I-40, BLAKE RANCH RD TI IMPROVEMENTS TBD FY 13
14114 SM1K 40 MO 57.0 IM -040-B(213)A K RATTLESNAKE WASH - JCT US 93 RR(5" TL, 3" PL) & AR-ACFC TBD FY 14
13015 CI1M 40 MO 87.0 IM -040-B(217)T K WILLOW RANCH ROAD TO MP 92, EB RR (5" TL, 3" PL) + AR-ACFC WITH SHOULDERS E TBD FY 15
16413 IW1L 40 CN 180.8 IM -040-C(208)A F EAST OF PARKS ROCKFALL MITIGATION JUN 13
14514 EE1K 40 NA 254.6 IM -040-D(213)A H RUBY WASH BRIDGE - E WINSLOW TI OP BRIDGE REHABILITATION JUL 13
14614 SJ1K 40 NA 290.2 H813101C IM -040-D(219)A H HOLBROOK - SUN VALLEY RR (5"TL, 3"PL) & AR-ACFC JUL 13
12813 ZY1J 40 NA 303.1 H785901C IM -040-E(214)T H BIG LITHODENDRON-PETRIFIED FOREST NATIONAL PA PAVEMENT PRESERVATION MAR 13
13115 WT1L 40 YV 144.0 IM -089-B(214)T K ASHFORK RR BR - JCT SR 89, #807,#440, #1760,#1761 BRIDGE DECK REHABILITATION TBD FY 15
40616 EV1M 303L MA 103.2 IM -303-A(216)S E I-10/303L TI, PHASE II CONSTRUCT NEW FREEWAY TBD FY 16
12815 CE1M 40F MO 47.8 IM -999-A(398)T K SOUTH OF KINGMAN ROCKFALL MITIGATION TBD FY 15
45314 EQ1M 202L MA 0.0 NH - E 24TH ST - 17TH AVE, SEGMENT 2 DESIGN NEW FREEWAY DESIGN FY 14
44811 ZN1J 85 MA 153.2 H800601C NH - E WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE TBD FY 14
12216 LY1C 260 GI 258.0 NH - P LION SPRINGS SECTION RECONSTRUCT TO A 4-LANE DIVIDED TBD FY 16
14515 FP1L 89 CN 525.0 NH - F JCT US 89A - BIG CUT EP (PIPE) DROP-OFF MITIGATION TBD FY 15
20513 EB1M 260 GI 262.0 NH - P VARIOUS BRIDGE APPROACHES REPAIR BRIDGE APPROACHES TBD FY 13
40216 EN1M 60 MA 192.0 NH - E CRISMON RD - MERIDIAN RD DESIGN HOV/GPL DESIGN FY 16
16615 XT1K 87 GI 226.0 H820701C NH - P SLATE CREEK ROAD REPAIR TBD FY 15
11207 QK1C 19 PM 58.7 NH - T AJO WAY TI (JCT SR 86) RECONSTRUCT TI TBD FY 17
16814 HG1L 89 CN 551.0 NH - F PAGE MAINTENANCE YARD WIDENING FOR TURN LANES TBD FY 14
11515 QQ1H 89 CN 452.6 H705601C NH - F SOUTH OF GRAY MOUNTAIN PASSING LANES (NB AND SB) TBD FY 15
16714 FD1L 89 CN 523.9 NH - F BITTER SPRINGS INSTALL INTERSECTION LIGHTING TBD FY 14
14213 DN1M 89 CN 420.0 NH - F FLAGSTAFF CITY LIMITS - LENOX PARK FEASIBILITY REPORT FOR ACCESS MGT PLANNI DESIGN FY 13
12716 FG1M 202L MA 0.0 NH - E PUMP STATION FLOOD EROSION CONTROL TBD FY 16
19413 WY1L 95 LA 142.0 NH - Y SR 95 AT MOHAVE ROAD PE PH 1 & 2 DESIGN FY 13
10015 VH1L 10 PM 252.0 NH - T RUTHRAFF ROAD TI RECONSTRUCTION FOR WIDENING TBD FY 15
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 9 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
40913 CM1J 10 MA 122.0 H770901C NH - E PERRYVILLE ROAD TI CONSTRUCT TI APR 13
11514 QN1C 40 AP 357.5 NH - H WINDOW ROCK TI PE PH 1 DESIGN FY 14
11312 CQ1J 10 PM 264.0 NH - T COUNTRY CLUB ROAD TI DESIGN TRAFFIC INTERCHANGE (PE PH 1) DESIGN FY 16
13016 TL1L 101L MA 50.7 NH - E RED MOUNTAIN - CHANDLER BLVD SIGN REHABILITATION TBD FY 16
10216 DO1M 93 MO 109.0 NH - K CANE SPRINGS PE PH 1 & 2 DESIGN FY 16
17413 CP1M 40 AP 322.0 NH - H CHAMBERS PORT OF ENTRY PE PH 1 & 2 DESIGN FY 13
15710 NN1F 10 LA 3 H616101C NH - Y EHRENBERG PORT OF ENTRY RECONSTRUCT EB PORT OF ENTRY TBD FY 16
10208 PJ1F 10 PM 248.0 NH -010-D T INA ROAD TI RECONSTRUCT TI & MAINLINE TBD FY 16
40613 NM1L 60 MA 194.0 NH -060-C(207)T E MERIDIAN ROAD. HALF TI CONSTRUCT TI TBD FY 14
YJ1L 69 YV 292.1 H854001C NH -069-A(211)T P SUNRISE BLVD TO PRESCOTT CANYON DR PAVEMENT PRESERVATION (AR-ACFC) MAR 13
10412 DA1J 89 CN 464.5 H791501C NH -089-D(201)T F SR-64 TO LITTLE COLORADO RIVER CONSTRUCT 4-LANE URBAN, SR64 INTERSECTIO JAN 13
13812 AH1K 89 CN 510.0 NH -089-D(202)A F GRAY SPOT WASH - NORTH RED HILL 3" AC + FR NOV 13
10312 LE1G 93 MO 101.8 H738801C NH -093-B(204)T K ANTELOPE WASH CONSTRUCT 4-LANE DIVIDED HIGHWAY FEB 13
19313 DP1M 93 MO 125.0 NH -093-B(211)T K MEDLIN CROSSOVER DESIGN AND CONSTRUCT NEW CROSSOVER DESIGN FY 13
10416 NW1L 95 YU 34.0 H459901C NH -095-B(201) Y FORTUNA WASH BRIDGE CONSTRUCT NEW BRIDGE TBD FY 16
11710 RJ1C 160 NA 375.2 H512001C NH -160-A(201)T H JCT SR 564 - TSEGI, PH I CONSTRUCT DUAL PASSING LANES FEB 13
17314 FN1L 160 CN 343.4 NH -160-A(203)A F TONALEA INSTALL INTERSECTION LIGHTING TBD FY 14
14513 PA1K 260 NA 310.0 H801201C NH -260-B(209)A G PIERCE WASH BRIDGE (STR # 1373) SCOUR RETROFIT JAN 13
18214 SH1K 260 NA 321.4 NH -260-B(216)A G COTTONWOOD WASH - SHOW LOW RR 3" AC & AR-ACFC TBD FY 14
45713 EU1M 303L MA 120.0 NH -303-A(215)T E EL MIRAGE RD DESIGN TI DESIGN FY 13
MZ1H 303L MA 5.0 NH -303-A(ASO) E I-10, MC 85 TO I-10 NEW 303 EXTENSION SOUTH TBD FY 14
40317 EP1M 101L MA 11.2 NH -888-A(217)T E AGUA FRIA I-10 TO I-17 CONSTRUCT FMS TBD FY 17
22013 VX1K 999 MA 0.0 NH -999-A(215)T E VARIOUS LOCATIONS ON SR 101L AND I-17 PUMP STATION IMPROVEMENTS JAN 13
NG1L 0000 MA PHX PHX-0(266)A E BLACK MOUNTAIN BLVD, SR 51/SR 101 NEW ROADWAY FY 14
43514 WZ1K 202L MA 0.0 RARF- E 17TH AVE TO 51ST AVE, SEGMENT 3 CONSTRUCT NEW FREEWAY TBD FY 15
40415 UF1H 202L MA 0.0 RARF- E SALT RIVER - BUCKEYE ROAD SEGMENT 8 CONSTRUCT NEW FREEWAY TBD FY 17
45613 UU1L 10 MA 129.5 RARF- E DYSART ROAD TO SR 101L (AUGA FRIA FWY) LANDSCAPE CONSTRUCTION JUN 13
45212 OF1L 303L MA 114.0 RARF- E WADDELL ROAD TO MOUNTAIN VEIW ROAD CONSTRUCT LANDSCAPE JUN 13
45113 OC1L 303L MA 109.0 H860301C RARF- E GLENDALE AVE TO PEORIA AVE CONSTRUCT LANDSCAPE JUN 14
43015 EW1M 303L MA 0.0 RARF- E US 60 GRAND AVE / SR 303L TI, INTERIM LANDSCAPE CONSTRUCTION TBD FY 15
44913 OE1L 303L MA 105.0 H850401C RARF- E THOMAS ROAD TO CAMELBACK ROAD CONSTRUCT LANDSCAPE TBD FY 14
41213 YR1K 202L MA 9.0 RARF- E SR 101 TO GILBERT ROAD DESIGN GENERAL PURPOSE LANES DESIGN FY 14
80899 S9SP 101L MA 73.0 H387501C RARF-101-B E PIMA ROAD EXTENSION, JPA CONSTRUCT ROADWAY IGA FY 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 10 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
HY1L 66 MO 56.4 H809401X SB -AZ09(002) K KINGMAN POWERHOUSE VISITOR CENTER IMPROVEMENTS IGA FY 13
45913 EO1M 101L MA 6.0 STAN- E MARYLAND AVENUE CONSTRUCT DIRECT HOV RAMP (DESIGN BUILD) FEB 13
15515 JC1H 286 PM 20.0 H690701C STP - T SR 286 (SASABE - ROBLES RANCH HWY) REPAIR HEADCUTTING PROBLEMS AT LW WATE TBD FY 15
14115 GP1G 82 SC 40.5 STP - T SR-82 AT MP 40.6 EXTEND CBC & ELIMINATE GUARDRAIL TBD FY 15
15914 GR1G 82 SC 36.5 STP - T SR-82, MP 36.5 - 36.9 EXTEND 2 CBC'S AND ELIMINATE GUARDRAIL TBD FY 14
11116 YF1K 40 SW 235.0 H821401C STP - H PAINTED CLIFFS & METEOR CRATER REST AREAS SYSTEM PRESERVATION - RESTORATION/REHAB TBD FY 16
12416 BU1L 999 SW 0.0 H826301C STP - K HAVILAND & MARBLE CANYON REST AREAS STRUCTURAL REHABILITATION TBD FY 16
14915 ZA1J 191 CH 331.0 STP - S I-10/ US 191 TI AT MP 331 CONSTRUCT IMPROVEMENTS TBD FY 15
11616 GQ1G 82 SC 39.0 STP - T ELGIN TURNOFF EXTEND CMP'S, FLATTEN SLOPE & ELIMINATE G TBD FY 16
15615 YC1K 999 SW 0.0 H821301C STP - T SACATON & CANOA RANCH REST AREAS WATER/WASTEWATER, STRUC & ELECTICAL RE TBD FY 15
18213 DE1M 80 CH 317.0 STP - S TOMBSTONE REMOVE PEDESTRIAN BRIDGE TBD FY 13
10717 FF1M 92 CH 351.0 STP - S MELODY LANE - NACO RD WIDEN TO 3 LANES TBD FY 17
20713 EF1M 266 GH 104.0 STP - S JCT 191 - BONITA CHIP SEAL & GR RENEWAL JUN 13
18414 EE1M 264 AP 446.0 STP - H GANADO SECTION WIDENING TO 3 LANES & TL TBD FY 14
18514 EG1M 288 GI 260 STP - G ROOSEVELT - YOUNG CBC EXTENSION OCT 13
19514 DT1M 188 GI 240.0 STP - G WINDY HILL INSTALL DRAINAGE FACILITY CBC SEP 13
12016 IS1L 191 GH 120.3 STP - S RELATION ST TO JCT US70 INTERSECTION IMPROVEMENT TBD FY 16
16512 DV1M 191 GH 104.0 STP - S SR 266 TO US 70 (REALIGNMENT) SCOPING DESIGN FY 13
13213 RN1K 88 MA 204.0 STP - E APACHE JCT - TORTILLA FLATS MILL 2" & 3" AC & CHIP SEAL JAN 14
13515 CQ1M 60 MA 189.0 STP - E SOSSAMAN - MERIDIAN DRAINAGE IMPROVEMENTS TBD FY 15
16914 AE1K 264 AP 459.0 H786301C STP - H CROSS CANYON - SUMMIT 2" AC & AR-ACFC TBD FY 14
20013 YU1L 180 AP 426.0 STP - G EAGER ALPINE INSTALL DRAINAGE FACILITY JUN 13
16614 HO1L 89 CN 403.0 STP - F JCT SR 89A / PLAZA WAY (FLAGSTAFF) DRAINAGE IMPROVEMENTS TBD FY 14
10617 DI1M 87 CN 324.0 STP - P CLOVER CREEK ROCKFALL MITIGATION TBD FY 17
17713 CZ1M 68 MO 20.0 STP - K MP 19, TURN LANES DESIGN & CONSTRUCT 3 EB TURN LANES DESIGN FY 13
12116 DW1M 191 AP 345.0 STP - H SANDERS - WITCH WELLS FENCING & CATTLE GUARDS TBD FY 16
11416 MW1L 74 MA 30.0 H840301C STP - E I-17 AND LAKE PLEASANT PKWY CONSTRUCT DRAINAGE IMPROVEMENTS TBD FY 16
14715 SF1K 180 AP 386.3 STP - G GENERATING STATION ROAD - JCT US 60 RR 3" & CHIP SEAL TBD FY 15
18013 ZS1H 77 NA 367.0 STP - H FIVE MILE WASH BRIDGE PE PH 1 & 2 (WIDEN ROADWAY TO 4 LANES) DESIGN FY 13
14815 SG1K 180 AP 407.0 STP - G JUAN CARILLO - FH275 RR 3" AC & AR-ACFC TBD FY 15
13914 CC1M 19 SC 9.0 STP - T I-19 FRONTAGE ROAD, NB DRAINAGE REPAIR TBD FY 14
16715 EA1M 260 YV 220.0 STP - P SR 260 AT INDUSTRIAL DRIVE IN CAMP VERDE ROUNDABOUT DEC 14
16315 UZ1J 89A CN 525.0 STP - F JCT US 89 - COLORADO RIVER EXTEND PIPES AND CULVERTS TBD FY 15
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 11 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
14415 SP1K 89 YV 258.3 STP - P JCT US 93 - JCT SR 71 RR 3" & AR-ACFC TBD FY 15
ZP1K 0000 YU YYU SS86101C STP - Y S. FRONTAGE ROAD - AVENUE 9E TO AVENUE13E PAVEMENT PRESERVATION FY 13
16215 DL1M 89A YV 343.0 STP - P SOUTH OF JEROME ROCKFALL MITIGATION TBD FY 15
16314 DM1M 89 YV 349.0 STP - P JCT SR 260 (COTTONWOOD) CONSTRUCT DUAL RIGHT TURN LANES TBD FY 14
16815 SL1K 264 AP 441.0 STP - H BURNSIDE - CROSS CANYON 2" AC & AR-ACFC TBD FY 15
20213 OT1F 188 GI 254.0 STP - G ROOSEVELT - JAKES CORNER INSTALL DRAINAGE FACILITY CBC TBD FY 13
17814 SK1K 191 AP 482.0 H813201C STP - H ROUND ROCK - JCT. US 160 3" AC & AR-ACFC FEB 14
10616 XD1K 260 YV 218.5 STP - P THOUSAND TRAILS TO I-17 CONSTRUCT INTERIM IMPROVEMENTS TBD FY 16
15815 QH1L 999 MA 0.0 STP - E VARIOUS LOCATIONS DRAINAGE TUNNEL IMPROVEMENTS TBD FY 15
13113 FF1G 73 NA 342.3 STP - G WHITERIVER TO COAL MINE CANYON 2" AC + FR FEB 14
10517 DD1M 79 PN 122.5 STP - T MP 122.5 EXTEND PIPES AND CULVERTS TBD FY 16
11216 CV1M 60 PN 232.0 STP - G WEST OF PINTO CREEK BRIDGE ROCKFALL MITIGATION TBD FY 16
10114 DU1M 191 GH 101.0 STP - S MP 100.7 TO SR 266 DESIGN PARALLEL ROADWAY DESIGN FY 14
15015 DX1M 191 AP 418.0 STP - H BURNSIDE - CHINLE FENCING & CATTLE GUARDS TBD FY 15
15315 ED1M 264 AP 441.0 STP - H BURNSIDE - SUMMIT FENCE & CATTLE GUARD TBD FY 15
12916 DC1M 77 NA 384.0 STP - H 5 MILE WASH - JCT 377 CBC EXTENSION TBD FY 16
13913 QE1K 387 PN 0.0 STP - T JCT SR 84 / SR 287 TO SANTA CRUZ RIVER BRIDGE RR 4" TL, 3" PL & FOG COAT JUN 13
12516 LP1K 89A CN 538.0 STP - F COLORADO RIVER TO HOUSE ROCK (PHASE II) EXTEND PIPES AND CULVERTS TBD FY 16
11716 DJ1M 87 NA 346.0 STP - H I-40 TO JCT SR 264 CBC EXTENSIONS TBD FY 16
14113 DK1M 89A YV 330.0 STP - P FAIN ROAD TO SR-169 CORRIDOR LOCATION REPORT FOR RTE EVALU DESIGN FY 13
17914 DZ1M 260 YV 211.2 STP - P THOUSAND TRAILS ROAD NEW TAPERS TO STANDARD TBD FY 14
12316 EH1M 288 GI 289.0 STP - G SOUTH OF YOUNG ROCKFALL MITIGATION TBD FY 16
20313 CX1M 210 PM 1.0 STP - T AVIATION CORRIDOR IN TUCSON SIGN REHABILITATION TBD FY 13
11916 KZ1K 180 CN 216.1 STP - F NAVAJO RD - FLAGSTAFF CITY LIMITS WIDENING, C&G & DRAINAGE IMPROVEMENTS TBD FY 16
WK1L 940 MA 0.0 SR19101C STP -000-6(171)T E UNIVERSITY DR (TEMPE) 741-561J AT-GRADE RAILROAD CROSSING DESIGN AUG 13
17610 SX1J 10 PN 208.8 H769601C STP -010-D(205)A T SR 87 TI TO TOWN OF PICACHO CAPACITY ADDITIONS - ENGINEERING TBD FY 13
10313 GS1H 60 PN 222.0 STP -060-D(208)A G SILVER KING SECTION & SUPERIOR STREETS RECONSTRUCT TO 4 LANE RDWY W/CNT TURN L TBD FY 15
11008 EX1F 60 PN 230.0 STP -060-D(211)A G OAK FLAT - MIAMI CONSTRUCT PASSING/CLIMBING LANE FEB 14
17613 XI1J 60 GI 305.0 H778601C STP -060-E(211)A G FLYING V CANYON TO SQUAW DRESS RIDGE SLOPE STABILIZATION JUN 13
13615 CW1M 60 GI 302.0 STP -060-E(214)T G MP 302 - 311 RR 3" AC + AR-ACFC TBD FY 15
15913 WC1L 74 MA 22.4 STP -074-A(204)T E PICACHO WASH TRAIL TO JCT I-17 RR(5" TL, 3" PL) + AR ACFC SEP 13
15614 UB1J 77 AP 362.1 STP -077-B(208)A H NORTH SNOWFLAKE BOX CULVERT EXTENSION TBD FY 14
11508 AZ1G 86 PM 159.5 H680601C STP -086-A(210)T T VALENCIA RD - KINNEY RD CONSTRUCT ROADWAY WIDENING TO 4 LANES TBD FY 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 12 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
10116 TE1J 89 YV 320.4 H803901C STP -089-B(203)A P DEEP WELL RANCH ROAD TO SOUTH CHINO VALLEY CONSTRUCT ROADWAY WIDENING AUG 13
25113 FS1M 89 YV 327.0 STP -089-B(213)T P SR 89 @ ROAD 1 NORTH IN CHINO VALLEY DESIGN DESIGN FY 13
13313 RR1K 89 CN 476.6 H811601C STP -089-D(203)T F MOENKOPI WASH - HIDDEN SPRINGS 2.5" AC OVERLAY AND 1/2" AR-ACFC NOV 13
10012 KM1K 95 YU 0.0 H800301C STP -095-A(204)A Y INTERNATIONAL BORDER - JUAN SANCHEZ BLVD INFRASTRUCTURE IMPROVEMENTS FEB 13
19613 EJ1L 95 MO 250.0 STP -095-D(207)T K AVIATION WAY - BULLHEAD CITY PARKWAY PE PH 1 & 2 TO CONSTRUCT CONCRETE MEDIAN DESIGN FY 13
17414 DS1M 169 YV 4.8 STP -169-A(203)S P CHERRY ROAD CONSTRUCT TURN LANES / BOX EXTENSION TBD FY 14
YT1L 169 YV 5.1 H853601C STP -169-A(204)T P E OLD CHERRY RD - W CHERRY CREEK RD PAVEMENT PRESERVATION (MICRO-SURFACING MAR 13
15214 DR1M 169 MA 4.0 STP -169-A(205)S P PASSING LANES CONSTRUCT TURN AND PASSING LANES TBD FY 14
13513 RT1K 180 CN 216.2 H811801C STP -180-(202)T F COLUMBUS AVENUE - SNOW BOWL RR 3" & AR-ACFC & TURN LANES NOV 13
17514 MQ1J 180 AP 338.0 H752001C STP -180-B(204)A G BEAVER DAM - RANCH (EB & WB) 3" CIPR & FR AUG 13
IX1L 180 NA 307.3 H831801C STP -180-B(205)T H EAST OF SR 77 NEAR HOLBROOK PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13
17614 ST1K 186 CH 328.2 STP -186-A(200)A S WILLCOX TO KANSAS SETTLEMENT R & R 3" AC & CHIP SEAL APR 14
NF1L 191 GE 184.5 H841201C STP -191-C(215)T S GREY PEAK TO JUAN MILLER ROAD PAVEMENT PRESERVATION (DOUBLE CHIP SEAL APR 13
12010 EB1E 191 AP 446.3 H543801C STP -191-E(205) H CHINLE - SOUTH ROADWAY WIDENING TBD FY 13
15115 DY1M 191 AP 462.5 STP -191-E(212)T H MANY FARMS - APACHE CO. RD 508 FENCING WIDENING JUN 14
17714 QC1L 191 AP 477.9 STP -191-E(213)T H JCT N12 TO JCT US-160 REPLACE FENCE AND CATTLE GUARDS JUN 14
LL1L 999 CH 0.0 H832801C STP -999-A(328)T S SR 186 & B-10, COCHISE COUNTY WIDE PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13
18814 YJ1K 999 SW 0.0 H821701C STP -999-A(351)T Y BURNT WELL AND EHRENBURG REST AREAS WATER,STRUCTURAL,MECH & ELECTRICAL REH NOV 13
10810 IV1A 89A CN 399.0 H413401C STP -A89-B(009)A F SR 89A JW POWELL BLVD CONSTRUCT INTERSECTION IMPROVEMENTS JUN 13
16514 SE1K 89A CN 386.6 STP -A89-B(210)A F PUMPHOUSE WASH - OVERLOOK RR (3"AC, 2.5" AC + AR-ACFC) FULL WIDTH DEC 13
13714 MS1L 19B SC 0.1 STP -B19-A(201)A T INTERNATIONAL BORDER - MARIPOSA/SR189 RR 2" AC DEC 13
OD1K 0000 MO CLC SS87801C STP -CLC-0(201)A F JOHNSON AVENUE PAVEMENT PRESERVATION FY 13
MB1K 0000 PN CLG SS87301C STP -CLG-0(200)A T COOLIDGE AVENUE DESIGN / RECONSTRUCTION FY 14
QM1L 0000 CN FLA SZ01901C STP -FLA-0(213)D F SITGREAVES ST, MILTON TO SANTE FE CONSTRUCTION OF ADA RAMPS FY 13
OB1K 0000 MA MMA SS88101C STP -MMA-0(217)A E MCKELLIPS ROAD - SR101L TO ALMA SCHOOL ROADWAY RECONSTRUCTION FY 15
OA1K 0000 MA MMA SS87901C STP -MMA-0(218)A E GILBERT ROAD BRIDGE OVER THE SALT RIVER CONSTRUCT BRIDGE FY 15
PG1K 0000 MA MMA SS89401C STP -MMA-0(225)A E MCKELLIPS ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 16
PH1K 0000 MA MMA SS89301C STP -MMA-0(226)A E DOBSON ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 15
UK1K 0000 PN PPN STP -PPN-0(205)A T HUNT HIGHWAY - SYSTEM PRESERVATION - ENGINEERING FY 13
KQ1H 0000 MA MMA STP -QCR-0(001)A E RIGGS RD,ELLSWORTH TO MERIDIAN CONSTRUCT NEW ROADWAY FY 13
WU1J 0000 PM TUC SS73001C STP -TUC-0(226)A T PANTANO BOULEVARD PAVEMENT RECONSTRUCTION FY 13
PU1K 0000 PM TUC SS86501C STP -TUC-0(233)A T KOLB ROAD CONNECTION TO SABINO CANYON ROADWAY AND SIDEWALK IMPROVEMENTS FY 14
HS1K 0000 YU 0.0 SL64401C TEA -SOM-0(200)A Y US 96 BETWEEN SOMERTON AND BINGHAM AVENUES SYSTEM ENHANCEMENT-OTHER ENHANCEMENT FY 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
2ND SORT: FEDERAL ID # Page 13 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
PW1H 0000 PM TUC SS63201C TEA -TUC-0(203)B T CAMPBELL AVE - MAIN STREET MAIN STREET REVITALIZATION FY 13
HV1L 0000 MA WBG SL69001C TEA -WBG-0(201)D P 1962 HASSAYAMPA RIVER BRIDGE PEDESTRIAN/BICYCLE IMPROVEMENT FY 13
GA1L 0000 NA WIN SL71101C TEA -WIN-0(203)A H THE STATION AT LA POSADA REHAB OF STATION AND LANDSCAPE FY 14
EP1K 0000 PM TUC SS73601C TUC-0(227)A T TUCSON BOULEVARD MULTI-USE PATH MULTI-USE PATH FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 1 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
18713 MS1K 89 YV 333.1 H791901C 089-B(208)T P DEL RIO RANCH BRIDGE #20046 BRIDGE REPLACEMENT JAN 13
18313 MI1K 89 YV 335.9 H797601C 089-B(204)T P BIG CHINO WASH BRIDGE #979 DECK REPLACEMENT / WIDENING JAN 13
10412 DA1J 89 CN 464.5 H791501C NH -089-D(201)T F SR-64 TO LITTLE COLORADO RIVER CONSTRUCT 4-LANE URBAN, SR64 INTERSECTIO JAN 13
14513 PA1K 260 NA 310.0 H801201C NH -260-B(209)A G PIERCE WASH BRIDGE (STR # 1373) SCOUR RETROFIT JAN 13
22013 VX1K 999 MA 0.0 NH -999-A(215)T E VARIOUS LOCATIONS ON SR 101L AND I-17 PUMP STATION IMPROVEMENTS JAN 13
ZP1K 0000 YU YYU SS86101C STP - Y S. FRONTAGE ROAD - AVENUE 9E TO AVENUE13E PAVEMENT PRESERVATION FY 13
12013 SW1K 10 LA 63.0 H815901C 010-A(217)T Y GAS LINE RD - COUNTY LINE RR (1/2" TL, 4" PL) & AR-ACFC FEB 13
12513 IG1K 40 YV 132.1 H785701C K WEIGH STATION TO ASH FORK (WB) RR (5" TL, 3" PL) + FR FEB 13
OR1K 60 GI 290.0 H808301C 060-E(206)T G MP 290, 296 AND 320 AT HAGEN HILL ROCKFALL CONTAINMENT FEB 13
22413 YC1L 64 CN 0.0 H817202C FA - F RURAL INTELLIGENT TRANSPORTATION SYSTEMS - PH CONSTRUCT FEB 13
HY1L 66 MO 56.4 H809401X SB -AZ09(002) K KINGMAN POWERHOUSE VISITOR CENTER IMPROVEMENTS IGA FY 13
10312 LE1G 93 MO 101.8 H738801C NH -093-B(204)T K ANTELOPE WASH CONSTRUCT 4-LANE DIVIDED HIGHWAY FEB 13
10012 KM1K 95 YU 0.0 H800301C STP -095-A(204)A Y INTERNATIONAL BORDER - JUAN SANCHEZ BLVD INFRASTRUCTURE IMPROVEMENTS FEB 13
MO1K 95 YU 0.6 H801701C Y US95, 'A' ST TO JUAN SANCHEZ BLVD, SAN LUIS ROAD & PEDESTRIAN ENHANCEMENTS FEB 13
45913 EO1M 101L MA 6.0 STAN- E MARYLAND AVENUE CONSTRUCT DIRECT HOV RAMP (DESIGN BUILD) FEB 13
VS1L 101L MA 60.0 H848801C 101-C(201)A E GALVESTON DRAINAGE BASIN G (THUDE PARK) DRAINAGE IMPROVEMENT & PUMP STATION IGA FY 13
14413 RU1K 160 NA 358.1 H811901C F COUNTY LINE - BLACK MESA RR 3" & AR-ACFC FEB 13
11710 RJ1C 160 NA 375.2 H512001C NH -160-A(201)T H JCT SR 564 - TSEGI, PH I CONSTRUCT DUAL PASSING LANES FEB 13
QM1L 0000 CN FLA SZ01901C STP -FLA-0(213)D F SITGREAVES ST, MILTON TO SANTE FE CONSTRUCTION OF ADA RAMPS FY 13
VK1J 0000 GI GGI HPP -GGI-0(204)A G TONTO CREEK BRIDGE DESIGN BRIDGE APPROACHES FY 13
OC1K 0000 MA MES SS87701C CM -MES-0(216)A E LOCAL AGENCY WIDE - FIBER-OPTIC COMMUNICATION FIBER OPTICS FY 13
JN1L 0000 MA MMA SS97201C E UPGRADE RADS REGIONWIDE SYSTEM UPGRADE FY 13
JO1L 0000 MA MMA SS97301C E WEST VALLEY DMS INSTALL ARTERIAL DMS FY 13
ZS1J 0000 MA PHX CM -PHX-0(223)A E SALT RIVER PATHWAY - 24TH ST TO I-10 TEMPE DRAIN PATHWAY IMPROVEMENTS FY 13
UK1K 0000 PN PPN STP -PPN-0(205)A T HUNT HIGHWAY - SYSTEM PRESERVATION - ENGINEERING FY 13
XY1K 0000 MA QCR SS87601C CM -QCR-0(207)A E TOWNWIDE - ITS DEVELOPMENT SYSTEM ENHANCEMENT - TRAFFIC MGMT AND E FY 13
BX1L 0000 MA TMP SS95301C CM -TMP-0(217)A E SALT RIVER MUP: I-10/TEMPE DRAIN TO PRIEST DRIVE PATHWAY IMPROVEMENTS FY 13
PW1H 0000 PM TUC SS63201C TEA -TUC-0(203)B T CAMPBELL AVE - MAIN STREET MAIN STREET REVITALIZATION FY 13
15513 KV1L 10 CH 381.0 H837101C BR - S SAN SIMON RIVER BR (STR #1167,1168 & 230) SCOUR RETROFIT MAR 13
16713 KW1L 40 NA 271.0 H837201C BR - H MANILA WASH BRIDGES STR #851,852 & 2080 SCOUR RETROFIT MAR 13
12813 ZY1J 40 NA 303.1 H785901C IM -040-E(214)T H BIG LITHODENDRON-PETRIFIED FOREST NATIONAL PA PAVEMENT PRESERVATION MAR 13
12913 RX1K 69 YV 271.6 H812201C P BIG BUG 4 TO POLAND JCT RR 3" TL, RR AR-ACFC FULL WIDTH MAR 13
YJ1L 69 YV 292.1 H854001C NH -069-A(211)T P SUNRISE BLVD TO PRESCOTT CANYON DR PAVEMENT PRESERVATION (AR-ACFC) MAR 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 2 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
YT1L 169 YV 5.1 H853601C STP -169-A(204)T P E OLD CHERRY RD - W CHERRY CREEK RD PAVEMENT PRESERVATION (MICRO-SURFACING MAR 13
IX1L 180 NA 307.3 H831801C STP -180-B(205)T H EAST OF SR 77 NEAR HOLBROOK PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13
LL1L 999 CH 0.0 H832801C STP -999-A(328)T S SR 186 & B-10, COCHISE COUNTY WIDE PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13
OD1K 0000 MO CLC SS87801C STP -CLC-0(201)A F JOHNSON AVENUE PAVEMENT PRESERVATION FY 13
40913 CM1J 10 MA 122.0 H770901C NH - E PERRYVILLE ROAD TI CONSTRUCT TI APR 13
12213 SQ1K 10 CH 318.8 H815101C IM -010-F(216)T S DRAGOON RD - WEST WILLCOX TI (WB) PAVEMENT PRESERVATION APR 13
12413 RW1K 17 YV 245.0 H812101C P BLACK CANYON HILL (NB) RR (5" TL, 3" PL) & AR-ACFC APR 13
12613 NQ1L 40 CN 146.0 H840201C IM - F EAST ASHFORK TI TO WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC APR 13
NF1L 191 GE 184.5 H841201C STP -191-C(215)T S GREY PEAK TO JUAN MILLER ROAD PAVEMENT PRESERVATION (DOUBLE CHIP SEAL APR 13
HZ1L 0000 MA SCT SS96701C E PAVEMENT PRESERVATION PHASE 3 PAVEMENT PRESERVATION FY 13
UH1K 0000 MA SCT SS91301C CM -SCT-0(211)A E DYNAMITE BLVD - PIMA TO ALMA SCHOOL ROAD INSTALL CURB AND GUTTER FY 13
HV1L 0000 MA WBG SL69001C TEA -WBG-0(201)D P 1962 HASSAYAMPA RIVER BRIDGE PEDESTRIAN/BICYCLE IMPROVEMENT FY 13
17610 SX1J 10 PN 208.8 H769601C STP -010-D(205)A T SR 87 TI TO TOWN OF PICACHO CAPACITY ADDITIONS - ENGINEERING TBD FY 13
24013 BH1M 15 MO 15.0 H857401C 015-A(208)S F VIRGIN RIVER BRIDGE #6 (STR #1619) CMAR BRIDGE REHABILITATION CONSTRUCTION TBD FY 13
45313 TR1H 17 MA 215.0 H844501C CM -017-A(230)A E SR 101L (AGUA FRIA) TO ANTHEM WAY CONSTRUCT FMS MAY 13
QP1J 40 MO 66.5 IM -040-B(208)A K I-40, BLAKE RANCH RD TI IMPROVEMENTS TBD FY 13
16313 PY1E 40 YV 102.0 IM - K CROSS MT - JOLLY RD UPGRADE EXISTING ROCKFALL PROTECTION TBD FY 13
12613 RP1K 40 YV 146.2 F EAST ASHFORK TI - COUNTY LINE RR 3" & 2" AC & AR-ACFC TBD FY 13
12713 RQ1K 40 CN 158.6 F PINE SPRINGS - WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC TBD FY 13
16913 CL1M 40 NA 290.0 IM - H HOLBROOK - SUN VALLEY FENCING AND CATTLE GUARDS TBD FY 13
YQ1L 70 GH 347.0 H853801C S HAEKEL RD TO US 191 SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13
18113 NY1K 79 PN 101.8 H807501C BR -079-A(205)T T CORONADO WASH BRIDGE STRUCTURE #222 BRIDGE REPLACEMENT MAY 13
18213 DE1M 80 CH 317.0 STP - S TOMBSTONE REMOVE PEDESTRIAN BRIDGE TBD FY 13
18413 DF1M 83 SC 12.0 H850101C T MP 12 - MP 14 MILL AND PAVE TBD FY 13
14313 SB1K 87 GI 236.2 H812301C P JCT 188 - RYE RR 3" TL & AR-ACFC FULL WIDTH MAY 13
13409 TQ1H 87 GI 263.0 H718301C P TONTO NATURAL BRIDGE STATE PARK CONSTRUCT NEW ROAD TBD FY 13
JN1M 89 YV 345.7 H863601C K HELL CANYON BRIDGE DECK REHABILITATION TBD FY 13
13413 RS1K 89A CN 609.3 F FREDONIA - STATE LINE RR 3" & AR-ACFC TBD FY 13
XT1H 180 AP 402.0 G JCT SR 260 / US 180 & RODEO GROUNDS INTERSECTIO REALIGN INTERSECTION TBD FY 13
20213 OT1F 188 GI 254.0 STP - G ROOSEVELT - JAKES CORNER INSTALL DRAINAGE FACILITY CBC TBD FY 13
13613 SC1K 191 CH 38.2 HSIP- S JCT SR 181 - PEARCE ROAD 3" AC & AR-ACFC MAY 13
12010 EB1E 191 AP 446.3 H543801C STP -191-E(205) H CHINLE - SOUTH ROADWAY WIDENING TBD FY 13
YM1L 202L MA 9.0 H854301C E L101 TO MCDOWELL ROAD SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 3 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
43208 ST1H 202L MA 44.0 CM - E LINDSAY ROAD TO GILBERT ROAD DESIGN & CONST MULTI-USE PATH TBD FY 13
20313 CX1M 210 PM 1.0 STP - T AVIATION CORRIDOR IN TUCSON SIGN REHABILITATION TBD FY 13
20513 EB1M 260 GI 262.0 NH - P VARIOUS BRIDGE APPROACHES REPAIR BRIDGE APPROACHES TBD FY 13
14013 RO1K 587 PN 218.8 H811301C E SR 87 - JCT I-10 RR 3" & AR-ACFC MAY 13
23913 ZC1L 999 SW 0.0 HSIP-999-A(377)S F I-17 AND I-40, INLAID PAVEMENT MARKERS, SEGMENT I INLAID PAVEMENT MARKINGS TBD FY 13
XX1K 0000 MA CHN SS93201C E CONSOLIDATED CANAL MULTI-USE PATH PATHWAY/TRAIN IMPROVEMENTS FY 13
ZQ1F 0000 MA GDY SS54401C STP-GDY-0(008)A E YUMA RD @ BULLARD WASH CONST BOX CULVERTS FY 13
PI1K 0000 MA MES SS89101C CM -MES-0(217)A E ITS TRAFFIC SIGNAL CONVERSIONS - PHASE 5 FIBER-OPTIC COMMUNICATIONS NET FY 13
BB1L 0000 MA MMA SS83001C CM -MMA-0(214)A E OLIVE AVE: LITCHFIELD ROAD TO LOOP 101 INSTALL FIBER OPTIC CONDUIT FY 13
KQ1H 0000 MA MMA STP -QCR-0(001)A E RIGGS RD,ELLSWORTH TO MERIDIAN CONSTRUCT NEW ROADWAY FY 13
CC1L 0000 MA MMA SS95701C CM -MMA-0(231)A E 88TH AVE: DEER VALLEY TO WILLIAMS RD PAVE UNPAVED ROAD FY 13
PL1K 0000 MA MMA SS89901C CM -MMA-0(228)A E 87TH AVENUE PAVING DIRT ROAD FY 13
JQ1L 0000 MA SUR SS95801C E DOVE VALLEY ROAD,18TH AVE-203RD AVE ROADWAY IMPROVEMENTS FY 13
WU1J 0000 PM TUC SS73001C STP -TUC-0(226)A T PANTANO BOULEVARD PAVEMENT RECONSTRUCTION FY 13
BA1L 0000 YU YYU SB43701C BR -YYU-0(201)T Y COUNTY 19TH ST BRIDGE OVER MAIN DRAIN (AVE F 1/2 BRIDGE REPLACEMENT FY 13
15413 HJ1J 8 YU 7.2 HSIP- Y I-8 AND ARABY ROAD PE PH 1 AND 2 DESIGN FY 13
14913 YG1L 8 YU 125.0 Y GILA BEND TO I-10 SIGN REHABILITATION DESIGN FY 13
HC1J 10 LA 1.0 Y EHRENBERG EXIT 1 ROUNDABOUT JUN 13
45613 UU1L 10 MA 129.5 RARF- E DYSART ROAD TO SR 101L (AUGA FRIA FWY) LANDSCAPE CONSTRUCTION JUN 13
HB1M 10 PN 209.9 H861401C IM -010-D(217)T T LA PALMA RD TO PICACHO HWY DESIGN PAVEMENTPRESERVATION PROJECT DESIGN FY 13
10117 BY1M 15 MO 0.0 F SCENIC TO STATE LINE PE PH 1 & 2 DESIGN FY 13
15613 RH1L 17 MA 238.6 BR - P MOORES GULCH BRIDGE SB #339 DESIGN BRIDGE REPLACEMENT DESIGN FY 13
HT1M 17 YV 287.0 017-B( )T P VERDE RIVER BRIDGE NB #1731 DESIGN BRIDGE REHABILITATION DESIGN FY 13
13814 MT1L 19 SC 0.3 IM -019-A(216)A T INTERNATIONAL BORDER - JCT B-19 RR AR-ACFC JUN 13
HV1M 40 MO 83.0 040-B(220)T K WILLOW CREEK BRIDGE NO 2 EB (#1593) DESIGN BRIDGE REHABILITATION DESIGN FY 13
16413 IW1L 40 CN 180.8 IM -040-C(208)A F EAST OF PARKS ROCKFALL MITIGATION JUN 13
16613 CK1M 40 NA 226.0 IM - H EAST WINSLOW TI PE PH 1 & 2 DESIGN FY 13
GT1M 40 NA 289.0 040-D(227)T H E HOLBROOK TI OP EB#1369 & WB #1370 DESIGN BRIDGE REHABILITATION DESIGN FY 13
17413 CP1M 40 AP 322.0 NH - H CHAMBERS PORT OF ENTRY PE PH 1 & 2 DESIGN FY 13
IN1M 60 MA 109.9 060-A(207)S P US 60 @ APACHE STREET IN WICKENBURG DESIGN DESIGN FY 13
17613 XI1J 60 GI 305.0 H778601C STP -060-E(211)A G FLYING V CANYON TO SQUAW DRESS RIDGE SLOPE STABILIZATION JUN 13
HU1M 66 CN 91.0 066-A( )T K WASH BR #141 & TRUXTON WASH BR #142 DESIGN BRIDGE REHABILITATION DESIGN FY 13
17713 CZ1M 68 MO 20.0 STP - K MP 19, TURN LANES DESIGN & CONSTRUCT 3 EB TURN LANES DESIGN FY 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 4 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
15813 BX1M 69 YV 281.1 HX24201C HSIP-069-A(210)T P MP 281.1 - MP 289.7 MODIFY SIGNALS JUN 13
11413 AY1G 77 PM 82.0 H669401C 077-A(204)T T TANGERINE RD TO PINAL COUNTY LINE WIDENING TO 6 LANES - CONSTRUCTION JUN 13
18013 ZS1H 77 NA 367.0 STP - H FIVE MILE WASH BRIDGE PE PH 1 & 2 (WIDEN ROADWAY TO 4 LANES) DESIGN FY 13
GX1M 86 PM 120.6 086-A-NFA T FRESNAL TO MP 123.9 DESIGN DESIGN FY 13
FO1M 87 MA 177.8 087-B(220)T E SR87 @ MCDOWELL RD DESIGN SIGNAL IMPROVEMENT DESIGN FY 13
GG1M 87 GI 252.0 087-B(218)A P SR 87 / SR 260 SAFETY IMPROVEMENT ACCESS CONTROL, SIGNING UPGRADES, ADA, M DESIGN FY 13
16513 DH1M 87 CN 268.1 HSIP- P MP 268.1 - MP 278 PE PH 1 & 2 DESIGN FY 13
25113 FS1M 89 YV 327.0 STP -089-B(213)T P SR 89 @ ROAD 1 NORTH IN CHINO VALLEY DESIGN DESIGN FY 13
JE1L 89 YV 328.0 H833001C P PERKINSVILLE RD ROUNDABOUT SYSTEM ENHANCEMENT - ENGINEERING DESIGN FY 13
14213 DN1M 89 CN 420.0 NH - F FLAGSTAFF CITY LIMITS - LENOX PARK FEASIBILITY REPORT FOR ACCESS MGT PLANNI DESIGN FY 13
14113 DK1M 89A YV 330.0 STP - P FAIN ROAD TO SR-169 CORRIDOR LOCATION REPORT FOR RTE EVALU DESIGN FY 13
15208 NSSP 89A YV 365.0 F RED ROCK STATE PARK DESIGN DESIGN FY 13
10810 IV1A 89A CN 399.0 H413401C STP -A89-B(009)A F SR 89A JW POWELL BLVD CONSTRUCT INTERSECTION IMPROVEMENTS JUN 13
19213 LC1J 92 CH 324.3 H716701C HSIP-092-A(200)T S BUFFALO SOLDIER TRAIL TO KACHINA TRAIL RAISED MEDIAN JUN 13
19313 DP1M 93 MO 125.0 NH -093-B(211)T K MEDLIN CROSSOVER DESIGN AND CONSTRUCT NEW CROSSOVER DESIGN FY 13
FK1M 93 YV 185.3 093-B(210)T P SOUTH OF SR71 - NORTH OF SR89 DESIGN ROADWAY WIDENING DESIGN FY 13
19413 WY1L 95 LA 142.0 NH - Y SR 95 AT MOHAVE ROAD PE PH 1 & 2 DESIGN FY 13
HH1M 95 MO 239.0 095-D(208)T K SR 95 @ VALENCIA ROAD DESIGN DESIGN FY 13
SL1L 95 MO 239.5 095-D(204)T K STATE ROUTE 95 @ STERLING RD DESIGN INTERSECTION IMPROVEMENT DESIGN FY 13
19613 EJ1L 95 MO 250.0 STP -095-D(207)T K AVIATION WAY - BULLHEAD CITY PARKWAY PE PH 1 & 2 TO CONSTRUCT CONCRETE MEDIAN DESIGN FY 13
40313 DD1J 101L MA 23.5 E I-17 TO TATUM BLVD CONSTRUCT HOV LANE DESIGN FY 13
VX1L 101L MA 46.0 E SR101L, CHAPARRAL ROAD TO SR202L GP LANES DESIGN FY 13
GQ1M 180 AP 403.5 180-C(201)A G SEVERAL LOCATIONS ON US180 SYSTEM PRESERVATION - ENGINEERING DESIGN FY 13
20013 YU1L 180 AP 426.0 STP - G EAGER ALPINE INSTALL DRAINAGE FACILITY JUN 13
16512 DV1M 191 GH 104.0 STP - S SR 266 TO US 70 (REALIGNMENT) SCOPING DESIGN FY 13
GA1M 191 GE 226 H843901C G US-191, GLOBE DISTRICT, WALLOW FIRE, SIGN REPAIR SYSTEM PRESERVATION (RESTORATION/REHAB/ DESIGN FY 13
GP1M 191 AP 247.8 191-C(216)A G RIGHT OF WAY FENCE IN BOTH DIRECTIONS RIGHT OF WAY FENCING DESIGN FY 13
YL1L 202L MA 9.0 H854201C E L101 TO MESA DRIVE SYSTEM PRESERVATION (RESTORATION/REHAB/ JUN 13
BK1M 260 YV 218.9 P SR 260; INDUSTRIAL DR - HOMESTEAD PKWY DESIGN DESIGN FY 13
20613 MQ1L 260 NA 282.5 HSIP- P RIM RD TO GIBSON RD, SEGMENTS 1, 2 & 3 SHOULDER WIDENING PROGRAM, PE PH 1 & 2 DESIGN FY 13
GO1M 260 AP 385.5 260-C(205)A G RIGHT OF WAY FENCING TWO LOCATIONS EAST BOUN RIGHT OF WAY FENCING DESIGN FY 13
20713 EF1M 266 GH 104.0 STP - S JCT 191 - BONITA CHIP SEAL & GR RENEWAL JUN 13
45112 WB1L 303L MA 112.0 E PEORIA AVE - WADDELL RD LANDSCAPE CONSTRUCTION JUN 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 5 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
45212 OF1L 303L MA 114.0 RARF- E WADDELL ROAD TO MOUNTAIN VEIW ROAD CONSTRUCT LANDSCAPE JUN 13
45713 EU1M 303L MA 120.0 NH -303-A(215)T E EL MIRAGE RD DESIGN TI DESIGN FY 13
CY1M 347 PN 172.0 347-A(209)T T ALTERRA TO CASA BLANCA RD, CITY OF MARICOPA DESIGN DESIGN FY 13
13913 QE1K 387 PN 0.0 STP - T JCT SR 84 / SR 287 TO SANTA CRUZ RIVER BRIDGE RR 4" TL, 3" PL & FOG COAT JUN 13
WL1L 940 MA 0.0 SR19201C 000-6(172)A E 5TH ST (TEMPE) 741-560-C AT-GRADE RAILROAD CROSSING DESIGN JUN 13
21513 XV1K 999 SW 0.0 H820601C HSIP- E STATEWIDE TREE THINNING TREE REMOVAL FROM CLEAR ZONE, PE PH 1 & 2 DESIGN FY 13
PK1K 0000 MA GDY SS89601C CM -GDY-0(203)A E TRAFFIC SIGNAL SYSTEM ITS BACKBONE & COMMUNICATION FY 13
JP1L 0000 MA MMA SS97401C E ATIS ENHANCEMENTS REGIONWIDE ARTERIAL ATIS FY 13
CX1G 0000 PM MRN SB41301C BR-MRN-0(014)A T INA BRIDGE OVER SANTA CRUZ BRIDGE REPLACEMENT FY 13
MD1K 0000 NA PLS SS86401C HPP -PLS-0(201)A G BILLY CREEK BRIDGE @ PORTER MOUNTAIN ROAD CAPACITY ADDITIONS - MAJOR WIDENING FY 13
JM1L 0000 PM PPM SS97501C T VALENCIA ROAD: WADE RD TO MARK RD WIDEN ROADWAY FY 13
ZN1E 0000 PN PPN SB41001C BR -PPN-0-(169) G KELVIN BRIDGE - #8441 BRIDGE REPLACEMENT FY 13
HP1L 0000 MA TMP SS96401C E VARIOUS LOCATIONS:WIRELESS COMMUNICATIONS & PROCUREMENT AND INSTALLATION FY 13
UU1K 0000 PM TUC T SPEEDWAY BLVD UNDERPASS @ UPRR ROADWAY RECONSTRUCTION FY 13
EP1K 0000 PM TUC SS73601C TUC-0(227)A T TUCSON BOULEVARD MULTI-USE PATH MULTI-USE PATH FY 13
43914 XE1K 303L MA 118.0 H814501C E US 60 GRAND AVE / SR 303L TI, INTERIM CONSTRUCT INTERIM TI DEC 12
13214 RC1L 10 CH 333.0 IM -010-F(218)A S US 191 TO EAST WILLCOX TI RR (5" TL, 3" PL) & AR-ACFC JAN 14
13514 CF1L 17 MA 231.0 H826801C E NEW RIVER BRIDGES, STR # 1290 &1291 SCOUR RETROFIT JAN 14
13213 RN1K 88 MA 204.0 STP - E APACHE JCT - TORTILLA FLATS MILL 2" & 3" AC & CHIP SEAL JAN 14
17014 HL1L 92 CH 322.1 H826501C HSIP- S SR 92 @ FOOTHILLS DR INTERSECTION IMPROVEMENTS JAN 14
XD1L 0000 YU YYU SB44501C BR -YYU-0(205)A Y BRIDGE REHABILITATION OLD HWY 80 & AVE 30 1/2 E BRIDGE REHABILITATION FY 14
45309 FN1H 10 MA 96.2 H708301X Y 395TH AVE (BELMONT RD) CONSTRUCT TI IGA FY 14
44909 FM1H 10 MA 105.0 H683801X I -010-A-901 Y I-10/DESERT CREEK TI (PRIVATE FUNDS) CONSTRUCT TI IGA FY 14
12113 IP1L 10 MA 112.8 IM -010-A(216)A E SR 85 - VERRADO (EB) RR(4"TL, 3" PL) & AR-ACFC FEB 14
11008 EX1F 60 PN 230.0 STP -060-D(211)A G OAK FLAT - MIAMI CONSTRUCT PASSING/CLIMBING LANE FEB 14
QJ1L 60 NA 341.0 HX23901C G US 60 & 9TH PLACE, SHOW LOW TRAFFIC SIGNAL FEB 14
13113 FF1G 73 NA 342.3 STP - G WHITERIVER TO COAL MINE CANYON 2" AC + FR FEB 14
80899 S9SP 101L MA 73.0 H387501C RARF-101-B E PIMA ROAD EXTENSION, JPA CONSTRUCT ROADWAY IGA FY 14
17814 SK1K 191 AP 482.0 H813201C STP - H ROUND ROCK - JCT. US 160 3" AC & AR-ACFC FEB 14
PU1K 0000 PM TUC SS86501C STP -TUC-0(233)A T KOLB ROAD CONNECTION TO SABINO CANYON ROADWAY AND SIDEWALK IMPROVEMENTS FY 14
11914 CG1L 8 PN 163.0 H827001C T SANTA ROSA WASH BRIDGES, STR # 1092 & 1093 SCOUR RETROFIT MAR 14
16914 VY1L 90 CH 321.0 H849701C HSIP-090-A(205)A S SR 92 - GIULIO CESARE AVENUE LIGHTING MAR 14
43414 WY1K 101L MA 41.0 H848401C E SHEA BLVD TO CHAPARRAL ROAD CONSTRUCT GPL MAR 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 6 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
14414 EV1L 40 CN 218.7 H789001C IM - F CANYON PADRE BRIDGE, STR #1670 DECK REPLACEMENT APR 14
19414 HS1L 89 YV 330.0 H827801C P ROAD 4 NORTH CONSTRUCT ROUNDABOUT APR 14
17214 XL1L 95 LA 149.2 HSIP-095-C(216)A Y CIENEGA SPRINGS RD SB LEFT TURN LANE APR 14
17614 ST1K 186 CH 328.2 STP -186-A(200)A S WILLCOX TO KANSAS SETTLEMENT R & R 3" AC & CHIP SEAL APR 14
KJ1K 8 MA 117.0 H800001C Y I-8 TO GILLESPIE CANAL REMOVE 3", REPLACE 2.5" & ACFC TBD FY 14
12314 YD1L 10 MA 144.9 IM -010-C(209)T E 3RD AVENUE TO 3RD STREET, DECK PARK TUNNEL DRAINAGE IMPROVEMENTS TBD FY 14
12014 BR1M 10 MA 145.0 IM - E 3RD AVENUE TO 3RD STREET PUMP STATION IMPROVEMENTS TBD FY 14
12414 FY1L 10 MA 162.0 IM -010-C(204)T E WILD HORSE PASS TO SR 347 (QUEEN CREEK ROAD) ROADWAY WIDENING TBD FY 14
12514 BT1M 10 MA 164.0 IM - E WILD HORSE PASS - RIGGS RR(5" TL - 3" PL) + AR-ACFC TBD FY 14
13914 CC1M 19 SC 9.0 STP - T I-19 FRONTAGE ROAD, NB DRAINAGE REPAIR TBD FY 14
14114 SM1K 40 MO 57.0 IM -040-B(213)A K RATTLESNAKE WASH - JCT US 93 RR(5" TL, 3" PL) & AR-ACFC TBD FY 14
14714 QO1L 40 NA 303.0 IM - H ADAMANA TI DRAINAGE IMROVEMENTS TBD FY 14
NL1L 60 MA 143.0 E US60/THUNDEBIRD ROAD INTERSECTION RECONSTRUCT TI TBD FY 14
UV1L 60 MA 144.0 E US 60 / BELL ROAD TI DCR AND ENVIRONMENTAL ASSESSMENT TBD FY 14
41814 WX1K 60 MA 148.9 E SR 101L, AGUA FRIA TO VAN BUREN STREET, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 14
40613 NM1L 60 MA 194.0 NH -060-C(207)T E MERIDIAN ROAD. HALF TI CONSTRUCT TI TBD FY 14
14914 CU1M 60 GI 229.4 HSIP- G MP 229.4 - MP 232.91 SHOULDER WIDENING TBD FY 14
10311 CY1J 77 PN 100.0 H739101C T ORACLE STATE PARK CONSTRUCT PARKING TBD FY 14
15614 UB1J 77 AP 362.1 STP -077-B(208)A H NORTH SNOWFLAKE BOX CULVERT EXTENSION TBD FY 14
15914 GR1G 82 SC 36.5 STP - T SR-82, MP 36.5 - 36.9 EXTEND 2 CBC'S AND ELIMINATE GUARDRAIL TBD FY 14
NK1L 85 PM 42.0 T WELCOME ST. TO MP 42.5 SYSTEM PRESERVATION - ENGINEERING TBD FY 14
44811 ZN1J 85 MA 153.2 H800601C NH - E WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE TBD FY 14
11508 AZ1G 86 PM 159.5 H680601C STP -086-A(210)T T VALENCIA RD - KINNEY RD CONSTRUCT ROADWAY WIDENING TO 4 LANES TBD FY 14
13209 A6SP 87 NA 346.0 H717901C H HOMOLOVI RUINS STATE PARK CONSTRUCT ROAD TBD FY 14
XA1L 89 YV 345.0 089-B(211)T K HELL CANYON BRIDGE #483 REPLACEMENT & WIENING TBD FY 14
16314 DM1M 89 YV 349.0 STP - P JCT SR 260 (COTTONWOOD) CONSTRUCT DUAL RIGHT TURN LANES TBD FY 14
16414 IS1J 89 CN 385.1 H741801C A89-B(204)A F OAK CREEK CANYON CREEK BANK PROTECTION TBD FY 14
16614 HO1L 89 CN 403.0 STP - F JCT SR 89A / PLAZA WAY (FLAGSTAFF) DRAINAGE IMPROVEMENTS TBD FY 14
16714 FD1L 89 CN 523.9 NH - F BITTER SPRINGS INSTALL INTERSECTION LIGHTING TBD FY 14
16814 HG1L 89 CN 551.0 NH - F PAGE MAINTENANCE YARD WIDENING FOR TURN LANES TBD FY 14
10910 DJ1G 90 CH 323.5 H655501C S CENTRAL AVE TO MOSON RD, E OF SIERRA VISTA WIDEN TO 5 LANES TBD FY 14
KK1L 93 MO 139.0 HPP -093-B(209) K US 93, SB BURRO CREEK BRIDGE SYSTEM PRESERVATION - ENGINEERING TBD FY 14
OP1L 101L MA 23.0 E SR 101L PIMA (I-17-PRINCESS DR) GP LANES DCR/ED CAPACITY ADDITIONS - ENGINEERING TBD FY 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 7 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
17314 FN1L 160 CN 343.4 NH -160-A(203)A F TONALEA INSTALL INTERSECTION LIGHTING TBD FY 14
15214 DR1M 169 MA 4.0 STP -169-A(205)S P PASSING LANES CONSTRUCT TURN AND PASSING LANES TBD FY 14
17414 DS1M 169 YV 4.8 STP -169-A(203)S P CHERRY ROAD CONSTRUCT TURN LANES / BOX EXTENSION TBD FY 14
14112 AI1K 191 CH 61.5 H788301C 191-A(203)A S COCHISE POWER PLANT - JCT I-10 RR 2" AC + 3" AC + FR TBD FY 14
41608 TY1H 202L MA 0.0 E I-10 EAST/SANTAN TI TO 51ST AVE DESIGN ROADWAY TBD FY 14
44814 TX1H 202L MA 47.8 CM -888-A(218)T E DOBSON ROAD TO I-10, MARICOPA CONSTRUCT FMS TBD FY 14
17914 DZ1M 260 YV 211.2 STP - P THOUSAND TRAILS ROAD NEW TAPERS TO STANDARD TBD FY 14
18214 SH1K 260 NA 321.4 NH -260-B(216)A G COTTONWOOD WASH - SHOW LOW RR 3" AC & AR-ACFC TBD FY 14
18414 EE1M 264 AP 446.0 STP - H GANADO SECTION WIDENING TO 3 LANES & TL TBD FY 14
16914 AE1K 264 AP 459.0 H786301C STP - H CROSS CANYON - SUMMIT 2" AC & AR-ACFC TBD FY 14
45213 NU1L 303L MA 0.0 E I-10/303L TI, PHASE I (I-10 REALIGNMENT) CONSTRUCT LANDSCAPE TBD FY 14
IZ1K 303L MA 3.8 E SR 303L, RIGGS RD - SR 801 SYSTEM ENHANCEMENT-ENGINEERING TBD FY 14
MZ1H 303L MA 5.0 NH -303-A(ASO) E I-10, MC 85 TO I-10 NEW 303 EXTENSION SOUTH TBD FY 14
44913 OE1L 303L MA 105.0 H850401C RARF- E THOMAS ROAD TO CAMELBACK ROAD CONSTRUCT LANDSCAPE TBD FY 14
JG1H 801 MA 0.0 E SR 303L TO SR 202L STUDY TBD FY 14
YH1H 801 MA 0.0 E SR 801, SR 85 TO SR 303L NEW ROADWAY CONSTRUCTION TBD FY 14
12914 EI1M 999 SW 0.0 HSIP- X STATEWIDE GUARDRAIL DELINEATORS TBD FY 14
HS1K 0000 YU 0.0 SL64401C TEA -SOM-0(200)A Y US 96 BETWEEN SOMERTON AND BINGHAM AVENUES SYSTEM ENHANCEMENT-OTHER ENHANCEMENT FY 14
22910 YS1K 0000 CH DGS SS87401C DGS-0(200)A S CHINO ROAD NEW FACILITIES - CONSTRUCTION OF NEW ROA FY 14
NG1L 0000 MA PHX PHX-0(266)A E BLACK MOUNTAIN BLVD, SR 51/SR 101 NEW ROADWAY FY 14
XZ1K 0000 YU SOM Y SOMERTON CANAL MUP:US95 TO COUNTY 17TH STRE SYSTEM ENHANCEMENT - ENGINEERING FY 14
11614 BM1M 8 YU 1.0 IM - Y WB OFF RAMP & GISS PARKWAY INTERSECTION INTERSECTION IMPROVEMENTS JUN 14
11714 BN1M 8 YU 2.0 IM - Y 16TH STREET LANDSCAPING JUN 14
11414 CU1J 17 YV 232.0 P ROCK SPRINGS TO CORDES JUNCTION PE PH2 (WIDEN ROADWAY) DESIGN FY 14
14214 CJ1M 40 CN 185.0 IM - F TRANSWESTERN - LEUPP JCT PE PH 1 & 2 DESIGN FY 14
11514 QN1C 40 AP 357.5 NH - H WINDOW ROCK TI PE PH 1 DESIGN FY 14
14310 QQ1K 40 AP 358.5 H LUPTON TI DCR AND ENVIRONMENTAL STUDIES DESIGN FY 14
15114 GN1J 70 GH 295.0 S BYLAS TWLTL & ROADWAY WIDENING JUN 14
19214 HM1L 77 PN 105.4 H826701C HSIP- T POWER LINE - SAN MANUEL ROAD DESIGN SHOULDER WIDENING DESIGN FY 14
16214 JD1L 88 PN 196.0 H830801C HSIP- E SUPERSTITION BLVD CONSTRUCT ROUNDABOUT JUN 14
19314 NC1H 88 MA 203.4 H700501C HSIP- E SR88, APACHE TRAIL GOLDFIELD TO CANYON LAKE SPOT SAFETY IMPROVEMENTS JUN 14
17114 IP1K 93 MO 17.4 HSIP- K MP 17.4 - MP 58.4 PE PH 1 & 2 DESIGN FY 14
10114 MG1E 191 GH 100.7 S SR 266 TO ARTESIA DESIGN PARALLEL ROADWAY DESIGN FY 14
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 8 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
10114 DU1M 191 GH 101.0 STP - S MP 100.7 TO SR 266 DESIGN PARALLEL ROADWAY DESIGN FY 14
15115 DY1M 191 AP 462.5 STP -191-E(212)T H MANY FARMS - APACHE CO. RD 508 FENCING WIDENING JUN 14
17714 QC1L 191 AP 477.9 STP -191-E(213)T H JCT N12 TO JCT US-160 REPLACE FENCE AND CATTLE GUARDS JUN 14
45314 EQ1M 202L MA 0.0 NH - E 24TH ST - 17TH AVE, SEGMENT 2 DESIGN NEW FREEWAY DESIGN FY 14
45414 ET1M 202L MA 0.0 IM - E I-10 PAPAGO/ SR202L SYSTEM INTERCHANGE SEGMEN DESIGN NEW SYSTEM TI DESIGN FY 14
41213 YR1K 202L MA 9.0 RARF- E SR 101 TO GILBERT ROAD DESIGN GENERAL PURPOSE LANES DESIGN FY 14
18314 HR1L 264 AP 441.1 H824601C HSIP- H US 191 TO SAWMILL ROAD SEGMENT 1 SHOULDER WIDENING PROGRAM PE PH 1 & PH 2 DESIGN FY 14
XX1G 264 AP 446.0 264-A(212)T H GANADO WASH BRIDGE #1046 DESIGN BRIDGE REPLACEMENT DESIGN FY 14
43814 OB1L 303L MA 107.0 E CAMELBACK ROAD TO GLENDALE AVENUE CONSTRUCT LANDSCAPE JUN 14
45113 OC1L 303L MA 109.0 H860301C RARF- E GLENDALE AVE TO PEORIA AVE CONSTRUCT LANDSCAPE JUN 14
12214 VX1J 10 MA 105.0 H775001C IM - E SR 85 TO DYSART (VERRADO WAY TO 85) SIGN REHABILITATION JUL 13
14514 EE1K 40 NA 254.6 IM -040-D(213)A H RUBY WASH BRIDGE - E WINSLOW TI OP BRIDGE REHABILITATION JUL 13
14614 SJ1K 40 NA 290.2 H813101C IM -040-D(219)A H HOLBROOK - SUN VALLEY RR (5"TL, 3"PL) & AR-ACFC JUL 13
15514 NH1L 77 GI 147.6 H832201C BR -077-A(207)A G DRIPPING SPRING BRIDGE #398 BRIDGE REPLACEMENT JUL 13
16114 VM1K 87 CN 323.9 BR -087-C(203)A H LIMESTONE WASH BRIDGE # BRIDGE REPLACEMENT JUL 13
WJ1L 0000 MA 0.0 SR23201C E DOBSON ROAD, AAR/DOT NO. 741-649-G SYSTEM ENHANCEMENT-SAFETY IMPROVEMENT FY 14
ZJ1K 0000 MA SUR SS85401C CM -SUR-0(210)A E BELL RD-US 60 TO 114TH AVE CONSTRUCT MULTI-USE PATH FY 14
12714 AZ1M 10 PM 268.0 IM -010-D(215)T T I-19 TO CRAYCROFT ROAD IN TUCSON SIGN REHABILITATION AUG 13
17913 LX1G 75 GE 384.0 075-A(200)T S LITTLE SANDS WASH BANK PROTECTION AUG 13
15414 JG1K 77 PN 123.5 H796901C T ARAVAIPA CREEK BRIDGE, STR #399 BRIDGE REPLACEMENT AUG 13
10116 TE1J 89 YV 320.4 H803901C STP -089-B(203)A P DEEP WELL RANCH ROAD TO SOUTH CHINO VALLEY CONSTRUCT ROADWAY WIDENING AUG 13
17514 MQ1J 180 AP 338.0 H752001C STP -180-B(204)A G BEAVER DAM - RANCH (EB & WB) 3" CIPR & FR AUG 13
WK1L 940 MA 0.0 SR19101C STP -000-6(171)T E UNIVERSITY DR (TEMPE) 741-561J AT-GRADE RAILROAD CROSSING DESIGN AUG 13
15913 WC1L 74 MA 22.4 STP -074-A(204)T E PICACHO WASH TRAIL TO JCT I-17 RR(5" TL, 3" PL) + AR ACFC SEP 13
19514 DT1M 188 GI 240.0 STP - G WINDY HILL INSTALL DRAINAGE FACILITY CBC SEP 13
WM1L 5013 MA 0.0 SR14401C 501-3(001)P E 32ND ST ( PHX) #741-536-B SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13
WN1L 7018 MA 0.0 SR09701C 701-8(003)P E 40TH ST PHOENIX 741-539-W SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13
18514 EG1M 288 GI 260 STP - G ROOSEVELT - YOUNG CBC EXTENSION OCT 13
ZV1L 0000 YU SLS CBI -SLS-0(201)A Y WIDENING AVE E FROM COUNTY 25TH STREET TO SR1 SYSTEM ENHANCEMENT (ENGINEERING) FY 14
GA1L 0000 NA WIN SL71101C TEA -WIN-0(203)A H THE STATION AT LA POSADA REHAB OF STATION AND LANDSCAPE FY 14
11814 SV1K 8 YU 13.7 H815801C IM - Y FOOTHILLS BLVD - DOME VALLEY RR (5" TL, 3" PL) & FR NOV 13
11913 TI1K 8 PN 170.0 IM - T BIANCO ROAD - JCT I-10 RR(5" TL, 3" PL) & AR-ACFC NOV 13
12814 NB1K 10 PM 283.6 H805201C IM -010-E(208)A T DAVIDSON CANYON - COUNTY LINE MILL AND REPLACE NOV 13
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 9 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
WQ1L 19 PM 59.0 H771401C T SAN XAVIER PEDESTRIAN BRIDGE PEDESTRIAN BRIDGE IMPROVEMENTS NOV 13
13313 RR1K 89 CN 476.6 H811601C STP -089-D(203)T F MOENKOPI WASH - HIDDEN SPRINGS 2.5" AC OVERLAY AND 1/2" AR-ACFC NOV 13
13812 AH1K 89 CN 510.0 NH -089-D(202)A F GRAY SPOT WASH - NORTH RED HILL 3" AC + FR NOV 13
13513 RT1K 180 CN 216.2 H811801C STP -180-(202)T F COLUMBUS AVENUE - SNOW BOWL RR 3" & AR-ACFC & TURN LANES NOV 13
18814 YJ1K 999 SW 0.0 H821701C STP -999-A(351)T Y BURNT WELL AND EHRENBURG REST AREAS WATER,STRUCTURAL,MECH & ELECTRICAL REH NOV 13
13614 SO1K 17 YV 269.2 IM -017-B(218)A P DUGAS TI - CHERRY ROAD RR (5" TL, 3" PL) & AR-ACFC DEC 13
13714 MS1L 19B SC 0.1 STP -B19-A(201)A T INTERNATIONAL BORDER - MARIPOSA/SR189 RR 2" AC DEC 13
14314 SD1K 40 CN 204.0 IM - F WALNUT CANYON - TWIN ARROWS RR 3" & 2" AC & AR-ACFC DEC 13
14814 RE1L 60 MA 115.5 BR -060-B(209)T P MONARCH WASH BR, STR #204 & 759 SCOUR RETROFIT DEC 13
15014 BT1L 60 GI 292.0 H826201C 060-E(207)A G SALT RIVER CANYON REST AREA REPLACE COMPOSTING TOILETS & STRUCTURA DEC 13
16514 SE1K 89A CN 386.6 STP -A89-B(210)A F PUMPHOUSE WASH - OVERLOOK RR (3"AC, 2.5" AC + AR-ACFC) FULL WIDTH DEC 13
MB1K 0000 PN CLG SS87301C STP -CLG-0(200)A T COOLIDGE AVENUE DESIGN / RECONSTRUCTION FY 14
13415 CN1M 40 NA 297.0 IM - H SUN VALLEY ROAD - WASHBOARD ROAD RR (5" TL, 3" PL) + 2"AC + FC JAN 15
17013 QD1L 40 NA 298.0 IM - H MP 298 UTILITY OVERPASS DESIGN OF CBC EXTENSION JAN 15
16006 QT1F 101L MA 53.5 E BALBOA DRIVE CONSTRUCT MULTI-USE PATH BRIDGE OVER TH IGA FY 15
15714 WH1K 80 CH 316.5 H800402C HSIP- S TOMBSTONE, MP 316.5 TO MP 318.0 LIGHTING AND SIDEWALKS MAR 15
13003 FR1C 8 YU 55.9 H206001C IM - Y MOHAWK REST AREA CONSTRUCT REST AREA TBD FY 15
40115 WU1K 10 MA 0.0 E SKY HARBOR WEST AIRPORT ACCESS CONSTRUCT ACCESS RAMPS TBD FY 15
11615 XP1L 10 LA 17.5 IM - Y WEST QUARTZSITE TI INTERSECTION IMPROVEMENTS TBD FY 15
11715 BA1M 10 LA 42.0 IM - Y MP 42 TO HOVATTER ROAD RR(4" TL, 3" PL) + AR-ACFC TBD FY 15
12407 FX1C 10 MA 161.2 H505101C E SR 202L (SANTAN) TO RIGGS ROAD CONST HOV & GEN PURPOSE LANE TBD FY 15
10015 QL1J 10 PM 247.0 H758301C T INA RD TO RUTHRAUFF RD RECONSTRUCTION FOR WIDENING TBD FY 15
10015 VH1L 10 PM 252.0 NH - T RUTHRAFF ROAD TI RECONSTRUCTION FOR WIDENING TBD FY 15
11815 NA1L 10 PM 284.4 IM -010-E(213)A T DAVIDSON CANYON WB BRIDGE, STR #598 SUPERSTRUCTURE REPLACEMENT TBD FY 15
11915 BU1M 10 CH 296.0 IM - T MESCAL ROAD TO JCT SR 90 RR(5" TL, 3" PL) + AR-ACFC TBD FY 15
12015 WD1L 10 CH 306.7 IM -010-F(219)A S SAN PEDRO RIVER BRIDGE EB #1530 & WB #1531 DECK REPLACEMENT & SCOUR RETROFIT TBD FY 15
12115 YB1K 10 CH 320.5 H821101C IM - S TEXAS CANYON REST AREA WATER, STRUCTURAL, MECHANICAL & ELECTRI TBD FY 15
12215 YI1K 10 CH 388.0 H821601C IM - S SAN SIMON REST AREA NEW WELL,WATER PUMPS,STRUC,ELECT,MECH TBD FY 15
12315 BW1M 15 MO 0.0 IM - F NEVADA STATE LINE - MP 13 RR(4" TL, 3" PL) AR-ACFC TBD FY 15
12415 VT1K 17 MA 195.0 E BUCKEYE RD,GRANT ST,ADAMS ST & JEFFERSON ST ELECTRICAL REHABILITATION TBD FY 15
12515 BZ1M 17 MA 198.0 IM - E BUCKEYE RD, GRANT,JEFFERSON & ADAMS ELECTRICAL REHABILITATION TBD FY 15
12415 HW1L 17 MA 202.3 IM - E INDIAN SCHOOL ROAD - PEORIA AVENUE SIGN REHABILITATION TBD FY 15
12615 CA1M 17 YV 279.6 IM - P SR 169 TO MIDDLE VERDE ROAD RR(5" TL, 3" PL) + AR-ACFC TBD FY 15
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 10 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
12715 SU1K 19 SC 16.0 IM - T PALO PARADO - CHAVEZ SLIDING TI RR (4" TL, 3" PL) + FR TBD FY 15
12915 CF1M 40 MO 74.0 IM - K HWY 141 JCT TO SILVER SPRINGS ROAD (WB) RR (5"TL, 3" PL) + AR-ACFC + SHOULDERS TBD FY 15
13015 CI1M 40 MO 87.0 IM -040-B(217)T K WILLOW RANCH ROAD TO MP 92, EB RR (5" TL, 3" PL) + AR-ACFC WITH SHOULDERS E TBD FY 15
13115 WT1L 40 YV 144.0 IM -089-B(214)T K ASHFORK RR BR - JCT SR 89, #807,#440, #1760,#1761 BRIDGE DECK REHABILITATION TBD FY 15
13315 JL1K 40 NA 284.3 BR -040-D(223)A H LEROUX WASH BRIDGE EB #1772 & WB #1773 BRIDGE REPAIR TBD FY 15
23701 ZY1D 40 AP 340.0 H552601C 040-E(001) H SANDERS PORT OF ENTRY RECONSTRUCT POE TBD FY 15
12815 CE1M 40F MO 47.8 IM -999-A(398)T K SOUTH OF KINGMAN ROCKFALL MITIGATION TBD FY 15
13515 CQ1M 60 MA 189.0 STP - E SOSSAMAN - MERIDIAN DRAINAGE IMPROVEMENTS TBD FY 15
10313 GS1H 60 PN 222.0 STP -060-D(208)A G SILVER KING SECTION & SUPERIOR STREETS RECONSTRUCT TO 4 LANE RDWY W/CNT TURN L TBD FY 15
16515 ZA1L 60 PN 228.8 G EAST OF QUEEN CREEK TUNNEL ROCKFALL MITIGATION TBD FY 15
13615 CW1M 60 GI 302.0 STP -060-E(214)T G MP 302 - 311 RR 3" AC + AR-ACFC TBD FY 15
23213 BM1L 64 CN 234.5 H825801C F GRAND CANYON AIRPORT- FS RD 328 SHOULDER WIDENING TBD FY 15
13715 KX1L 70 GI 259.0 H835901C G GILSON WASH BRIDGE, STR # 464 SCOUR RETOFIT TBD FY 15
13815 SR1K 75 GE 379.1 S DUNCAN BRIDGE - LITTLE SANDS WASH 3" AC & AR-ACFC TBD FY 15
14015 YZ1L 77 GI 156.8 G NEAR SUMMIT ROCKFALL MITIGATION TBD FY 15
14115 GP1G 82 SC 40.5 STP - T SR-82 AT MP 40.6 EXTEND CBC & ELIMINATE GUARDRAIL TBD FY 15
GU1M 86 PM 114.7 086-A(211)T T TOWN OF SELLS PEDESTRIAN BRIDGES CONSTRUCT PEDESTRIAN BRIDGE TBD FY 15
14215 KI1L 86 PM 115.8 T TOWN OF SELLS TO FRESNAL WIDEN SHOULDERS AND CULVERT EXTENSIONS TBD FY 15
16615 XT1K 87 GI 226.0 H820701C NH - P SLATE CREEK ROAD REPAIR TBD FY 15
14415 SP1K 89 YV 258.3 STP - P JCT US 93 - JCT SR 71 RR 3" & AR-ACFC TBD FY 15
11515 QQ1H 89 CN 452.6 H705601C NH - F SOUTH OF GRAY MOUNTAIN PASSING LANES (NB AND SB) TBD FY 15
14515 FP1L 89 CN 525.0 NH - F JCT US 89A - BIG CUT EP (PIPE) DROP-OFF MITIGATION TBD FY 15
16215 DL1M 89A YV 343.0 STP - P SOUTH OF JEROME ROCKFALL MITIGATION TBD FY 15
16315 UZ1J 89A CN 525.0 STP - F JCT US 89 - COLORADO RIVER EXTEND PIPES AND CULVERTS TBD FY 15
14615 JR1L 92 CH 340.5 BR -092-A(203)A S SAN PEDRO RIVER BRIDGE #449 BRIDGE REPLACEMENT TBD FY 15
14715 SF1K 180 AP 386.3 STP - G GENERATING STATION ROAD - JCT US 60 RR 3" & CHIP SEAL TBD FY 15
14815 SG1K 180 AP 407.0 STP - G JUAN CARILLO - FH275 RR 3" AC & AR-ACFC TBD FY 15
14915 ZA1J 191 CH 331.0 STP - S I-10/ US 191 TI AT MP 331 CONSTRUCT IMPROVEMENTS TBD FY 15
15015 DX1M 191 AP 418.0 STP - H BURNSIDE - CHINLE FENCING & CATTLE GUARDS TBD FY 15
41015 NX1L 202L MA 0.0 E BASELINE - SALT RIVER, SEGMENT 6 CONSTRUCT NEW FREEWAY TBD FY 15
43514 WZ1K 202L MA 0.0 RARF- E 17TH AVE TO 51ST AVE, SEGMENT 3 CONSTRUCT NEW FREEWAY TBD FY 15
41215 XC1K 202L MA 43.0 CM - E VAL VISTA DR. - DOBSON RD CONSTRUCT FMS TBD FY 15
15315 ED1M 264 AP 441.0 STP - H BURNSIDE - SUMMIT FENCE & CATTLE GUARD TBD FY 15
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 11 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
16815 SL1K 264 AP 441.0 STP - H BURNSIDE - CROSS CANYON 2" AC & AR-ACFC TBD FY 15
15515 JC1H 286 PM 20.0 H690701C STP - T SR 286 (SASABE - ROBLES RANCH HWY) REPAIR HEADCUTTING PROBLEMS AT LW WATE TBD FY 15
43015 EW1M 303L MA 0.0 RARF- E US 60 GRAND AVE / SR 303L TI, INTERIM LANDSCAPE CONSTRUCTION TBD FY 15
15615 YC1K 999 SW 0.0 H821301C STP - T SACATON & CANOA RANCH REST AREAS WATER/WASTEWATER, STRUC & ELECTICAL RE TBD FY 15
16115 XX1L 999 SW 0.0 FA -999-A(383)T E STATEWIDE DYNAMIC MESSAGE SIGN PHASE 10 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 15
15815 QH1L 999 MA 0.0 STP - E VARIOUS LOCATIONS DRAINAGE TUNNEL IMPROVEMENTS TBD FY 15
OB1K 0000 MA MMA SS88101C STP -MMA-0(217)A E MCKELLIPS ROAD - SR101L TO ALMA SCHOOL ROADWAY RECONSTRUCTION FY 15
PH1K 0000 MA MMA SS89301C STP -MMA-0(226)A E DOBSON ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 15
OA1K 0000 MA MMA SS87901C STP -MMA-0(218)A E GILBERT ROAD BRIDGE OVER THE SALT RIVER CONSTRUCT BRIDGE FY 15
11112 CO1J 10 PM 236.4 T MARANA ROAD TO CORTARO ROAD DESIGN (RECONSTRUCT & WIDEN FRONTAGE R DESIGN FY 15
10511 XQ1L 95 MO 182.0 K LAKE HAVASU STATE PARK (CONTACT POINT) PH II DESIGN PARKING DESIGN FY 15
42115 ER1M 202L MA 0.0 IM - E ELLIOT RD - BASELINE RD, SEGMENT 5 DESIGN NEW FREEWAY DESIGN FY 15
10612 QP1C 60 NA 342.0 H510701C G SHOW LOW TO LITTLE MORMON LAKE WIDEN ROADWAY JUL 14
LK1K 0000 MA TMP SS73401C CM -TMP-0(210)X E BROADWAY ROAD: RURAL TO MILL AVENUE PEDESTRIAN IMPROVEMENTS FY 15
13915 RW1L 75 GE 387.0 BR - S VARIOUS BRIDGES (STR #S 861,202,242,983,243,251) SCOUR RETROFIT DEC 14
14315 SG1L 87 PN 148.0 BR - T GILA RIVER BRIDGE, STR #635 SCOUR RETROFIT DEC 14
16715 EA1M 260 YV 220.0 STP - P SR 260 AT INDUSTRIAL DRIVE IN CAMP VERDE ROUNDABOUT DEC 14
GZ1L 0000 PM TUC HPP -TUC-0(241)A T HOUGHTON RD: UPRR TO I-10 - WIDENING ROADWAY WIDENING FY 16
15710 NN1F 10 LA 3 H616101C NH - Y EHRENBERG PORT OF ENTRY RECONSTRUCT EB PORT OF ENTRY TBD FY 16
40016 EK1M 10 MA 129.5 IM - E DYSART RD - 83RD AVE DESIGN & CONSTRUCT FMS TBD FY 16
10112 JW1K 10 PN 186.7 T EARLEY ROAD TO JCT I-8 ROAD WIDENING TBD FY 16
10208 PJ1F 10 PM 248.0 NH -010-D T INA ROAD TI RECONSTRUCT TI & MAINLINE TBD FY 16
10816 GQ1J 17 MA 216.0 IM - E I-17 @ PEORIA AND UNION HILLS DRAINAGE GRATE IMPROVEMENTS TBD FY 16
10916 CB1M 17 YV 292.0 IM - P SOUTH OF MCGUIREVILLE ROCKFALL MITIGATION TBD FY 16
11016 KH1L 40 CN 218.7 IM - F TWIN ARROWS TI, EB OFF-RAMP RAMP REMOVAL, RECONSTR & ACCESS CTRL M TBD FY 16
11116 YF1K 40 SW 235.0 H821401C STP - H PAINTED CLIFFS & METEOR CRATER REST AREAS SYSTEM PRESERVATION - RESTORATION/REHAB TBD FY 16
43016 JJ1H 60 MA 139.0 HES -060-B(ATZ) E SR 303L TO SR 101L, AGUA FRIA, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 16
11216 CV1M 60 PN 232.0 STP - G WEST OF PINTO CREEK BRIDGE ROCKFALL MITIGATION TBD FY 16
11416 MW1L 74 MA 30.0 H840301C STP - E I-17 AND LAKE PLEASANT PKWY CONSTRUCT DRAINAGE IMPROVEMENTS TBD FY 16
12916 DC1M 77 NA 384.0 STP - H 5 MILE WASH - JCT 377 CBC EXTENSION TBD FY 16
10517 DD1M 79 PN 122.5 STP - T MP 122.5 EXTEND PIPES AND CULVERTS TBD FY 16
11616 GQ1G 82 SC 39.0 STP - T ELGIN TURNOFF EXTEND CMP'S, FLATTEN SLOPE & ELIMINATE G TBD FY 16
11716 DJ1M 87 NA 346.0 STP - H I-40 TO JCT SR 264 CBC EXTENSIONS TBD FY 16
PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED.
ARIZONA DEPARTMENT OF TRANSPORTATION
5 YEAR BID DATE REPORT
3RD SORT: BID DATE, RTE, MP Page 12 of 13
CPSID: RTE: CO: TRACS:
PROJECT
ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK:
BID
DATE:
DESIGN
DIST: FIRM:
10512 CZ1J 89 YV 319.0 H851801C P JCT SR 89A TO DEEPWELL RANCH ROAD WIDEN THE SR 89 CORRIDOR TBD FY 16
12516 LP1K 89A CN 538.0 STP - F COLORADO RIVER TO HOUSE ROCK (PHASE II) EXTEND PIPES AND CULVERTS TBD FY 16
10413 TC1J 93 MO 116.0 K CARROW TO STEPHENS CONSTRUCT 4-LANE DIVIDED HIGHWAY TBD FY 16
10416 NW1L 95 YU 34.0 H459901C NH -095-B(201) Y FORTUNA WASH BRIDGE CONSTRUCT NEW BRIDGE TBD FY 16
13016 TL1L 101L MA 50.7 NH - E RED MOUNTAIN - CHANDLER BLVD SIGN REHABILITATION TBD FY 16
11916 KZ1K 180 CN 216.1 STP - F NAVAJO RD - FLAGSTAFF CITY LIMITS WIDENING, C&G & DRAINAGE IMPROVEMENTS TBD FY 16
12016 IS1L 191 GH 120.3 STP - S RELATION ST TO JCT US70 INTERSECTION IMPROVEMENT TBD FY 16
12116 DW1M 191 AP 345.0 STP - H SANDERS - WITCH WELLS FENCING & CATTLE GUARDS TBD FY 16
41115 WW1K 202L MA 0.0 E SALT RIVER BRIDGE, SEGMENT 7 CONSTRUCT NEW FREEWAY TBD FY 16
12716 FG1M 202L MA 0.0 NH - E PUMP STATION FLOOD EROSION CONTROL TBD FY 16
10616 XD1K 260 YV 218.5 STP - P THOUSAND TRAILS TO I-17 CONSTRUCT INTERIM IMPROVEMENTS TBD FY 16
12216 LY1C 260 GI 258.0 NH - P LION SPRINGS SECTION RECONSTRUCT TO A 4-LANE DIVIDED TBD FY 16
CD1L 260 AP 394.0 H826901C G LITTLE COLORADO RIVER BR (STR # 416) SYSTEM PRESERVATION - MINOR BRIDGE REHA TBD FY 16
12316 EH1M 288 GI 289.0 STP - G SOUTH OF YOUNG ROCKFALL MITIGATION TBD FY 16
40616 EV1M 303L MA 103.2 IM -303-A(216)S E I-10/303L TI, PHASE II CONSTRUCT NEW FREEWAY TBD FY 16
12416 BU1L 999 SW 0.0 H826301C STP - K HAVILAND & MARBLE CANYON REST AREAS STRUCTURAL REHABILITATION TBD FY 16
PG1K 0000 MA MMA SS89401C STP -MMA-0(225)A E MCKELLIPS ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 16
BP1J 0000 PM TUC HPP -TUC-0(201)A T HOUGHTON ROAD WIDENING @ UPRR ROAD WIDENING OVER RAILROAD BRIDGE FY 16
11312 CQ1J 10 PM 264.0 NH - T COUNTRY CLUB ROAD TI DESIGN TRAFFIC INTERCHANGE (PE PH 1) DESIGN FY 16
10716 BV1M 10 CH 383.0 IM - S SAN SIMON PORT OF ENTRY PE PH 1 & 2 DESIGN FY 16
12816 CM1M 40 NA 297.0 IM - H GOODWATER - YELLOWHORSE PE PH 1 & 2 DESIGN FY 16
40216 EN1M 60 MA 192.0 NH - E CRISMON RD - MERIDIAN RD DESIGN HOV/GPL DESIGN FY 16
10216 DO1M 93 MO 109.0 NH - K CANE SPRINGS PE PH 1 & 2 DESIGN FY 16
ZE1L 17 YV 287.0 017-B(224)S P VERDE RIVER BRIDGES NB & SB #1731 & #505 DESIGN DEC 15
ZI1L 80 CH 364.0 S WHITE WATER DRAW BRIDGE #1626 DESIGN DEC 15
11207 QK1C 19 PM 58.7 NH - T AJO WAY TI (JCT SR 86) RECONSTRUCT TI TBD FY 17
10217 CD1M 40 MO 40.0 IM - K CROOKTON TO TRANSWESTERN SIGN REHABILITATION TBD FY 17
10317 CG1M 40 MO 81.0 IM - K EAST OF US 93 TI ROCKFALL MITIGATION TBD FY 17
10417 CH1M 40 MO 83.0 IM - K WILLOW SPRINGS ROCKFALL MITIGATION TBD FY 17
10617 DI1M 87 CN 324.0 STP - P CLOVER CREEK ROCKFALL MITIGATION TBD FY 17
10717 FF1M 92 CH 351.0 STP - S MELODY LANE - NACO RD WIDEN TO 3 LANES TBD FY 17
40317 EP1M 101L MA 11.2 NH -888-A(217)T E AGUA FRIA I-10 TO I-17 CONSTRUCT FMS TBD FY 17
Object Description
| Rating | |
| TITLE | 5 year bid date report |
| CREATOR | Arizona. Dept. of Transportation, Intermodal Transportation Division. |
| SUBJECT | Transportation--Arizona; |
| Browse Topic |
Transportation |
| DESCRIPTION | This item contains one or more publications. |
| Language | English |
| Publisher | Arizona Dept. of Transportation, Intermodal Transportation Division. |
| Material Collection |
State Documents |
| Source Identifier | TRT 7.2:B 42 |
| Location | ocn439092231 |
| REPOSITORY | Arizona State Library. Archives and Public Records--Law and Research Library. |
Description
| TITLE | 5 year bid date report February 15, 2013 |
| DESCRIPTION | 90 pages (PDF version). File size: 751 KB |
| TYPE |
Text |
| RIGHTS MANAGEMENT | Copyright to this resource is held by the creating agency and is provided here for educational purposes only. It may not be downloaded, reproduced or distributed in any format without written permission of the creating agency. Any attempt to circumvent the access controls placed on this file is a violation of United States and international copyright laws, and is subject to criminal prosecution. |
| DATE ORIGINAL | 2013-02-15 |
| Time Period |
2010s (2010-2019) |
| ORIGINAL FORMAT | Born Digital |
| Source Identifier | TRT 7.2:B 42 |
| Location | o439092231 |
| DIGITAL IDENTIFIER | 5yrbiddate20130215.pdf |
| DIGITAL FORMAT | PDF (Portable Document Format) |
| REPOSITORY | Arizona State Library, Archives and Public Records--Law and Research Library. |
| File Size | 768685 Bytes |
| Full Text | February 15, 2013 This report contains the construction projects from the new 5-Year Program. The report is sorted 7 different ways; 1) by project name, 3) by bid date, route and beginning milepost, 4) by TRACS number, 5) by route, beginning milepost and TRACS 6) by engineering district, route, beginning milepost and TRACS number and 7) by CPSID. Several projects are on “special” status as indicated by a bid date in the year 2050. The special categories are listed below. STATUS 02/25/2050 IGA/JPA PROJECTS WITHOUT SCHEDULE 05/25/2050 PROJECTS IN THE NEW 5-YEAR PROGRAM IN THE PROCESS OF BEING SCHEDULED. 06/25/2050 DESIGN PROJECTS IN THE 5-YEAR PROGRAM WITHOUT CORRESPONDING CONSTRUCTION PROJECT 08/25/2050 PROJECTS THAT ARE ON “HOLD” STATUS UNTIL THE PROBLEMS ARE RESOLVED AND A DECISION IS MADE ON RESCHEDULING. PROJECT DEVELOPMENT SHOULD CONTINUE IF POSSIBLE. 09/25/2050 PROJECTS THAT HAVE BEEN DELETED FROM THE CURRENT 5-YEAR CONSTRUCTION PROGRAM. WE WILL MAINTAIN THESE PROJECTS ON THE PRIMAVERA SYSTEM FOR RECORD. PROJECT DEVELOPMENT IS TERMINATED FOR THESE PROJECTS . ARIZONA DEPARTMENT OF TRANSPORTATION PROJECT CATEGORIES PROJECT CATEGORY 5-YEAR BID DATE REPORT PROGRAM & PROJECT MANAGEMENT SECTION AMEC AMEC LSD Logan Simpson Design AZTC Aztec Engineering MB Michael Baker Jr., Inc. BN Burgess & Niple MBD1 Michael Baker/Design One BRW BRW MMLA MMLA, Inc. BSA Bulduc, Smiley & Associates. Inc. OLSN Olsson & Associates C&B Carter & Burgess PARS Parsons Transportation Group CANN Cannon & Associates PBQD PBQD - Parsons Brinkerhoff Quade & Douglas CDG Corral Dybas Group, Inc. PBSJ PBS&J CH2M CH2M Hill PREM Premier Engineering Corporation DIBL Dibble & Associates RBF RBF Consulting DMJM DMJM+Harris RPOW Ritoch Powell & Associates EEC EEC SCON Stanley Consultants ENTR Entranco STEC Stantec Consulting, Inc. ERTH Earth Tech SVER Sverdrup GANN Gannett Fleming TBA To Be Assigned HDR HDR Engineering TCOR Transcore HUIT Huitt - Zollars TTI Tetra Tech, Inc. JLK JLK Eingeers TYLN T. Y. Lin International INCA Inca Engineering, Inc. URS URS DESIGN FIRM ABBREVIATIONS ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 1 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 11714 BN1M 8 YU 2.0 IM - Y 16TH STREET LANDSCAPING JUN 14 43514 WZ1K 202L MA 0.0 RARF- E 17TH AVE TO 51ST AVE, SEGMENT 3 CONSTRUCT NEW FREEWAY TBD FY 15 HV1L 0000 MA WBG SL69001C TEA -WBG-0(201)D P 1962 HASSAYAMPA RIVER BRIDGE PEDESTRIAN/BICYCLE IMPROVEMENT FY 13 45314 EQ1M 202L MA 0.0 NH - E 24TH ST - 17TH AVE, SEGMENT 2 DESIGN NEW FREEWAY DESIGN FY 14 44612 WR1K 10 MA 151.5 IM - E 32ND ST - SR202L, SANTAN PHASE 1 CONSTRUCT LOCAL EXPRESS LANES DESIGN FY 17 WM1L 5013 MA 0.0 SR14401C 501-3(001)P E 32ND ST ( PHX) #741-536-B SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13 45309 FN1H 10 MA 96.2 H708301X Y 395TH AVE (BELMONT RD) CONSTRUCT TI IGA FY 14 12014 BR1M 10 MA 145.0 IM - E 3RD AVENUE TO 3RD STREET PUMP STATION IMPROVEMENTS TBD FY 14 12314 YD1L 10 MA 144.9 IM -010-C(209)T E 3RD AVENUE TO 3RD STREET, DECK PARK TUNNEL DRAINAGE IMPROVEMENTS TBD FY 14 WN1L 7018 MA 0.0 SR09701C 701-8(003)P E 40TH ST PHOENIX 741-539-W SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13 12916 DC1M 77 NA 384.0 STP - H 5 MILE WASH - JCT 377 CBC EXTENSION TBD FY 16 WL1L 940 MA 0.0 SR19201C 000-6(172)A E 5TH ST (TEMPE) 741-560-C AT-GRADE RAILROAD CROSSING DESIGN JUN 13 PL1K 0000 MA MMA SS89901C CM -MMA-0(228)A E 87TH AVENUE PAVING DIRT ROAD FY 13 CC1L 0000 MA MMA SS95701C CM -MMA-0(231)A E 88TH AVE: DEER VALLEY TO WILLIAMS RD PAVE UNPAVED ROAD FY 13 14714 QO1L 40 NA 303.0 IM - H ADAMANA TI DRAINAGE IMROVEMENTS TBD FY 14 40317 EP1M 101L MA 11.2 NH -888-A(217)T E AGUA FRIA I-10 TO I-17 CONSTRUCT FMS TBD FY 17 11207 QK1C 19 PM 58.7 NH - T AJO WAY TI (JCT SR 86) RECONSTRUCT TI TBD FY 17 CY1M 347 PN 172.0 347-A(209)T T ALTERRA TO CASA BLANCA RD, CITY OF MARICOPA DESIGN DESIGN FY 13 10312 LE1G 93 MO 101.8 H738801C NH -093-B(204)T K ANTELOPE WASH CONSTRUCT 4-LANE DIVIDED HIGHWAY FEB 13 13213 RN1K 88 MA 204.0 STP - E APACHE JCT - TORTILLA FLATS MILL 2" & 3" AC & CHIP SEAL JAN 14 15414 JG1K 77 PN 123.5 H796901C T ARAVAIPA CREEK BRIDGE, STR #399 BRIDGE REPLACEMENT AUG 13 13115 WT1L 40 YV 144.0 IM -089-B(214)T K ASHFORK RR BR - JCT SR 89, #807,#440, #1760,#1761 BRIDGE DECK REHABILITATION TBD FY 15 JP1L 0000 MA MMA SS97401C E ATIS ENHANCEMENTS REGIONWIDE ARTERIAL ATIS FY 13 20313 CX1M 210 PM 1.0 STP - T AVIATION CORRIDOR IN TUCSON SIGN REHABILITATION TBD FY 13 19613 EJ1L 95 MO 250.0 STP -095-D(207)T K AVIATION WAY - BULLHEAD CITY PARKWAY PE PH 1 & 2 TO CONSTRUCT CONCRETE MEDIAN DESIGN FY 13 16006 QT1F 101L MA 53.5 E BALBOA DRIVE CONSTRUCT MULTI-USE PATH BRIDGE OVER TH IGA FY 15 41015 NX1L 202L MA 0.0 E BASELINE - SALT RIVER, SEGMENT 6 CONSTRUCT NEW FREEWAY TBD FY 15 17514 MQ1J 180 AP 338.0 H752001C STP -180-B(204)A G BEAVER DAM - RANCH (EB & WB) 3" CIPR & FR AUG 13 ZJ1K 0000 MA SUR SS85401C CM -SUR-0(210)A E BELL RD-US 60 TO 114TH AVE CONSTRUCT MULTI-USE PATH FY 14 11913 TI1K 8 PN 170.0 IM - T BIANCO ROAD - JCT I-10 RR(5" TL, 3" PL) & AR-ACFC NOV 13 12913 RX1K 69 YV 271.6 H812201C P BIG BUG 4 TO POLAND JCT RR 3" TL, RR AR-ACFC FULL WIDTH MAR 13 18313 MI1K 89 YV 335.9 H797601C 089-B(204)T P BIG CHINO WASH BRIDGE #979 DECK REPLACEMENT / WIDENING JAN 13 12813 ZY1J 40 NA 303.1 H785901C IM -040-E(214)T H BIG LITHODENDRON-PETRIFIED FOREST NATIONAL PA PAVEMENT PRESERVATION MAR 13 MD1K 0000 NA PLS SS86401C HPP -PLS-0(201)A G BILLY CREEK BRIDGE @ PORTER MOUNTAIN ROAD CAPACITY ADDITIONS - MAJOR WIDENING FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 2 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 16714 FD1L 89 CN 523.9 NH - F BITTER SPRINGS INSTALL INTERSECTION LIGHTING TBD FY 14 12413 RW1K 17 YV 245.0 H812101C P BLACK CANYON HILL (NB) RR (5" TL, 3" PL) & AR-ACFC APR 13 NG1L 0000 MA PHX PHX-0(266)A E BLACK MOUNTAIN BLVD, SR 51/SR 101 NEW ROADWAY FY 14 XD1L 0000 YU YYU SB44501C BR -YYU-0(205)A Y BRIDGE REHABILITATION OLD HWY 80 & AVE 30 1/2 E BRIDGE REHABILITATION FY 14 LK1K 0000 MA TMP SS73401C CM -TMP-0(210)X E BROADWAY ROAD: RURAL TO MILL AVENUE PEDESTRIAN IMPROVEMENTS FY 15 12515 BZ1M 17 MA 198.0 IM - E BUCKEYE RD, GRANT,JEFFERSON & ADAMS ELECTRICAL REHABILITATION TBD FY 15 12415 VT1K 17 MA 195.0 E BUCKEYE RD,GRANT ST,ADAMS ST & JEFFERSON ST ELECTRICAL REHABILITATION TBD FY 15 19213 LC1J 92 CH 324.3 H716701C HSIP-092-A(200)T S BUFFALO SOLDIER TRAIL TO KACHINA TRAIL RAISED MEDIAN JUN 13 15015 DX1M 191 AP 418.0 STP - H BURNSIDE - CHINLE FENCING & CATTLE GUARDS TBD FY 15 16815 SL1K 264 AP 441.0 STP - H BURNSIDE - CROSS CANYON 2" AC & AR-ACFC TBD FY 15 15315 ED1M 264 AP 441.0 STP - H BURNSIDE - SUMMIT FENCE & CATTLE GUARD TBD FY 15 18814 YJ1K 999 SW 0.0 H821701C STP -999-A(351)T Y BURNT WELL AND EHRENBURG REST AREAS WATER,STRUCTURAL,MECH & ELECTRICAL REH NOV 13 15114 GN1J 70 GH 295.0 S BYLAS TWLTL & ROADWAY WIDENING JUN 14 43814 OB1L 303L MA 107.0 E CAMELBACK ROAD TO GLENDALE AVENUE CONSTRUCT LANDSCAPE JUN 14 PW1H 0000 PM TUC SS63201C TEA -TUC-0(203)B T CAMPBELL AVE - MAIN STREET MAIN STREET REVITALIZATION FY 13 10216 DO1M 93 MO 109.0 NH - K CANE SPRINGS PE PH 1 & 2 DESIGN FY 16 14414 EV1L 40 CN 218.7 H789001C IM - F CANYON PADRE BRIDGE, STR #1670 DECK REPLACEMENT APR 14 10413 TC1J 93 MO 116.0 K CARROW TO STEPHENS CONSTRUCT 4-LANE DIVIDED HIGHWAY TBD FY 16 10910 DJ1G 90 CH 323.5 H655501C S CENTRAL AVE TO MOSON RD, E OF SIERRA VISTA WIDEN TO 5 LANES TBD FY 14 17413 CP1M 40 AP 322.0 NH - H CHAMBERS PORT OF ENTRY PE PH 1 & 2 DESIGN FY 13 17414 DS1M 169 YV 4.8 STP -169-A(203)S P CHERRY ROAD CONSTRUCT TURN LANES / BOX EXTENSION TBD FY 14 12010 EB1E 191 AP 446.3 H543801C STP -191-E(205) H CHINLE - SOUTH ROADWAY WIDENING TBD FY 13 22910 YS1K 0000 CH DGS SS87401C DGS-0(200)A S CHINO ROAD NEW FACILITIES - CONSTRUCTION OF NEW ROA FY 14 17214 XL1L 95 LA 149.2 HSIP-095-C(216)A Y CIENEGA SPRINGS RD SB LEFT TURN LANE APR 14 10617 DI1M 87 CN 324.0 STP - P CLOVER CREEK ROCKFALL MITIGATION TBD FY 17 14112 AI1K 191 CH 61.5 H788301C 191-A(203)A S COCHISE POWER PLANT - JCT I-10 RR 2" AC + 3" AC + FR TBD FY 14 12516 LP1K 89A CN 538.0 STP - F COLORADO RIVER TO HOUSE ROCK (PHASE II) EXTEND PIPES AND CULVERTS TBD FY 16 13513 RT1K 180 CN 216.2 H811801C STP -180-(202)T F COLUMBUS AVENUE - SNOW BOWL RR 3" & AR-ACFC & TURN LANES NOV 13 XX1K 0000 MA CHN SS93201C E CONSOLIDATED CANAL MULTI-USE PATH PATHWAY/TRAIN IMPROVEMENTS FY 13 MB1K 0000 PN CLG SS87301C STP -CLG-0(200)A T COOLIDGE AVENUE DESIGN / RECONSTRUCTION FY 14 18113 NY1K 79 PN 101.8 H807501C BR -079-A(205)T T CORONADO WASH BRIDGE STRUCTURE #222 BRIDGE REPLACEMENT MAY 13 18214 SH1K 260 NA 321.4 NH -260-B(216)A G COTTONWOOD WASH - SHOW LOW RR 3" AC & AR-ACFC TBD FY 14 11312 CQ1J 10 PM 264.0 NH - T COUNTRY CLUB ROAD TI DESIGN TRAFFIC INTERCHANGE (PE PH 1) DESIGN FY 16 BA1L 0000 YU YYU SB43701C BR -YYU-0(201)T Y COUNTY 19TH ST BRIDGE OVER MAIN DRAIN (AVE F 1/2 BRIDGE REPLACEMENT FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 3 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 14413 RU1K 160 NA 358.1 H811901C F COUNTY LINE - BLACK MESA RR 3" & AR-ACFC FEB 13 40216 EN1M 60 MA 192.0 NH - E CRISMON RD - MERIDIAN RD DESIGN HOV/GPL DESIGN FY 16 10217 CD1M 40 MO 40.0 IM - K CROOKTON TO TRANSWESTERN SIGN REHABILITATION TBD FY 17 16914 AE1K 264 AP 459.0 H786301C STP - H CROSS CANYON - SUMMIT 2" AC & AR-ACFC TBD FY 14 16313 PY1E 40 YV 102.0 IM - K CROSS MT - JOLLY RD UPGRADE EXISTING ROCKFALL PROTECTION TBD FY 13 12814 NB1K 10 PM 283.6 H805201C IM -010-E(208)A T DAVIDSON CANYON - COUNTY LINE MILL AND REPLACE NOV 13 11815 NA1L 10 PM 284.4 IM -010-E(213)A T DAVIDSON CANYON WB BRIDGE, STR #598 SUPERSTRUCTURE REPLACEMENT TBD FY 15 10116 TE1J 89 YV 320.4 H803901C STP -089-B(203)A P DEEP WELL RANCH ROAD TO SOUTH CHINO VALLEY CONSTRUCT ROADWAY WIDENING AUG 13 18713 MS1K 89 YV 333.1 H791901C 089-B(208)T P DEL RIO RANCH BRIDGE #20046 BRIDGE REPLACEMENT JAN 13 PH1K 0000 MA MMA SS89301C STP -MMA-0(226)A E DOBSON ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 15 44814 TX1H 202L MA 47.8 CM -888-A(218)T E DOBSON ROAD TO I-10, MARICOPA CONSTRUCT FMS TBD FY 14 WJ1L 0000 MA 0.0 SR23201C E DOBSON ROAD, AAR/DOT NO. 741-649-G SYSTEM ENHANCEMENT-SAFETY IMPROVEMENT FY 14 JQ1L 0000 MA SUR SS95801C E DOVE VALLEY ROAD,18TH AVE-203RD AVE ROADWAY IMPROVEMENTS FY 13 12213 SQ1K 10 CH 318.8 H815101C IM -010-F(216)T S DRAGOON RD - WEST WILLCOX TI (WB) PAVEMENT PRESERVATION APR 13 15514 NH1L 77 GI 147.6 H832201C BR -077-A(207)A G DRIPPING SPRING BRIDGE #398 BRIDGE REPLACEMENT JUL 13 13614 SO1K 17 YV 269.2 IM -017-B(218)A P DUGAS TI - CHERRY ROAD RR (5" TL, 3" PL) & AR-ACFC DEC 13 13815 SR1K 75 GE 379.1 S DUNCAN BRIDGE - LITTLE SANDS WASH 3" AC & AR-ACFC TBD FY 15 UH1K 0000 MA SCT SS91301C CM -SCT-0(211)A E DYNAMITE BLVD - PIMA TO ALMA SCHOOL ROAD INSTALL CURB AND GUTTER FY 13 40016 EK1M 10 MA 129.5 IM - E DYSART RD - 83RD AVE DESIGN & CONSTRUCT FMS TBD FY 16 45613 UU1L 10 MA 129.5 RARF- E DYSART ROAD TO SR 101L (AUGA FRIA FWY) LANDSCAPE CONSTRUCTION JUN 13 GT1M 40 NA 289.0 040-D(227)T H E HOLBROOK TI OP EB#1369 & WB #1370 DESIGN BRIDGE REHABILITATION DESIGN FY 13 YT1L 169 YV 5.1 H853601C STP -169-A(204)T P E OLD CHERRY RD - W CHERRY CREEK RD PAVEMENT PRESERVATION (MICRO-SURFACING MAR 13 20013 YU1L 180 AP 426.0 STP - G EAGER ALPINE INSTALL DRAINAGE FACILITY JUN 13 10112 JW1K 10 PN 186.7 T EARLEY ROAD TO JCT I-8 ROAD WIDENING TBD FY 16 12613 RP1K 40 YV 146.2 F EAST ASHFORK TI - COUNTY LINE RR 3" & 2" AC & AR-ACFC TBD FY 13 12613 NQ1L 40 CN 146.0 H840201C IM - F EAST ASHFORK TI TO WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC APR 13 16413 IW1L 40 CN 180.8 IM -040-C(208)A F EAST OF PARKS ROCKFALL MITIGATION JUN 13 16515 ZA1L 60 PN 228.8 G EAST OF QUEEN CREEK TUNNEL ROCKFALL MITIGATION TBD FY 15 IX1L 180 NA 307.3 H831801C STP -180-B(205)T H EAST OF SR 77 NEAR HOLBROOK PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13 10317 CG1M 40 MO 81.0 IM - K EAST OF US 93 TI ROCKFALL MITIGATION TBD FY 17 16613 CK1M 40 NA 226.0 IM - H EAST WINSLOW TI PE PH 1 & 2 DESIGN FY 13 HC1J 10 LA 1.0 Y EHRENBERG EXIT 1 ROUNDABOUT JUN 13 15710 NN1F 10 LA 3 H616101C NH - Y EHRENBERG PORT OF ENTRY RECONSTRUCT EB PORT OF ENTRY TBD FY 16 45713 EU1M 303L MA 120.0 NH -303-A(215)T E EL MIRAGE RD DESIGN TI DESIGN FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 4 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 11616 GQ1G 82 SC 39.0 STP - T ELGIN TURNOFF EXTEND CMP'S, FLATTEN SLOPE & ELIMINATE G TBD FY 16 42115 ER1M 202L MA 0.0 IM - E ELLIOT RD - BASELINE RD, SEGMENT 5 DESIGN NEW FREEWAY DESIGN FY 15 14113 DK1M 89A YV 330.0 STP - P FAIN ROAD TO SR-169 CORRIDOR LOCATION REPORT FOR RTE EVALU DESIGN FY 13 18013 ZS1H 77 NA 367.0 STP - H FIVE MILE WASH BRIDGE PE PH 1 & 2 (WIDEN ROADWAY TO 4 LANES) DESIGN FY 13 14213 DN1M 89 CN 420.0 NH - F FLAGSTAFF CITY LIMITS - LENOX PARK FEASIBILITY REPORT FOR ACCESS MGT PLANNI DESIGN FY 13 17613 XI1J 60 GI 305.0 H778601C STP -060-E(211)A G FLYING V CANYON TO SQUAW DRESS RIDGE SLOPE STABILIZATION JUN 13 11814 SV1K 8 YU 13.7 H815801C IM - Y FOOTHILLS BLVD - DOME VALLEY RR (5" TL, 3" PL) & FR NOV 13 10416 NW1L 95 YU 34.0 H459901C NH -095-B(201) Y FORTUNA WASH BRIDGE CONSTRUCT NEW BRIDGE TBD FY 16 13413 RS1K 89A CN 609.3 F FREDONIA - STATE LINE RR 3" & AR-ACFC TBD FY 13 GX1M 86 PM 120.6 086-A-NFA T FRESNAL TO MP 123.9 DESIGN DESIGN FY 13 VS1L 101L MA 60.0 H848801C 101-C(201)A E GALVESTON DRAINAGE BASIN G (THUDE PARK) DRAINAGE IMPROVEMENT & PUMP STATION IGA FY 13 18414 EE1M 264 AP 446.0 STP - H GANADO SECTION WIDENING TO 3 LANES & TL TBD FY 14 XX1G 264 AP 446.0 264-A(212)T H GANADO WASH BRIDGE #1046 DESIGN BRIDGE REPLACEMENT DESIGN FY 14 12013 SW1K 10 LA 63.0 H815901C 010-A(217)T Y GAS LINE RD - COUNTY LINE RR (1/2" TL, 4" PL) & AR-ACFC FEB 13 14715 SF1K 180 AP 386.3 STP - G GENERATING STATION ROAD - JCT US 60 RR 3" & CHIP SEAL TBD FY 15 14913 YG1L 8 YU 125.0 Y GILA BEND TO I-10 SIGN REHABILITATION DESIGN FY 13 14315 SG1L 87 PN 148.0 BR - T GILA RIVER BRIDGE, STR #635 SCOUR RETROFIT DEC 14 OA1K 0000 MA MMA SS87901C STP -MMA-0(218)A E GILBERT ROAD BRIDGE OVER THE SALT RIVER CONSTRUCT BRIDGE FY 15 13715 KX1L 70 GI 259.0 H835901C G GILSON WASH BRIDGE, STR # 464 SCOUR RETOFIT TBD FY 15 45113 OC1L 303L MA 109.0 H860301C RARF- E GLENDALE AVE TO PEORIA AVE CONSTRUCT LANDSCAPE JUN 14 12816 CM1M 40 NA 297.0 IM - H GOODWATER - YELLOWHORSE PE PH 1 & 2 DESIGN FY 16 23213 BM1L 64 CN 234.5 H825801C F GRAND CANYON AIRPORT- FS RD 328 SHOULDER WIDENING TBD FY 15 13812 AH1K 89 CN 510.0 NH -089-D(202)A F GRAY SPOT WASH - NORTH RED HILL 3" AC + FR NOV 13 NF1L 191 GE 184.5 H841201C STP -191-C(215)T S GREY PEAK TO JUAN MILLER ROAD PAVEMENT PRESERVATION (DOUBLE CHIP SEAL APR 13 YQ1L 70 GH 347.0 H853801C S HAEKEL RD TO US 191 SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13 12416 BU1L 999 SW 0.0 H826301C STP - K HAVILAND & MARBLE CANYON REST AREAS STRUCTURAL REHABILITATION TBD FY 16 JN1M 89 YV 345.7 H863601C K HELL CANYON BRIDGE DECK REHABILITATION TBD FY 13 XA1L 89 YV 345.0 089-B(211)T K HELL CANYON BRIDGE #483 REPLACEMENT & WIENING TBD FY 14 14614 SJ1K 40 NA 290.2 H813101C IM -040-D(219)A H HOLBROOK - SUN VALLEY RR (5"TL, 3"PL) & AR-ACFC JUL 13 16913 CL1M 40 NA 290.0 IM - H HOLBROOK - SUN VALLEY FENCING AND CATTLE GUARDS TBD FY 13 13209 A6SP 87 NA 346.0 H717901C H HOMOLOVI RUINS STATE PARK CONSTRUCT ROAD TBD FY 14 GZ1L 0000 PM TUC HPP -TUC-0(241)A T HOUGHTON RD: UPRR TO I-10 - WIDENING ROADWAY WIDENING FY 16 BP1J 0000 PM TUC HPP -TUC-0(201)A T HOUGHTON ROAD WIDENING @ UPRR ROAD WIDENING OVER RAILROAD BRIDGE FY 16 UK1K 0000 PN PPN STP -PPN-0(205)A T HUNT HIGHWAY - SYSTEM PRESERVATION - ENGINEERING FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 5 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 12915 CF1M 40 MO 74.0 IM - K HWY 141 JCT TO SILVER SPRINGS ROAD (WB) RR (5"TL, 3" PL) + AR-ACFC + SHOULDERS TBD FY 15 41608 TY1H 202L MA 0.0 E I-10 EAST/SANTAN TI TO 51ST AVE DESIGN ROADWAY TBD FY 14 40017 ES1M 202L MA 0.0 IM - E I-10 MARICOPA - 24TH ST, SEGMENT 1 CONSTRUCT NEW FREEWAY TBD FY 17 45414 ET1M 202L MA 0.0 IM - E I-10 PAPAGO/ SR202L SYSTEM INTERCHANGE SEGMEN DESIGN NEW SYSTEM TI DESIGN FY 14 MZ1H 303L MA 5.0 NH -303-A(ASO) E I-10, MC 85 TO I-10 NEW 303 EXTENSION SOUTH TBD FY 14 14915 ZA1J 191 CH 331.0 STP - S I-10/ US 191 TI AT MP 331 CONSTRUCT IMPROVEMENTS TBD FY 15 45213 NU1L 303L MA 0.0 E I-10/303L TI, PHASE I (I-10 REALIGNMENT) CONSTRUCT LANDSCAPE TBD FY 14 40616 EV1M 303L MA 103.2 IM -303-A(216)S E I-10/303L TI, PHASE II CONSTRUCT NEW FREEWAY TBD FY 16 44909 FM1H 10 MA 105.0 H683801X I -010-A-901 Y I-10/DESERT CREEK TI (PRIVATE FUNDS) CONSTRUCT TI IGA FY 14 40313 DD1J 101L MA 23.5 E I-17 TO TATUM BLVD CONSTRUCT HOV LANE DESIGN FY 13 10816 GQ1J 17 MA 216.0 IM - E I-17 @ PEORIA AND UNION HILLS DRAINAGE GRATE IMPROVEMENTS TBD FY 16 23913 ZC1L 999 SW 0.0 HSIP-999-A(377)S F I-17 AND I-40, INLAID PAVEMENT MARKERS, SEGMENT I INLAID PAVEMENT MARKINGS TBD FY 13 11416 MW1L 74 MA 30.0 H840301C STP - E I-17 AND LAKE PLEASANT PKWY CONSTRUCT DRAINAGE IMPROVEMENTS TBD FY 16 13914 CC1M 19 SC 9.0 STP - T I-19 FRONTAGE ROAD, NB DRAINAGE REPAIR TBD FY 14 12714 AZ1M 10 PM 268.0 IM -010-D(215)T T I-19 TO CRAYCROFT ROAD IN TUCSON SIGN REHABILITATION AUG 13 11716 DJ1M 87 NA 346.0 STP - H I-40 TO JCT SR 264 CBC EXTENSIONS TBD FY 16 QP1J 40 MO 66.5 IM -040-B(208)A K I-40, BLAKE RANCH RD TI IMPROVEMENTS TBD FY 13 15413 HJ1J 8 YU 7.2 HSIP- Y I-8 AND ARABY ROAD PE PH 1 AND 2 DESIGN FY 13 KJ1K 8 MA 117.0 H800001C Y I-8 TO GILLESPIE CANAL REMOVE 3", REPLACE 2.5" & ACFC TBD FY 14 CX1G 0000 PM MRN SB41301C BR-MRN-0(014)A T INA BRIDGE OVER SANTA CRUZ BRIDGE REPLACEMENT FY 13 10015 QL1J 10 PM 247.0 H758301C T INA RD TO RUTHRAUFF RD RECONSTRUCTION FOR WIDENING TBD FY 15 10208 PJ1F 10 PM 248.0 NH -010-D T INA ROAD TI RECONSTRUCT TI & MAINLINE TBD FY 16 12415 HW1L 17 MA 202.3 IM - E INDIAN SCHOOL ROAD - PEORIA AVENUE SIGN REHABILITATION TBD FY 15 13814 MT1L 19 SC 0.3 IM -019-A(216)A T INTERNATIONAL BORDER - JCT B-19 RR AR-ACFC JUN 13 10012 KM1K 95 YU 0.0 H800301C STP -095-A(204)A Y INTERNATIONAL BORDER - JUAN SANCHEZ BLVD INFRASTRUCTURE IMPROVEMENTS FEB 13 13714 MS1L 19B SC 0.1 STP -B19-A(201)A T INTERNATIONAL BORDER - MARIPOSA/SR189 RR 2" AC DEC 13 PI1K 0000 MA MES SS89101C CM -MES-0(217)A E ITS TRAFFIC SIGNAL CONVERSIONS - PHASE 5 FIBER-OPTIC COMMUNICATIONS NET FY 13 14313 SB1K 87 GI 236.2 H812301C P JCT 188 - RYE RR 3" TL & AR-ACFC FULL WIDTH MAY 13 20713 EF1M 266 GH 104.0 STP - S JCT 191 - BONITA CHIP SEAL & GR RENEWAL JUN 13 17714 QC1L 191 AP 477.9 STP -191-E(213)T H JCT N12 TO JCT US-160 REPLACE FENCE AND CATTLE GUARDS JUN 14 13613 SC1K 191 CH 38.2 HSIP- S JCT SR 181 - PEARCE ROAD 3" AC & AR-ACFC MAY 13 16314 DM1M 89 YV 349.0 STP - P JCT SR 260 (COTTONWOOD) CONSTRUCT DUAL RIGHT TURN LANES TBD FY 14 XT1H 180 AP 402.0 G JCT SR 260 / US 180 & RODEO GROUNDS INTERSECTIO REALIGN INTERSECTION TBD FY 13 11710 RJ1C 160 NA 375.2 H512001C NH -160-A(201)T H JCT SR 564 - TSEGI, PH I CONSTRUCT DUAL PASSING LANES FEB 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 6 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 13913 QE1K 387 PN 0.0 STP - T JCT SR 84 / SR 287 TO SANTA CRUZ RIVER BRIDGE RR 4" TL, 3" PL & FOG COAT JUN 13 16614 HO1L 89 CN 403.0 STP - F JCT SR 89A / PLAZA WAY (FLAGSTAFF) DRAINAGE IMPROVEMENTS TBD FY 14 10512 CZ1J 89 YV 319.0 H851801C P JCT SR 89A TO DEEPWELL RANCH ROAD WIDEN THE SR 89 CORRIDOR TBD FY 16 16315 UZ1J 89A CN 525.0 STP - F JCT US 89 - COLORADO RIVER EXTEND PIPES AND CULVERTS TBD FY 15 14515 FP1L 89 CN 525.0 NH - F JCT US 89A - BIG CUT EP (PIPE) DROP-OFF MITIGATION TBD FY 15 14415 SP1K 89 YV 258.3 STP - P JCT US 93 - JCT SR 71 RR 3" & AR-ACFC TBD FY 15 OD1K 0000 MO CLC SS87801C STP -CLC-0(201)A F JOHNSON AVENUE PAVEMENT PRESERVATION FY 13 14815 SG1K 180 AP 407.0 STP - G JUAN CARILLO - FH275 RR 3" AC & AR-ACFC TBD FY 15 ZN1E 0000 PN PPN SB41001C BR -PPN-0-(169) G KELVIN BRIDGE - #8441 BRIDGE REPLACEMENT FY 13 HY1L 66 MO 56.4 H809401X SB -AZ09(002) K KINGMAN POWERHOUSE VISITOR CENTER IMPROVEMENTS IGA FY 13 PU1K 0000 PM TUC SS86501C STP -TUC-0(233)A T KOLB ROAD CONNECTION TO SABINO CANYON ROADWAY AND SIDEWALK IMPROVEMENTS FY 14 YM1L 202L MA 9.0 H854301C E L101 TO MCDOWELL ROAD SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13 YL1L 202L MA 9.0 H854201C E L101 TO MESA DRIVE SYSTEM PRESERVATION (RESTORATION/REHAB/ JUN 13 HB1M 10 PN 209.9 H861401C IM -010-D(217)T T LA PALMA RD TO PICACHO HWY DESIGN PAVEMENTPRESERVATION PROJECT DESIGN FY 13 10511 XQ1L 95 MO 182.0 K LAKE HAVASU STATE PARK (CONTACT POINT) PH II DESIGN PARKING DESIGN FY 15 13315 JL1K 40 NA 284.3 BR -040-D(223)A H LEROUX WASH BRIDGE EB #1772 & WB #1773 BRIDGE REPAIR TBD FY 15 16114 VM1K 87 CN 323.9 BR -087-C(203)A H LIMESTONE WASH BRIDGE # BRIDGE REPLACEMENT JUL 13 43208 ST1H 202L MA 44.0 CM - E LINDSAY ROAD TO GILBERT ROAD DESIGN & CONST MULTI-USE PATH TBD FY 13 12216 LY1C 260 GI 258.0 NH - P LION SPRINGS SECTION RECONSTRUCT TO A 4-LANE DIVIDED TBD FY 16 CD1L 260 AP 394.0 H826901C G LITTLE COLORADO RIVER BR (STR # 416) SYSTEM PRESERVATION - MINOR BRIDGE REHA TBD FY 16 17913 LX1G 75 GE 384.0 075-A(200)T S LITTLE SANDS WASH BANK PROTECTION AUG 13 OC1K 0000 MA MES SS87701C CM -MES-0(216)A E LOCAL AGENCY WIDE - FIBER-OPTIC COMMUNICATION FIBER OPTICS FY 13 14310 QQ1K 40 AP 358.5 H LUPTON TI DCR AND ENVIRONMENTAL STUDIES DESIGN FY 14 16713 KW1L 40 NA 271.0 H837201C BR - H MANILA WASH BRIDGES STR #851,852 & 2080 SCOUR RETROFIT MAR 13 15115 DY1M 191 AP 462.5 STP -191-E(212)T H MANY FARMS - APACHE CO. RD 508 FENCING WIDENING JUN 14 11112 CO1J 10 PM 236.4 T MARANA ROAD TO CORTARO ROAD DESIGN (RECONSTRUCT & WIDEN FRONTAGE R DESIGN FY 15 45913 EO1M 101L MA 6.0 STAN- E MARYLAND AVENUE CONSTRUCT DIRECT HOV RAMP (DESIGN BUILD) FEB 13 OB1K 0000 MA MMA SS88101C STP -MMA-0(217)A E MCKELLIPS ROAD - SR101L TO ALMA SCHOOL ROADWAY RECONSTRUCTION FY 15 PG1K 0000 MA MMA SS89401C STP -MMA-0(225)A E MCKELLIPS ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 16 19313 DP1M 93 MO 125.0 NH -093-B(211)T K MEDLIN CROSSOVER DESIGN AND CONSTRUCT NEW CROSSOVER DESIGN FY 13 10717 FF1M 92 CH 351.0 STP - S MELODY LANE - NACO RD WIDEN TO 3 LANES TBD FY 17 40613 NM1L 60 MA 194.0 NH -060-C(207)T E MERIDIAN ROAD. HALF TI CONSTRUCT TI TBD FY 14 11915 BU1M 10 CH 296.0 IM - T MESCAL ROAD TO JCT SR 90 RR(5" TL, 3" PL) + AR-ACFC TBD FY 15 13313 RR1K 89 CN 476.6 H811601C STP -089-D(203)T F MOENKOPI WASH - HIDDEN SPRINGS 2.5" AC OVERLAY AND 1/2" AR-ACFC NOV 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 7 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 13003 FR1C 8 YU 55.9 H206001C IM - Y MOHAWK REST AREA CONSTRUCT REST AREA TBD FY 15 14814 RE1L 60 MA 115.5 BR -060-B(209)T P MONARCH WASH BR, STR #204 & 759 SCOUR RETROFIT DEC 13 15613 RH1L 17 MA 238.6 BR - P MOORES GULCH BRIDGE SB #339 DESIGN BRIDGE REPLACEMENT DESIGN FY 13 10114 DU1M 191 GH 101.0 STP - S MP 100.7 TO SR 266 DESIGN PARALLEL ROADWAY DESIGN FY 14 18413 DF1M 83 SC 12.0 H850101C T MP 12 - MP 14 MILL AND PAVE TBD FY 13 10517 DD1M 79 PN 122.5 STP - T MP 122.5 EXTEND PIPES AND CULVERTS TBD FY 16 17114 IP1K 93 MO 17.4 HSIP- K MP 17.4 - MP 58.4 PE PH 1 & 2 DESIGN FY 14 17713 CZ1M 68 MO 20.0 STP - K MP 19, TURN LANES DESIGN & CONSTRUCT 3 EB TURN LANES DESIGN FY 13 14914 CU1M 60 GI 229.4 HSIP- G MP 229.4 - MP 232.91 SHOULDER WIDENING TBD FY 14 16513 DH1M 87 CN 268.1 HSIP- P MP 268.1 - MP 278 PE PH 1 & 2 DESIGN FY 13 15813 BX1M 69 YV 281.1 HX24201C HSIP-069-A(210)T P MP 281.1 - MP 289.7 MODIFY SIGNALS JUN 13 OR1K 60 GI 290.0 H808301C 060-E(206)T G MP 290, 296 AND 320 AT HAGEN HILL ROCKFALL CONTAINMENT FEB 13 17013 QD1L 40 NA 298.0 IM - H MP 298 UTILITY OVERPASS DESIGN OF CBC EXTENSION JAN 15 13615 CW1M 60 GI 302.0 STP -060-E(214)T G MP 302 - 311 RR 3" AC + AR-ACFC TBD FY 15 11715 BA1M 10 LA 42.0 IM - Y MP 42 TO HOVATTER ROAD RR(4" TL, 3" PL) + AR-ACFC TBD FY 15 11916 KZ1K 180 CN 216.1 STP - F NAVAJO RD - FLAGSTAFF CITY LIMITS WIDENING, C&G & DRAINAGE IMPROVEMENTS TBD FY 16 14015 YZ1L 77 GI 156.8 G NEAR SUMMIT ROCKFALL MITIGATION TBD FY 15 12315 BW1M 15 MO 0.0 IM - F NEVADA STATE LINE - MP 13 RR(4" TL, 3" PL) AR-ACFC TBD FY 15 13514 CF1L 17 MA 231.0 H826801C E NEW RIVER BRIDGES, STR # 1290 &1291 SCOUR RETROFIT JAN 14 15614 UB1J 77 AP 362.1 STP -077-B(208)A H NORTH SNOWFLAKE BOX CULVERT EXTENSION TBD FY 14 16414 IS1J 89 CN 385.1 H741801C A89-B(204)A F OAK CREEK CANYON CREEK BANK PROTECTION TBD FY 14 11008 EX1F 60 PN 230.0 STP -060-D(211)A G OAK FLAT - MIAMI CONSTRUCT PASSING/CLIMBING LANE FEB 14 BB1L 0000 MA MMA SS83001C CM -MMA-0(214)A E OLIVE AVE: LITCHFIELD ROAD TO LOOP 101 INSTALL FIBER OPTIC CONDUIT FY 13 10311 CY1J 77 PN 100.0 H739101C T ORACLE STATE PARK CONSTRUCT PARKING TBD FY 14 16814 HG1L 89 CN 551.0 NH - F PAGE MAINTENANCE YARD WIDENING FOR TURN LANES TBD FY 14 11116 YF1K 40 SW 235.0 H821401C STP - H PAINTED CLIFFS & METEOR CRATER REST AREAS SYSTEM PRESERVATION - RESTORATION/REHAB TBD FY 16 12715 SU1K 19 SC 16.0 IM - T PALO PARADO - CHAVEZ SLIDING TI RR (4" TL, 3" PL) + FR TBD FY 15 WU1J 0000 PM TUC SS73001C STP -TUC-0(226)A T PANTANO BOULEVARD PAVEMENT RECONSTRUCTION FY 13 15214 DR1M 169 MA 4.0 STP -169-A(205)S P PASSING LANES CONSTRUCT TURN AND PASSING LANES TBD FY 14 HZ1L 0000 MA SCT SS96701C E PAVEMENT PRESERVATION PHASE 3 PAVEMENT PRESERVATION FY 13 45112 WB1L 303L MA 112.0 E PEORIA AVE - WADDELL RD LANDSCAPE CONSTRUCTION JUN 13 JE1L 89 YV 328.0 H833001C P PERKINSVILLE RD ROUNDABOUT SYSTEM ENHANCEMENT - ENGINEERING DESIGN FY 13 40913 CM1J 10 MA 122.0 H770901C NH - E PERRYVILLE ROAD TI CONSTRUCT TI APR 13 15913 WC1L 74 MA 22.4 STP -074-A(204)T E PICACHO WASH TRAIL TO JCT I-17 RR(5" TL, 3" PL) + AR ACFC SEP 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 8 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 14513 PA1K 260 NA 310.0 H801201C NH -260-B(209)A G PIERCE WASH BRIDGE (STR # 1373) SCOUR RETROFIT JAN 13 80899 S9SP 101L MA 73.0 H387501C RARF-101-B E PIMA ROAD EXTENSION, JPA CONSTRUCT ROADWAY IGA FY 14 12713 RQ1K 40 CN 158.6 F PINE SPRINGS - WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC TBD FY 13 19214 HM1L 77 PN 105.4 H826701C HSIP- T POWER LINE - SAN MANUEL ROAD DESIGN SHOULDER WIDENING DESIGN FY 14 12716 FG1M 202L MA 0.0 NH - E PUMP STATION FLOOD EROSION CONTROL TBD FY 16 16514 SE1K 89A CN 386.6 STP -A89-B(210)A F PUMPHOUSE WASH - OVERLOOK RR (3"AC, 2.5" AC + AR-ACFC) FULL WIDTH DEC 13 14114 SM1K 40 MO 57.0 IM -040-B(213)A K RATTLESNAKE WASH - JCT US 93 RR(5" TL, 3" PL) & AR-ACFC TBD FY 14 13016 TL1L 101L MA 50.7 NH - E RED MOUNTAIN - CHANDLER BLVD SIGN REHABILITATION TBD FY 16 15208 NSSP 89A YV 365.0 F RED ROCK STATE PARK DESIGN DESIGN FY 13 12016 IS1L 191 GH 120.3 STP - S RELATION ST TO JCT US70 INTERSECTION IMPROVEMENT TBD FY 16 KQ1H 0000 MA MMA STP -QCR-0(001)A E RIGGS RD,ELLSWORTH TO MERIDIAN CONSTRUCT NEW ROADWAY FY 13 GP1M 191 AP 247.8 191-C(216)A G RIGHT OF WAY FENCE IN BOTH DIRECTIONS RIGHT OF WAY FENCING DESIGN FY 13 GO1M 260 AP 385.5 260-C(205)A G RIGHT OF WAY FENCING TWO LOCATIONS EAST BOUN RIGHT OF WAY FENCING DESIGN FY 13 20613 MQ1L 260 NA 282.5 HSIP- P RIM RD TO GIBSON RD, SEGMENTS 1, 2 & 3 SHOULDER WIDENING PROGRAM, PE PH 1 & 2 DESIGN FY 13 19414 HS1L 89 YV 330.0 H827801C P ROAD 4 NORTH CONSTRUCT ROUNDABOUT APR 14 11414 CU1J 17 YV 232.0 P ROCK SPRINGS TO CORDES JUNCTION PE PH2 (WIDEN ROADWAY) DESIGN FY 14 20213 OT1F 188 GI 254.0 STP - G ROOSEVELT - JAKES CORNER INSTALL DRAINAGE FACILITY CBC TBD FY 13 18514 EG1M 288 GI 260 STP - G ROOSEVELT - YOUNG CBC EXTENSION OCT 13 17814 SK1K 191 AP 482.0 H813201C STP - H ROUND ROCK - JCT. US 160 3" AC & AR-ACFC FEB 14 14514 EE1K 40 NA 254.6 IM -040-D(213)A H RUBY WASH BRIDGE - E WINSLOW TI OP BRIDGE REHABILITATION JUL 13 22413 YC1L 64 CN 0.0 H817202C FA - F RURAL INTELLIGENT TRANSPORTATION SYSTEMS - PH CONSTRUCT FEB 13 10015 VH1L 10 PM 252.0 NH - T RUTHRAFF ROAD TI RECONSTRUCTION FOR WIDENING TBD FY 15 ZP1K 0000 YU YYU SS86101C STP - Y S. FRONTAGE ROAD - AVENUE 9E TO AVENUE13E PAVEMENT PRESERVATION FY 13 15615 YC1K 999 SW 0.0 H821301C STP - T SACATON & CANOA RANCH REST AREAS WATER/WASTEWATER, STRUC & ELECTICAL RE TBD FY 15 40415 UF1H 202L MA 0.0 RARF- E SALT RIVER - BUCKEYE ROAD SEGMENT 8 CONSTRUCT NEW FREEWAY TBD FY 17 41115 WW1K 202L MA 0.0 E SALT RIVER BRIDGE, SEGMENT 7 CONSTRUCT NEW FREEWAY TBD FY 16 15014 BT1L 60 GI 292.0 H826201C 060-E(207)A G SALT RIVER CANYON REST AREA REPLACE COMPOSTING TOILETS & STRUCTURA DEC 13 BX1L 0000 MA TMP SS95301C CM -TMP-0(217)A E SALT RIVER MUP: I-10/TEMPE DRAIN TO PRIEST DRIVE PATHWAY IMPROVEMENTS FY 13 ZS1J 0000 MA PHX CM -PHX-0(223)A E SALT RIVER PATHWAY - 24TH ST TO I-10 TEMPE DRAIN PATHWAY IMPROVEMENTS FY 13 14615 JR1L 92 CH 340.5 BR -092-A(203)A S SAN PEDRO RIVER BRIDGE #449 BRIDGE REPLACEMENT TBD FY 15 12015 WD1L 10 CH 306.7 IM -010-F(219)A S SAN PEDRO RIVER BRIDGE EB #1530 & WB #1531 DECK REPLACEMENT & SCOUR RETROFIT TBD FY 15 10716 BV1M 10 CH 383.0 IM - S SAN SIMON PORT OF ENTRY PE PH 1 & 2 DESIGN FY 16 12215 YI1K 10 CH 388.0 H821601C IM - S SAN SIMON REST AREA NEW WELL,WATER PUMPS,STRUC,ELECT,MECH TBD FY 15 15513 KV1L 10 CH 381.0 H837101C BR - S SAN SIMON RIVER BR (STR #1167,1168 & 230) SCOUR RETROFIT MAR 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 9 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: WQ1L 19 PM 59.0 H771401C T SAN XAVIER PEDESTRIAN BRIDGE PEDESTRIAN BRIDGE IMPROVEMENTS NOV 13 12116 DW1M 191 AP 345.0 STP - H SANDERS - WITCH WELLS FENCING & CATTLE GUARDS TBD FY 16 23701 ZY1D 40 AP 340.0 H552601C 040-E(001) H SANDERS PORT OF ENTRY RECONSTRUCT POE TBD FY 15 11914 CG1L 8 PN 163.0 H827001C T SANTA ROSA WASH BRIDGES, STR # 1092 & 1093 SCOUR RETROFIT MAR 14 10117 BY1M 15 MO 0.0 F SCENIC TO STATE LINE PE PH 1 & 2 DESIGN FY 13 GQ1M 180 AP 403.5 180-C(201)A G SEVERAL LOCATIONS ON US180 SYSTEM PRESERVATION - ENGINEERING DESIGN FY 13 43414 WY1K 101L MA 41.0 H848401C E SHEA BLVD TO CHAPARRAL ROAD CONSTRUCT GPL MAR 14 10612 QP1C 60 NA 342.0 H510701C G SHOW LOW TO LITTLE MORMON LAKE WIDEN ROADWAY JUL 14 10313 GS1H 60 PN 222.0 STP -060-D(208)A G SILVER KING SECTION & SUPERIOR STREETS RECONSTRUCT TO 4 LANE RDWY W/CNT TURN L TBD FY 15 QM1L 0000 CN FLA SZ01901C STP -FLA-0(213)D F SITGREAVES ST, MILTON TO SANTE FE CONSTRUCTION OF ADA RAMPS FY 13 40115 WU1K 10 MA 0.0 E SKY HARBOR WEST AIRPORT ACCESS CONSTRUCT ACCESS RAMPS TBD FY 15 16615 XT1K 87 GI 226.0 H820701C NH - P SLATE CREEK ROAD REPAIR TBD FY 15 XZ1K 0000 YU SOM Y SOMERTON CANAL MUP:US95 TO COUNTY 17TH STRE SYSTEM ENHANCEMENT - ENGINEERING FY 14 13515 CQ1M 60 MA 189.0 STP - E SOSSAMAN - MERIDIAN DRAINAGE IMPROVEMENTS TBD FY 15 11515 QQ1H 89 CN 452.6 H705601C NH - F SOUTH OF GRAY MOUNTAIN PASSING LANES (NB AND SB) TBD FY 15 16215 DL1M 89A YV 343.0 STP - P SOUTH OF JEROME ROCKFALL MITIGATION TBD FY 15 12815 CE1M 40F MO 47.8 IM -999-A(398)T K SOUTH OF KINGMAN ROCKFALL MITIGATION TBD FY 15 10916 CB1M 17 YV 292.0 IM - P SOUTH OF MCGUIREVILLE ROCKFALL MITIGATION TBD FY 16 FK1M 93 YV 185.3 093-B(210)T P SOUTH OF SR71 - NORTH OF SR89 DESIGN ROADWAY WIDENING DESIGN FY 13 12316 EH1M 288 GI 289.0 STP - G SOUTH OF YOUNG ROCKFALL MITIGATION TBD FY 16 UU1K 0000 PM TUC T SPEEDWAY BLVD UNDERPASS @ UPRR ROADWAY RECONSTRUCTION FY 13 41213 YR1K 202L MA 9.0 RARF- E SR 101 TO GILBERT ROAD DESIGN GENERAL PURPOSE LANES DESIGN FY 14 45313 TR1H 17 MA 215.0 H844501C CM -017-A(230)A E SR 101L (AGUA FRIA) TO ANTHEM WAY CONSTRUCT FMS MAY 13 OP1L 101L MA 23.0 E SR 101L PIMA (I-17-PRINCESS DR) GP LANES DCR/ED CAPACITY ADDITIONS - ENGINEERING TBD FY 14 41814 WX1K 60 MA 148.9 E SR 101L, AGUA FRIA TO VAN BUREN STREET, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 14 12615 CA1M 17 YV 279.6 IM - P SR 169 TO MIDDLE VERDE ROAD RR(5" TL, 3" PL) + AR-ACFC TBD FY 15 LL1L 999 CH 0.0 H832801C STP -999-A(328)T S SR 186 & B-10, COCHISE COUNTY WIDE PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13 12407 FX1C 10 MA 161.2 H505101C E SR 202L (SANTAN) TO RIGGS ROAD CONST HOV & GEN PURPOSE LANE TBD FY 15 16715 EA1M 260 YV 220.0 STP - P SR 260 AT INDUSTRIAL DRIVE IN CAMP VERDE ROUNDABOUT DEC 14 BK1M 260 YV 218.9 P SR 260; INDUSTRIAL DR - HOMESTEAD PKWY DESIGN DESIGN FY 13 10114 MG1E 191 GH 100.7 S SR 266 TO ARTESIA DESIGN PARALLEL ROADWAY DESIGN FY 14 16512 DV1M 191 GH 104.0 STP - S SR 266 TO US 70 (REALIGNMENT) SCOPING DESIGN FY 13 15515 JC1H 286 PM 20.0 H690701C STP - T SR 286 (SASABE - ROBLES RANCH HWY) REPAIR HEADCUTTING PROBLEMS AT LW WATE TBD FY 15 43016 JJ1H 60 MA 139.0 HES -060-B(ATZ) E SR 303L TO SR 101L, AGUA FRIA, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 16 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 10 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: JG1H 801 MA 0.0 E SR 303L TO SR 202L STUDY TBD FY 14 IZ1K 303L MA 3.8 E SR 303L, RIGGS RD - SR 801 SYSTEM ENHANCEMENT-ENGINEERING TBD FY 14 YH1H 801 MA 0.0 E SR 801, SR 85 TO SR 303L NEW ROADWAY CONSTRUCTION TBD FY 14 12113 IP1L 10 MA 112.8 IM -010-A(216)A E SR 85 - VERRADO (EB) RR(4"TL, 3" PL) & AR-ACFC FEB 14 12214 VX1J 10 MA 105.0 H775001C IM - E SR 85 TO DYSART (VERRADO WAY TO 85) SIGN REHABILITATION JUL 13 14013 RO1K 587 PN 218.8 H811301C E SR 87 - JCT I-10 RR 3" & AR-ACFC MAY 13 GG1M 87 GI 252.0 087-B(218)A P SR 87 / SR 260 SAFETY IMPROVEMENT ACCESS CONTROL, SIGNING UPGRADES, ADA, M DESIGN FY 13 17610 SX1J 10 PN 208.8 H769601C STP -010-D(205)A T SR 87 TI TO TOWN OF PICACHO CAPACITY ADDITIONS - ENGINEERING TBD FY 13 25113 FS1M 89 YV 327.0 STP -089-B(213)T P SR 89 @ ROAD 1 NORTH IN CHINO VALLEY DESIGN DESIGN FY 13 10810 IV1A 89A CN 399.0 H413401C STP -A89-B(009)A F SR 89A JW POWELL BLVD CONSTRUCT INTERSECTION IMPROVEMENTS JUN 13 16914 VY1L 90 CH 321.0 H849701C HSIP-090-A(205)A S SR 92 - GIULIO CESARE AVENUE LIGHTING MAR 14 17014 HL1L 92 CH 322.1 H826501C HSIP- S SR 92 @ FOOTHILLS DR INTERSECTION IMPROVEMENTS JAN 14 HH1M 95 MO 239.0 095-D(208)T K SR 95 @ VALENCIA ROAD DESIGN DESIGN FY 13 19413 WY1L 95 LA 142.0 NH - Y SR 95 AT MOHAVE ROAD PE PH 1 & 2 DESIGN FY 13 VX1L 101L MA 46.0 E SR101L, CHAPARRAL ROAD TO SR202L GP LANES DESIGN FY 13 10412 DA1J 89 CN 464.5 H791501C NH -089-D(201)T F SR-64 TO LITTLE COLORADO RIVER CONSTRUCT 4-LANE URBAN, SR64 INTERSECTIO JAN 13 14115 GP1G 82 SC 40.5 STP - T SR-82 AT MP 40.6 EXTEND CBC & ELIMINATE GUARDRAIL TBD FY 15 15914 GR1G 82 SC 36.5 STP - T SR-82, MP 36.5 - 36.9 EXTEND 2 CBC'S AND ELIMINATE GUARDRAIL TBD FY 14 FO1M 87 MA 177.8 087-B(220)T E SR87 @ MCDOWELL RD DESIGN SIGNAL IMPROVEMENT DESIGN FY 13 19314 NC1H 88 MA 203.4 H700501C HSIP- E SR88, APACHE TRAIL GOLDFIELD TO CANYON LAKE SPOT SAFETY IMPROVEMENTS JUN 14 SL1L 95 MO 239.5 095-D(204)T K STATE ROUTE 95 @ STERLING RD DESIGN INTERSECTION IMPROVEMENT DESIGN FY 13 12914 EI1M 999 SW 0.0 HSIP- X STATEWIDE GUARDRAIL DELINEATORS TBD FY 14 16115 XX1L 999 SW 0.0 FA -999-A(383)T E STATEWIDE DYNAMIC MESSAGE SIGN PHASE 10 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 15 10917 EJ1M 999 SW 0.0 FA - X STATEWIDE DYNAMIC MESSAGE SIGN PHASE 11 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 17 21513 XV1K 999 SW 0.0 H820601C HSIP- E STATEWIDE TREE THINNING TREE REMOVAL FROM CLEAR ZONE, PE PH 1 & 2 DESIGN FY 13 13415 CN1M 40 NA 297.0 IM - H SUN VALLEY ROAD - WASHBOARD ROAD RR (5" TL, 3" PL) + 2"AC + FC JAN 15 YJ1L 69 YV 292.1 H854001C NH -069-A(211)T P SUNRISE BLVD TO PRESCOTT CANYON DR PAVEMENT PRESERVATION (AR-ACFC) MAR 13 16214 JD1L 88 PN 196.0 H830801C HSIP- E SUPERSTITION BLVD CONSTRUCT ROUNDABOUT JUN 14 11413 AY1G 77 PM 82.0 H669401C 077-A(204)T T TANGERINE RD TO PINAL COUNTY LINE WIDENING TO 6 LANES - CONSTRUCTION JUN 13 12115 YB1K 10 CH 320.5 H821101C IM - S TEXAS CANYON REST AREA WATER, STRUCTURAL, MECHANICAL & ELECTRI TBD FY 15 GA1L 0000 NA WIN SL71101C TEA -WIN-0(203)A H THE STATION AT LA POSADA REHAB OF STATION AND LANDSCAPE FY 14 44913 OE1L 303L MA 105.0 H850401C RARF- E THOMAS ROAD TO CAMELBACK ROAD CONSTRUCT LANDSCAPE TBD FY 14 17914 DZ1M 260 YV 211.2 STP - P THOUSAND TRAILS ROAD NEW TAPERS TO STANDARD TBD FY 14 10616 XD1K 260 YV 218.5 STP - P THOUSAND TRAILS TO I-17 CONSTRUCT INTERIM IMPROVEMENTS TBD FY 16 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 11 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 18213 DE1M 80 CH 317.0 STP - S TOMBSTONE REMOVE PEDESTRIAN BRIDGE TBD FY 13 15714 WH1K 80 CH 316.5 H800402C HSIP- S TOMBSTONE, MP 316.5 TO MP 318.0 LIGHTING AND SIDEWALKS MAR 15 17314 FN1L 160 CN 343.4 NH -160-A(203)A F TONALEA INSTALL INTERSECTION LIGHTING TBD FY 14 VK1J 0000 GI GGI HPP -GGI-0(204)A G TONTO CREEK BRIDGE DESIGN BRIDGE APPROACHES FY 13 13409 TQ1H 87 GI 263.0 H718301C P TONTO NATURAL BRIDGE STATE PARK CONSTRUCT NEW ROAD TBD FY 13 GU1M 86 PM 114.7 086-A(211)T T TOWN OF SELLS PEDESTRIAN BRIDGES CONSTRUCT PEDESTRIAN BRIDGE TBD FY 15 14215 KI1L 86 PM 115.8 T TOWN OF SELLS TO FRESNAL WIDEN SHOULDERS AND CULVERT EXTENSIONS TBD FY 15 XY1K 0000 MA QCR SS87601C CM -QCR-0(207)A E TOWNWIDE - ITS DEVELOPMENT SYSTEM ENHANCEMENT - TRAFFIC MGMT AND E FY 13 PK1K 0000 MA GDY SS89601C CM -GDY-0(203)A E TRAFFIC SIGNAL SYSTEM ITS BACKBONE & COMMUNICATION FY 13 14214 CJ1M 40 CN 185.0 IM - F TRANSWESTERN - LEUPP JCT PE PH 1 & 2 DESIGN FY 14 EP1K 0000 PM TUC SS73601C TUC-0(227)A T TUCSON BOULEVARD MULTI-USE PATH MULTI-USE PATH FY 13 11016 KH1L 40 CN 218.7 IM - F TWIN ARROWS TI, EB OFF-RAMP RAMP REMOVAL, RECONSTR & ACCESS CTRL M TBD FY 16 WK1L 940 MA 0.0 SR19101C STP -000-6(171)T E UNIVERSITY DR (TEMPE) 741-561J AT-GRADE RAILROAD CROSSING DESIGN AUG 13 JN1L 0000 MA MMA SS97201C E UPGRADE RADS REGIONWIDE SYSTEM UPGRADE FY 13 13214 RC1L 10 CH 333.0 IM -010-F(218)A S US 191 TO EAST WILLCOX TI RR (5" TL, 3" PL) & AR-ACFC JAN 14 18314 HR1L 264 AP 441.1 H824601C HSIP- H US 191 TO SAWMILL ROAD SEGMENT 1 SHOULDER WIDENING PROGRAM PE PH 1 & PH 2 DESIGN FY 14 QJ1L 60 NA 341.0 HX23901C G US 60 & 9TH PLACE, SHOW LOW TRAFFIC SIGNAL FEB 14 UV1L 60 MA 144.0 E US 60 / BELL ROAD TI DCR AND ENVIRONMENTAL ASSESSMENT TBD FY 14 IN1M 60 MA 109.9 060-A(207)S P US 60 @ APACHE STREET IN WICKENBURG DESIGN DESIGN FY 13 43015 EW1M 303L MA 0.0 RARF- E US 60 GRAND AVE / SR 303L TI, INTERIM LANDSCAPE CONSTRUCTION TBD FY 15 43914 XE1K 303L MA 118.0 H814501C E US 60 GRAND AVE / SR 303L TI, INTERIM CONSTRUCT INTERIM TI DEC 12 KK1L 93 MO 139.0 HPP -093-B(209) K US 93, SB BURRO CREEK BRIDGE SYSTEM PRESERVATION - ENGINEERING TBD FY 14 HS1K 0000 YU 0.0 SL64401C TEA -SOM-0(200)A Y US 96 BETWEEN SOMERTON AND BINGHAM AVENUES SYSTEM ENHANCEMENT-OTHER ENHANCEMENT FY 14 GA1M 191 GE 226 H843901C G US-191, GLOBE DISTRICT, WALLOW FIRE, SIGN REPAIR SYSTEM PRESERVATION (RESTORATION/REHAB/ DESIGN FY 13 NL1L 60 MA 143.0 E US60/THUNDEBIRD ROAD INTERSECTION RECONSTRUCT TI TBD FY 14 MO1K 95 YU 0.6 H801701C Y US95, 'A' ST TO JUAN SANCHEZ BLVD, SAN LUIS ROAD & PEDESTRIAN ENHANCEMENTS FEB 13 41215 XC1K 202L MA 43.0 CM - E VAL VISTA DR. - DOBSON RD CONSTRUCT FMS TBD FY 15 11508 AZ1G 86 PM 159.5 H680601C STP -086-A(210)T T VALENCIA RD - KINNEY RD CONSTRUCT ROADWAY WIDENING TO 4 LANES TBD FY 14 JM1L 0000 PM PPM SS97501C T VALENCIA ROAD: WADE RD TO MARK RD WIDEN ROADWAY FY 13 20513 EB1M 260 GI 262.0 NH - P VARIOUS BRIDGE APPROACHES REPAIR BRIDGE APPROACHES TBD FY 13 13915 RW1L 75 GE 387.0 BR - S VARIOUS BRIDGES (STR #S 861,202,242,983,243,251) SCOUR RETROFIT DEC 14 15815 QH1L 999 MA 0.0 STP - E VARIOUS LOCATIONS DRAINAGE TUNNEL IMPROVEMENTS TBD FY 15 22013 VX1K 999 MA 0.0 NH -999-A(215)T E VARIOUS LOCATIONS ON SR 101L AND I-17 PUMP STATION IMPROVEMENTS JAN 13 HP1L 0000 MA TMP SS96401C E VARIOUS LOCATIONS:WIRELESS COMMUNICATIONS & PROCUREMENT AND INSTALLATION FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 1ST SORT: PROJECT NAME Page 12 of 12 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: HT1M 17 YV 287.0 017-B( )T P VERDE RIVER BRIDGE NB #1731 DESIGN BRIDGE REHABILITATION DESIGN FY 13 ZE1L 17 YV 287.0 017-B(224)S P VERDE RIVER BRIDGES NB & SB #1731 & #505 DESIGN DEC 15 24013 BH1M 15 MO 15.0 H857401C 015-A(208)S F VIRGIN RIVER BRIDGE #6 (STR #1619) CMAR BRIDGE REHABILITATION CONSTRUCTION TBD FY 13 45212 OF1L 303L MA 114.0 RARF- E WADDELL ROAD TO MOUNTAIN VEIW ROAD CONSTRUCT LANDSCAPE JUN 13 14314 SD1K 40 CN 204.0 IM - F WALNUT CANYON - TWIN ARROWS RR 3" & 2" AC & AR-ACFC DEC 13 44811 ZN1J 85 MA 153.2 H800601C NH - E WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE TBD FY 14 HU1M 66 CN 91.0 066-A( )T K WASH BR #141 & TRUXTON WASH BR #142 DESIGN BRIDGE REHABILITATION DESIGN FY 13 11614 BM1M 8 YU 1.0 IM - Y WB OFF RAMP & GISS PARKWAY INTERSECTION INTERSECTION IMPROVEMENTS JUN 14 12513 IG1K 40 YV 132.1 H785701C K WEIGH STATION TO ASH FORK (WB) RR (5" TL, 3" PL) + FR FEB 13 NK1L 85 PM 42.0 T WELCOME ST. TO MP 42.5 SYSTEM PRESERVATION - ENGINEERING TBD FY 14 11216 CV1M 60 PN 232.0 STP - G WEST OF PINTO CREEK BRIDGE ROCKFALL MITIGATION TBD FY 16 11615 XP1L 10 LA 17.5 IM - Y WEST QUARTZSITE TI INTERSECTION IMPROVEMENTS TBD FY 15 JO1L 0000 MA MMA SS97301C E WEST VALLEY DMS INSTALL ARTERIAL DMS FY 13 ZI1L 80 CH 364.0 S WHITE WATER DRAW BRIDGE #1626 DESIGN DEC 15 13113 FF1G 73 NA 342.3 STP - G WHITERIVER TO COAL MINE CANYON 2" AC + FR FEB 14 ZV1L 0000 YU SLS CBI -SLS-0(201)A Y WIDENING AVE E FROM COUNTY 25TH STREET TO SR1 SYSTEM ENHANCEMENT (ENGINEERING) FY 14 12514 BT1M 10 MA 164.0 IM - E WILD HORSE PASS - RIGGS RR(5" TL - 3" PL) + AR-ACFC TBD FY 14 12414 FY1L 10 MA 162.0 IM -010-C(204)T E WILD HORSE PASS TO SR 347 (QUEEN CREEK ROAD) ROADWAY WIDENING TBD FY 14 17614 ST1K 186 CH 328.2 STP -186-A(200)A S WILLCOX TO KANSAS SETTLEMENT R & R 3" AC & CHIP SEAL APR 14 HV1M 40 MO 83.0 040-B(220)T K WILLOW CREEK BRIDGE NO 2 EB (#1593) DESIGN BRIDGE REHABILITATION DESIGN FY 13 13015 CI1M 40 MO 87.0 IM -040-B(217)T K WILLOW RANCH ROAD TO MP 92, EB RR (5" TL, 3" PL) + AR-ACFC WITH SHOULDERS E TBD FY 15 10417 CH1M 40 MO 83.0 IM - K WILLOW SPRINGS ROCKFALL MITIGATION TBD FY 17 11514 QN1C 40 AP 357.5 NH - H WINDOW ROCK TI PE PH 1 DESIGN FY 14 19514 DT1M 188 GI 240.0 STP - G WINDY HILL INSTALL DRAINAGE FACILITY CBC SEP 13 10017 XT1L 8 YU 0.0 IM - Y YUMA PORT OF ENTRY PE PH2 DESIGN FY 17 ZQ1F 0000 MA GDY SS54401C STP-GDY-0(008)A E YUMA RD @ BULLARD WASH CONST BOX CULVERTS FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 1 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: XZ1K 0000 YU SOM Y SOMERTON CANAL MUP:US95 TO COUNTY 17TH STRE SYSTEM ENHANCEMENT - ENGINEERING FY 14 JM1L 0000 PM PPM SS97501C T VALENCIA ROAD: WADE RD TO MARK RD WIDEN ROADWAY FY 13 OP1L 101L MA 23.0 E SR 101L PIMA (I-17-PRINCESS DR) GP LANES DCR/ED CAPACITY ADDITIONS - ENGINEERING TBD FY 14 NL1L 60 MA 143.0 E US60/THUNDEBIRD ROAD INTERSECTION RECONSTRUCT TI TBD FY 14 41814 WX1K 60 MA 148.9 E SR 101L, AGUA FRIA TO VAN BUREN STREET, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 14 43414 WY1K 101L MA 41.0 H848401C E SHEA BLVD TO CHAPARRAL ROAD CONSTRUCT GPL MAR 14 14413 RU1K 160 NA 358.1 H811901C F COUNTY LINE - BLACK MESA RR 3" & AR-ACFC FEB 13 14310 QQ1K 40 AP 358.5 H LUPTON TI DCR AND ENVIRONMENTAL STUDIES DESIGN FY 14 NK1L 85 PM 42.0 T WELCOME ST. TO MP 42.5 SYSTEM PRESERVATION - ENGINEERING TBD FY 14 YM1L 202L MA 9.0 H854301C E L101 TO MCDOWELL ROAD SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13 YQ1L 70 GH 347.0 H853801C S HAEKEL RD TO US 191 SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13 11112 CO1J 10 PM 236.4 T MARANA ROAD TO CORTARO ROAD DESIGN (RECONSTRUCT & WIDEN FRONTAGE R DESIGN FY 15 16006 QT1F 101L MA 53.5 E BALBOA DRIVE CONSTRUCT MULTI-USE PATH BRIDGE OVER TH IGA FY 15 16515 ZA1L 60 PN 228.8 G EAST OF QUEEN CREEK TUNNEL ROCKFALL MITIGATION TBD FY 15 UV1L 60 MA 144.0 E US 60 / BELL ROAD TI DCR AND ENVIRONMENTAL ASSESSMENT TBD FY 14 12513 IG1K 40 YV 132.1 H785701C K WEIGH STATION TO ASH FORK (WB) RR (5" TL, 3" PL) + FR FEB 13 UU1K 0000 PM TUC T SPEEDWAY BLVD UNDERPASS @ UPRR ROADWAY RECONSTRUCTION FY 13 JE1L 89 YV 328.0 H833001C P PERKINSVILLE RD ROUNDABOUT SYSTEM ENHANCEMENT - ENGINEERING DESIGN FY 13 10512 CZ1J 89 YV 319.0 H851801C P JCT SR 89A TO DEEPWELL RANCH ROAD WIDEN THE SR 89 CORRIDOR TBD FY 16 JO1L 0000 MA MMA SS97301C E WEST VALLEY DMS INSTALL ARTERIAL DMS FY 13 XT1H 180 AP 402.0 G JCT SR 260 / US 180 & RODEO GROUNDS INTERSECTIO REALIGN INTERSECTION TBD FY 13 13209 A6SP 87 NA 346.0 H717901C H HOMOLOVI RUINS STATE PARK CONSTRUCT ROAD TBD FY 14 10311 CY1J 77 PN 100.0 H739101C T ORACLE STATE PARK CONSTRUCT PARKING TBD FY 14 HZ1L 0000 MA SCT SS96701C E PAVEMENT PRESERVATION PHASE 3 PAVEMENT PRESERVATION FY 13 JP1L 0000 MA MMA SS97401C E ATIS ENHANCEMENTS REGIONWIDE ARTERIAL ATIS FY 13 14015 YZ1L 77 GI 156.8 G NEAR SUMMIT ROCKFALL MITIGATION TBD FY 15 XX1K 0000 MA CHN SS93201C E CONSOLIDATED CANAL MULTI-USE PATH PATHWAY/TRAIN IMPROVEMENTS FY 13 MO1K 95 YU 0.6 H801701C Y US95, 'A' ST TO JUAN SANCHEZ BLVD, SAN LUIS ROAD & PEDESTRIAN ENHANCEMENTS FEB 13 12413 RW1K 17 YV 245.0 H812101C P BLACK CANYON HILL (NB) RR (5" TL, 3" PL) & AR-ACFC APR 13 10112 JW1K 10 PN 186.7 T EARLEY ROAD TO JCT I-8 ROAD WIDENING TBD FY 16 JG1H 801 MA 0.0 E SR 303L TO SR 202L STUDY TBD FY 14 YH1H 801 MA 0.0 E SR 801, SR 85 TO SR 303L NEW ROADWAY CONSTRUCTION TBD FY 14 10612 QP1C 60 NA 342.0 H510701C G SHOW LOW TO LITTLE MORMON LAKE WIDEN ROADWAY JUL 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 2 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 13413 RS1K 89A CN 609.3 F FREDONIA - STATE LINE RR 3" & AR-ACFC TBD FY 13 12713 RQ1K 40 CN 158.6 F PINE SPRINGS - WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC TBD FY 13 12613 RP1K 40 YV 146.2 F EAST ASHFORK TI - COUNTY LINE RR 3" & 2" AC & AR-ACFC TBD FY 13 JN1M 89 YV 345.7 H863601C K HELL CANYON BRIDGE DECK REHABILITATION TBD FY 13 12913 RX1K 69 YV 271.6 H812201C P BIG BUG 4 TO POLAND JCT RR 3" TL, RR AR-ACFC FULL WIDTH MAR 13 23213 BM1L 64 CN 234.5 H825801C F GRAND CANYON AIRPORT- FS RD 328 SHOULDER WIDENING TBD FY 15 11414 CU1J 17 YV 232.0 P ROCK SPRINGS TO CORDES JUNCTION PE PH2 (WIDEN ROADWAY) DESIGN FY 14 VX1L 101L MA 46.0 E SR101L, CHAPARRAL ROAD TO SR202L GP LANES DESIGN FY 13 HC1J 10 LA 1.0 Y EHRENBERG EXIT 1 ROUNDABOUT JUN 13 HP1L 0000 MA TMP SS96401C E VARIOUS LOCATIONS:WIRELESS COMMUNICATIONS & PROCUREMENT AND INSTALLATION FY 13 KJ1K 8 MA 117.0 H800001C Y I-8 TO GILLESPIE CANAL REMOVE 3", REPLACE 2.5" & ACFC TBD FY 14 QJ1L 60 NA 341.0 HX23901C G US 60 & 9TH PLACE, SHOW LOW TRAFFIC SIGNAL FEB 14 13514 CF1L 17 MA 231.0 H826801C E NEW RIVER BRIDGES, STR # 1290 &1291 SCOUR RETROFIT JAN 14 13715 KX1L 70 GI 259.0 H835901C G GILSON WASH BRIDGE, STR # 464 SCOUR RETOFIT TBD FY 15 19414 HS1L 89 YV 330.0 H827801C P ROAD 4 NORTH CONSTRUCT ROUNDABOUT APR 14 45112 WB1L 303L MA 112.0 E PEORIA AVE - WADDELL RD LANDSCAPE CONSTRUCTION JUN 13 JQ1L 0000 MA SUR SS95801C E DOVE VALLEY ROAD,18TH AVE-203RD AVE ROADWAY IMPROVEMENTS FY 13 43814 OB1L 303L MA 107.0 E CAMELBACK ROAD TO GLENDALE AVENUE CONSTRUCT LANDSCAPE JUN 14 WQ1L 19 PM 59.0 H771401C T SAN XAVIER PEDESTRIAN BRIDGE PEDESTRIAN BRIDGE IMPROVEMENTS NOV 13 10117 BY1M 15 MO 0.0 F SCENIC TO STATE LINE PE PH 1 & 2 DESIGN FY 13 45213 NU1L 303L MA 0.0 E I-10/303L TI, PHASE I (I-10 REALIGNMENT) CONSTRUCT LANDSCAPE TBD FY 14 40313 DD1J 101L MA 23.5 E I-17 TO TATUM BLVD CONSTRUCT HOV LANE DESIGN FY 13 CD1L 260 AP 394.0 H826901C G LITTLE COLORADO RIVER BR (STR # 416) SYSTEM PRESERVATION - MINOR BRIDGE REHA TBD FY 16 12415 VT1K 17 MA 195.0 E BUCKEYE RD,GRANT ST,ADAMS ST & JEFFERSON ST ELECTRICAL REHABILITATION TBD FY 15 14215 KI1L 86 PM 115.8 T TOWN OF SELLS TO FRESNAL WIDEN SHOULDERS AND CULVERT EXTENSIONS TBD FY 15 10910 DJ1G 90 CH 323.5 H655501C S CENTRAL AVE TO MOSON RD, E OF SIERRA VISTA WIDEN TO 5 LANES TBD FY 14 18413 DF1M 83 SC 12.0 H850101C T MP 12 - MP 14 MILL AND PAVE TBD FY 13 15114 GN1J 70 GH 295.0 S BYLAS TWLTL & ROADWAY WIDENING JUN 14 10114 MG1E 191 GH 100.7 S SR 266 TO ARTESIA DESIGN PARALLEL ROADWAY DESIGN FY 14 41115 WW1K 202L MA 0.0 E SALT RIVER BRIDGE, SEGMENT 7 CONSTRUCT NEW FREEWAY TBD FY 16 41608 TY1H 202L MA 0.0 E I-10 EAST/SANTAN TI TO 51ST AVE DESIGN ROADWAY TBD FY 14 ZI1L 80 CH 364.0 S WHITE WATER DRAW BRIDGE #1626 DESIGN DEC 15 JN1L 0000 MA MMA SS97201C E UPGRADE RADS REGIONWIDE SYSTEM UPGRADE FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 3 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: YL1L 202L MA 9.0 H854201C E L101 TO MESA DRIVE SYSTEM PRESERVATION (RESTORATION/REHAB/ JUN 13 GA1M 191 GE 226 H843901C G US-191, GLOBE DISTRICT, WALLOW FIRE, SIGN REPAIR SYSTEM PRESERVATION (RESTORATION/REHAB/ DESIGN FY 13 45309 FN1H 10 MA 96.2 H708301X Y 395TH AVE (BELMONT RD) CONSTRUCT TI IGA FY 14 BK1M 260 YV 218.9 P SR 260; INDUSTRIAL DR - HOMESTEAD PKWY DESIGN DESIGN FY 13 10511 XQ1L 95 MO 182.0 K LAKE HAVASU STATE PARK (CONTACT POINT) PH II DESIGN PARKING DESIGN FY 15 WJ1L 0000 MA 0.0 SR23201C E DOBSON ROAD, AAR/DOT NO. 741-649-G SYSTEM ENHANCEMENT-SAFETY IMPROVEMENT FY 14 10413 TC1J 93 MO 116.0 K CARROW TO STEPHENS CONSTRUCT 4-LANE DIVIDED HIGHWAY TBD FY 16 14313 SB1K 87 GI 236.2 H812301C P JCT 188 - RYE RR 3" TL & AR-ACFC FULL WIDTH MAY 13 41015 NX1L 202L MA 0.0 E BASELINE - SALT RIVER, SEGMENT 6 CONSTRUCT NEW FREEWAY TBD FY 15 15414 JG1K 77 PN 123.5 H796901C T ARAVAIPA CREEK BRIDGE, STR #399 BRIDGE REPLACEMENT AUG 13 IZ1K 303L MA 3.8 E SR 303L, RIGGS RD - SR 801 SYSTEM ENHANCEMENT-ENGINEERING TBD FY 14 13409 TQ1H 87 GI 263.0 H718301C P TONTO NATURAL BRIDGE STATE PARK CONSTRUCT NEW ROAD TBD FY 13 10015 QL1J 10 PM 247.0 H758301C T INA RD TO RUTHRAUFF RD RECONSTRUCTION FOR WIDENING TBD FY 15 40115 WU1K 10 MA 0.0 E SKY HARBOR WEST AIRPORT ACCESS CONSTRUCT ACCESS RAMPS TBD FY 15 43914 XE1K 303L MA 118.0 H814501C E US 60 GRAND AVE / SR 303L TI, INTERIM CONSTRUCT INTERIM TI DEC 12 13815 SR1K 75 GE 379.1 S DUNCAN BRIDGE - LITTLE SANDS WASH 3" AC & AR-ACFC TBD FY 15 14013 RO1K 587 PN 218.8 H811301C E SR 87 - JCT I-10 RR 3" & AR-ACFC MAY 13 14913 YG1L 8 YU 125.0 Y GILA BEND TO I-10 SIGN REHABILITATION DESIGN FY 13 15208 NSSP 89A YV 365.0 F RED ROCK STATE PARK DESIGN DESIGN FY 13 11914 CG1L 8 PN 163.0 H827001C T SANTA ROSA WASH BRIDGES, STR # 1092 & 1093 SCOUR RETROFIT MAR 14 12407 FX1C 10 MA 161.2 H505101C E SR 202L (SANTAN) TO RIGGS ROAD CONST HOV & GEN PURPOSE LANE TBD FY 15 CX1G 0000 PM MRN SB41301C BR-MRN-0(014)A T INA BRIDGE OVER SANTA CRUZ BRIDGE REPLACEMENT FY 13 23701 ZY1D 40 AP 340.0 H552601C 040-E(001) H SANDERS PORT OF ENTRY RECONSTRUCT POE TBD FY 15 ZQ1F 0000 MA GDY SS54401C STP-GDY-0(008)A E YUMA RD @ BULLARD WASH CONST BOX CULVERTS FY 13 WL1L 940 MA 0.0 SR19201C 000-6(172)A E 5TH ST (TEMPE) 741-560-C AT-GRADE RAILROAD CROSSING DESIGN JUN 13 12013 SW1K 10 LA 63.0 H815901C 010-A(217)T Y GAS LINE RD - COUNTY LINE RR (1/2" TL, 4" PL) & AR-ACFC FEB 13 24013 BH1M 15 MO 15.0 H857401C 015-A(208)S F VIRGIN RIVER BRIDGE #6 (STR #1619) CMAR BRIDGE REHABILITATION CONSTRUCTION TBD FY 13 HT1M 17 YV 287.0 017-B( )T P VERDE RIVER BRIDGE NB #1731 DESIGN BRIDGE REHABILITATION DESIGN FY 13 ZE1L 17 YV 287.0 017-B(224)S P VERDE RIVER BRIDGES NB & SB #1731 & #505 DESIGN DEC 15 HV1M 40 MO 83.0 040-B(220)T K WILLOW CREEK BRIDGE NO 2 EB (#1593) DESIGN BRIDGE REHABILITATION DESIGN FY 13 GT1M 40 NA 289.0 040-D(227)T H E HOLBROOK TI OP EB#1369 & WB #1370 DESIGN BRIDGE REHABILITATION DESIGN FY 13 IN1M 60 MA 109.9 060-A(207)S P US 60 @ APACHE STREET IN WICKENBURG DESIGN DESIGN FY 13 OR1K 60 GI 290.0 H808301C 060-E(206)T G MP 290, 296 AND 320 AT HAGEN HILL ROCKFALL CONTAINMENT FEB 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 4 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 15014 BT1L 60 GI 292.0 H826201C 060-E(207)A G SALT RIVER CANYON REST AREA REPLACE COMPOSTING TOILETS & STRUCTURA DEC 13 HU1M 66 CN 91.0 066-A( )T K WASH BR #141 & TRUXTON WASH BR #142 DESIGN BRIDGE REHABILITATION DESIGN FY 13 17913 LX1G 75 GE 384.0 075-A(200)T S LITTLE SANDS WASH BANK PROTECTION AUG 13 11413 AY1G 77 PM 82.0 H669401C 077-A(204)T T TANGERINE RD TO PINAL COUNTY LINE WIDENING TO 6 LANES - CONSTRUCTION JUN 13 GU1M 86 PM 114.7 086-A(211)T T TOWN OF SELLS PEDESTRIAN BRIDGES CONSTRUCT PEDESTRIAN BRIDGE TBD FY 15 GX1M 86 PM 120.6 086-A-NFA T FRESNAL TO MP 123.9 DESIGN DESIGN FY 13 GG1M 87 GI 252.0 087-B(218)A P SR 87 / SR 260 SAFETY IMPROVEMENT ACCESS CONTROL, SIGNING UPGRADES, ADA, M DESIGN FY 13 FO1M 87 MA 177.8 087-B(220)T E SR87 @ MCDOWELL RD DESIGN SIGNAL IMPROVEMENT DESIGN FY 13 18313 MI1K 89 YV 335.9 H797601C 089-B(204)T P BIG CHINO WASH BRIDGE #979 DECK REPLACEMENT / WIDENING JAN 13 18713 MS1K 89 YV 333.1 H791901C 089-B(208)T P DEL RIO RANCH BRIDGE #20046 BRIDGE REPLACEMENT JAN 13 XA1L 89 YV 345.0 089-B(211)T K HELL CANYON BRIDGE #483 REPLACEMENT & WIENING TBD FY 14 FK1M 93 YV 185.3 093-B(210)T P SOUTH OF SR71 - NORTH OF SR89 DESIGN ROADWAY WIDENING DESIGN FY 13 SL1L 95 MO 239.5 095-D(204)T K STATE ROUTE 95 @ STERLING RD DESIGN INTERSECTION IMPROVEMENT DESIGN FY 13 HH1M 95 MO 239.0 095-D(208)T K SR 95 @ VALENCIA ROAD DESIGN DESIGN FY 13 VS1L 101L MA 60.0 H848801C 101-C(201)A E GALVESTON DRAINAGE BASIN G (THUDE PARK) DRAINAGE IMPROVEMENT & PUMP STATION IGA FY 13 GQ1M 180 AP 403.5 180-C(201)A G SEVERAL LOCATIONS ON US180 SYSTEM PRESERVATION - ENGINEERING DESIGN FY 13 14112 AI1K 191 CH 61.5 H788301C 191-A(203)A S COCHISE POWER PLANT - JCT I-10 RR 2" AC + 3" AC + FR TBD FY 14 GP1M 191 AP 247.8 191-C(216)A G RIGHT OF WAY FENCE IN BOTH DIRECTIONS RIGHT OF WAY FENCING DESIGN FY 13 GO1M 260 AP 385.5 260-C(205)A G RIGHT OF WAY FENCING TWO LOCATIONS EAST BOUN RIGHT OF WAY FENCING DESIGN FY 13 XX1G 264 AP 446.0 264-A(212)T H GANADO WASH BRIDGE #1046 DESIGN BRIDGE REPLACEMENT DESIGN FY 14 CY1M 347 PN 172.0 347-A(209)T T ALTERRA TO CASA BLANCA RD, CITY OF MARICOPA DESIGN DESIGN FY 13 WM1L 5013 MA 0.0 SR14401C 501-3(001)P E 32ND ST ( PHX) #741-536-B SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13 WN1L 7018 MA 0.0 SR09701C 701-8(003)P E 40TH ST PHOENIX 741-539-W SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13 16414 IS1J 89 CN 385.1 H741801C A89-B(204)A F OAK CREEK CANYON CREEK BANK PROTECTION TBD FY 14 14315 SG1L 87 PN 148.0 BR - T GILA RIVER BRIDGE, STR #635 SCOUR RETROFIT DEC 14 15613 RH1L 17 MA 238.6 BR - P MOORES GULCH BRIDGE SB #339 DESIGN BRIDGE REPLACEMENT DESIGN FY 13 16713 KW1L 40 NA 271.0 H837201C BR - H MANILA WASH BRIDGES STR #851,852 & 2080 SCOUR RETROFIT MAR 13 13915 RW1L 75 GE 387.0 BR - S VARIOUS BRIDGES (STR #S 861,202,242,983,243,251) SCOUR RETROFIT DEC 14 15513 KV1L 10 CH 381.0 H837101C BR - S SAN SIMON RIVER BR (STR #1167,1168 & 230) SCOUR RETROFIT MAR 13 13315 JL1K 40 NA 284.3 BR -040-D(223)A H LEROUX WASH BRIDGE EB #1772 & WB #1773 BRIDGE REPAIR TBD FY 15 14814 RE1L 60 MA 115.5 BR -060-B(209)T P MONARCH WASH BR, STR #204 & 759 SCOUR RETROFIT DEC 13 15514 NH1L 77 GI 147.6 H832201C BR -077-A(207)A G DRIPPING SPRING BRIDGE #398 BRIDGE REPLACEMENT JUL 13 18113 NY1K 79 PN 101.8 H807501C BR -079-A(205)T T CORONADO WASH BRIDGE STRUCTURE #222 BRIDGE REPLACEMENT MAY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 5 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 16114 VM1K 87 CN 323.9 BR -087-C(203)A H LIMESTONE WASH BRIDGE # BRIDGE REPLACEMENT JUL 13 14615 JR1L 92 CH 340.5 BR -092-A(203)A S SAN PEDRO RIVER BRIDGE #449 BRIDGE REPLACEMENT TBD FY 15 ZN1E 0000 PN PPN SB41001C BR -PPN-0-(169) G KELVIN BRIDGE - #8441 BRIDGE REPLACEMENT FY 13 BA1L 0000 YU YYU SB43701C BR -YYU-0(201)T Y COUNTY 19TH ST BRIDGE OVER MAIN DRAIN (AVE F 1/2 BRIDGE REPLACEMENT FY 13 XD1L 0000 YU YYU SB44501C BR -YYU-0(205)A Y BRIDGE REHABILITATION OLD HWY 80 & AVE 30 1/2 E BRIDGE REHABILITATION FY 14 ZV1L 0000 YU SLS CBI -SLS-0(201)A Y WIDENING AVE E FROM COUNTY 25TH STREET TO SR1 SYSTEM ENHANCEMENT (ENGINEERING) FY 14 43208 ST1H 202L MA 44.0 CM - E LINDSAY ROAD TO GILBERT ROAD DESIGN & CONST MULTI-USE PATH TBD FY 13 41215 XC1K 202L MA 43.0 CM - E VAL VISTA DR. - DOBSON RD CONSTRUCT FMS TBD FY 15 45313 TR1H 17 MA 215.0 H844501C CM -017-A(230)A E SR 101L (AGUA FRIA) TO ANTHEM WAY CONSTRUCT FMS MAY 13 44814 TX1H 202L MA 47.8 CM -888-A(218)T E DOBSON ROAD TO I-10, MARICOPA CONSTRUCT FMS TBD FY 14 PK1K 0000 MA GDY SS89601C CM -GDY-0(203)A E TRAFFIC SIGNAL SYSTEM ITS BACKBONE & COMMUNICATION FY 13 OC1K 0000 MA MES SS87701C CM -MES-0(216)A E LOCAL AGENCY WIDE - FIBER-OPTIC COMMUNICATION FIBER OPTICS FY 13 PI1K 0000 MA MES SS89101C CM -MES-0(217)A E ITS TRAFFIC SIGNAL CONVERSIONS - PHASE 5 FIBER-OPTIC COMMUNICATIONS NET FY 13 BB1L 0000 MA MMA SS83001C CM -MMA-0(214)A E OLIVE AVE: LITCHFIELD ROAD TO LOOP 101 INSTALL FIBER OPTIC CONDUIT FY 13 PL1K 0000 MA MMA SS89901C CM -MMA-0(228)A E 87TH AVENUE PAVING DIRT ROAD FY 13 CC1L 0000 MA MMA SS95701C CM -MMA-0(231)A E 88TH AVE: DEER VALLEY TO WILLIAMS RD PAVE UNPAVED ROAD FY 13 ZS1J 0000 MA PHX CM -PHX-0(223)A E SALT RIVER PATHWAY - 24TH ST TO I-10 TEMPE DRAIN PATHWAY IMPROVEMENTS FY 13 XY1K 0000 MA QCR SS87601C CM -QCR-0(207)A E TOWNWIDE - ITS DEVELOPMENT SYSTEM ENHANCEMENT - TRAFFIC MGMT AND E FY 13 UH1K 0000 MA SCT SS91301C CM -SCT-0(211)A E DYNAMITE BLVD - PIMA TO ALMA SCHOOL ROAD INSTALL CURB AND GUTTER FY 13 ZJ1K 0000 MA SUR SS85401C CM -SUR-0(210)A E BELL RD-US 60 TO 114TH AVE CONSTRUCT MULTI-USE PATH FY 14 LK1K 0000 MA TMP SS73401C CM -TMP-0(210)X E BROADWAY ROAD: RURAL TO MILL AVENUE PEDESTRIAN IMPROVEMENTS FY 15 BX1L 0000 MA TMP SS95301C CM -TMP-0(217)A E SALT RIVER MUP: I-10/TEMPE DRAIN TO PRIEST DRIVE PATHWAY IMPROVEMENTS FY 13 22910 YS1K 0000 CH DGS SS87401C DGS-0(200)A S CHINO ROAD NEW FACILITIES - CONSTRUCTION OF NEW ROA FY 14 10917 EJ1M 999 SW 0.0 FA - X STATEWIDE DYNAMIC MESSAGE SIGN PHASE 11 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 17 22413 YC1L 64 CN 0.0 H817202C FA - F RURAL INTELLIGENT TRANSPORTATION SYSTEMS - PH CONSTRUCT FEB 13 16115 XX1L 999 SW 0.0 FA -999-A(383)T E STATEWIDE DYNAMIC MESSAGE SIGN PHASE 10 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 15 43016 JJ1H 60 MA 139.0 HES -060-B(ATZ) E SR 303L TO SR 101L, AGUA FRIA, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 16 KK1L 93 MO 139.0 HPP -093-B(209) K US 93, SB BURRO CREEK BRIDGE SYSTEM PRESERVATION - ENGINEERING TBD FY 14 VK1J 0000 GI GGI HPP -GGI-0(204)A G TONTO CREEK BRIDGE DESIGN BRIDGE APPROACHES FY 13 MD1K 0000 NA PLS SS86401C HPP -PLS-0(201)A G BILLY CREEK BRIDGE @ PORTER MOUNTAIN ROAD CAPACITY ADDITIONS - MAJOR WIDENING FY 13 BP1J 0000 PM TUC HPP -TUC-0(201)A T HOUGHTON ROAD WIDENING @ UPRR ROAD WIDENING OVER RAILROAD BRIDGE FY 16 GZ1L 0000 PM TUC HPP -TUC-0(241)A T HOUGHTON RD: UPRR TO I-10 - WIDENING ROADWAY WIDENING FY 16 12914 EI1M 999 SW 0.0 HSIP- X STATEWIDE GUARDRAIL DELINEATORS TBD FY 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 6 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 16513 DH1M 87 CN 268.1 HSIP- P MP 268.1 - MP 278 PE PH 1 & 2 DESIGN FY 13 18314 HR1L 264 AP 441.1 H824601C HSIP- H US 191 TO SAWMILL ROAD SEGMENT 1 SHOULDER WIDENING PROGRAM PE PH 1 & PH 2 DESIGN FY 14 19314 NC1H 88 MA 203.4 H700501C HSIP- E SR88, APACHE TRAIL GOLDFIELD TO CANYON LAKE SPOT SAFETY IMPROVEMENTS JUN 14 15714 WH1K 80 CH 316.5 H800402C HSIP- S TOMBSTONE, MP 316.5 TO MP 318.0 LIGHTING AND SIDEWALKS MAR 15 17114 IP1K 93 MO 17.4 HSIP- K MP 17.4 - MP 58.4 PE PH 1 & 2 DESIGN FY 14 14914 CU1M 60 GI 229.4 HSIP- G MP 229.4 - MP 232.91 SHOULDER WIDENING TBD FY 14 15413 HJ1J 8 YU 7.2 HSIP- Y I-8 AND ARABY ROAD PE PH 1 AND 2 DESIGN FY 13 13613 SC1K 191 CH 38.2 HSIP- S JCT SR 181 - PEARCE ROAD 3" AC & AR-ACFC MAY 13 20613 MQ1L 260 NA 282.5 HSIP- P RIM RD TO GIBSON RD, SEGMENTS 1, 2 & 3 SHOULDER WIDENING PROGRAM, PE PH 1 & 2 DESIGN FY 13 21513 XV1K 999 SW 0.0 H820601C HSIP- E STATEWIDE TREE THINNING TREE REMOVAL FROM CLEAR ZONE, PE PH 1 & 2 DESIGN FY 13 16214 JD1L 88 PN 196.0 H830801C HSIP- E SUPERSTITION BLVD CONSTRUCT ROUNDABOUT JUN 14 17014 HL1L 92 CH 322.1 H826501C HSIP- S SR 92 @ FOOTHILLS DR INTERSECTION IMPROVEMENTS JAN 14 19214 HM1L 77 PN 105.4 H826701C HSIP- T POWER LINE - SAN MANUEL ROAD DESIGN SHOULDER WIDENING DESIGN FY 14 15813 BX1M 69 YV 281.1 HX24201C HSIP-069-A(210)T P MP 281.1 - MP 289.7 MODIFY SIGNALS JUN 13 16914 VY1L 90 CH 321.0 H849701C HSIP-090-A(205)A S SR 92 - GIULIO CESARE AVENUE LIGHTING MAR 14 19213 LC1J 92 CH 324.3 H716701C HSIP-092-A(200)T S BUFFALO SOLDIER TRAIL TO KACHINA TRAIL RAISED MEDIAN JUN 13 17214 XL1L 95 LA 149.2 HSIP-095-C(216)A Y CIENEGA SPRINGS RD SB LEFT TURN LANE APR 14 23913 ZC1L 999 SW 0.0 HSIP-999-A(377)S F I-17 AND I-40, INLAID PAVEMENT MARKERS, SEGMENT I INLAID PAVEMENT MARKINGS TBD FY 13 44909 FM1H 10 MA 105.0 H683801X I -010-A-901 Y I-10/DESERT CREEK TI (PRIVATE FUNDS) CONSTRUCT TI IGA FY 14 14314 SD1K 40 CN 204.0 IM - F WALNUT CANYON - TWIN ARROWS RR 3" & 2" AC & AR-ACFC DEC 13 45414 ET1M 202L MA 0.0 IM - E I-10 PAPAGO/ SR202L SYSTEM INTERCHANGE SEGMEN DESIGN NEW SYSTEM TI DESIGN FY 14 11715 BA1M 10 LA 42.0 IM - Y MP 42 TO HOVATTER ROAD RR(4" TL, 3" PL) + AR-ACFC TBD FY 15 16313 PY1E 40 YV 102.0 IM - K CROSS MT - JOLLY RD UPGRADE EXISTING ROCKFALL PROTECTION TBD FY 13 10317 CG1M 40 MO 81.0 IM - K EAST OF US 93 TI ROCKFALL MITIGATION TBD FY 17 42115 ER1M 202L MA 0.0 IM - E ELLIOT RD - BASELINE RD, SEGMENT 5 DESIGN NEW FREEWAY DESIGN FY 15 10217 CD1M 40 MO 40.0 IM - K CROOKTON TO TRANSWESTERN SIGN REHABILITATION TBD FY 17 10417 CH1M 40 MO 83.0 IM - K WILLOW SPRINGS ROCKFALL MITIGATION TBD FY 17 12915 CF1M 40 MO 74.0 IM - K HWY 141 JCT TO SILVER SPRINGS ROAD (WB) RR (5"TL, 3" PL) + AR-ACFC + SHOULDERS TBD FY 15 40017 ES1M 202L MA 0.0 IM - E I-10 MARICOPA - 24TH ST, SEGMENT 1 CONSTRUCT NEW FREEWAY TBD FY 17 12816 CM1M 40 NA 297.0 IM - H GOODWATER - YELLOWHORSE PE PH 1 & 2 DESIGN FY 16 40016 EK1M 10 MA 129.5 IM - E DYSART RD - 83RD AVE DESIGN & CONSTRUCT FMS TBD FY 16 12615 CA1M 17 YV 279.6 IM - P SR 169 TO MIDDLE VERDE ROAD RR(5" TL, 3" PL) + AR-ACFC TBD FY 15 10916 CB1M 17 YV 292.0 IM - P SOUTH OF MCGUIREVILLE ROCKFALL MITIGATION TBD FY 16 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 7 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 10017 XT1L 8 YU 0.0 IM - Y YUMA PORT OF ENTRY PE PH2 DESIGN FY 17 12315 BW1M 15 MO 0.0 IM - F NEVADA STATE LINE - MP 13 RR(4" TL, 3" PL) AR-ACFC TBD FY 15 11016 KH1L 40 CN 218.7 IM - F TWIN ARROWS TI, EB OFF-RAMP RAMP REMOVAL, RECONSTR & ACCESS CTRL M TBD FY 16 12115 YB1K 10 CH 320.5 H821101C IM - S TEXAS CANYON REST AREA WATER, STRUCTURAL, MECHANICAL & ELECTRI TBD FY 15 16613 CK1M 40 NA 226.0 IM - H EAST WINSLOW TI PE PH 1 & 2 DESIGN FY 13 12613 NQ1L 40 CN 146.0 H840201C IM - F EAST ASHFORK TI TO WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC APR 13 17013 QD1L 40 NA 298.0 IM - H MP 298 UTILITY OVERPASS DESIGN OF CBC EXTENSION JAN 15 16913 CL1M 40 NA 290.0 IM - H HOLBROOK - SUN VALLEY FENCING AND CATTLE GUARDS TBD FY 13 13415 CN1M 40 NA 297.0 IM - H SUN VALLEY ROAD - WASHBOARD ROAD RR (5" TL, 3" PL) + 2"AC + FC JAN 15 14714 QO1L 40 NA 303.0 IM - H ADAMANA TI DRAINAGE IMROVEMENTS TBD FY 14 11814 SV1K 8 YU 13.7 H815801C IM - Y FOOTHILLS BLVD - DOME VALLEY RR (5" TL, 3" PL) & FR NOV 13 12215 YI1K 10 CH 388.0 H821601C IM - S SAN SIMON REST AREA NEW WELL,WATER PUMPS,STRUC,ELECT,MECH TBD FY 15 12715 SU1K 19 SC 16.0 IM - T PALO PARADO - CHAVEZ SLIDING TI RR (4" TL, 3" PL) + FR TBD FY 15 14214 CJ1M 40 CN 185.0 IM - F TRANSWESTERN - LEUPP JCT PE PH 1 & 2 DESIGN FY 14 12514 BT1M 10 MA 164.0 IM - E WILD HORSE PASS - RIGGS RR(5" TL - 3" PL) + AR-ACFC TBD FY 14 11915 BU1M 10 CH 296.0 IM - T MESCAL ROAD TO JCT SR 90 RR(5" TL, 3" PL) + AR-ACFC TBD FY 15 10716 BV1M 10 CH 383.0 IM - S SAN SIMON PORT OF ENTRY PE PH 1 & 2 DESIGN FY 16 12415 HW1L 17 MA 202.3 IM - E INDIAN SCHOOL ROAD - PEORIA AVENUE SIGN REHABILITATION TBD FY 15 13003 FR1C 8 YU 55.9 H206001C IM - Y MOHAWK REST AREA CONSTRUCT REST AREA TBD FY 15 12014 BR1M 10 MA 145.0 IM - E 3RD AVENUE TO 3RD STREET PUMP STATION IMPROVEMENTS TBD FY 14 12214 VX1J 10 MA 105.0 H775001C IM - E SR 85 TO DYSART (VERRADO WAY TO 85) SIGN REHABILITATION JUL 13 44612 WR1K 10 MA 151.5 IM - E 32ND ST - SR202L, SANTAN PHASE 1 CONSTRUCT LOCAL EXPRESS LANES DESIGN FY 17 12515 BZ1M 17 MA 198.0 IM - E BUCKEYE RD, GRANT,JEFFERSON & ADAMS ELECTRICAL REHABILITATION TBD FY 15 10816 GQ1J 17 MA 216.0 IM - E I-17 @ PEORIA AND UNION HILLS DRAINAGE GRATE IMPROVEMENTS TBD FY 16 11913 TI1K 8 PN 170.0 IM - T BIANCO ROAD - JCT I-10 RR(5" TL, 3" PL) & AR-ACFC NOV 13 14414 EV1L 40 CN 218.7 H789001C IM - F CANYON PADRE BRIDGE, STR #1670 DECK REPLACEMENT APR 14 11615 XP1L 10 LA 17.5 IM - Y WEST QUARTZSITE TI INTERSECTION IMPROVEMENTS TBD FY 15 11714 BN1M 8 YU 2.0 IM - Y 16TH STREET LANDSCAPING JUN 14 11614 BM1M 8 YU 1.0 IM - Y WB OFF RAMP & GISS PARKWAY INTERSECTION INTERSECTION IMPROVEMENTS JUN 14 12113 IP1L 10 MA 112.8 IM -010-A(216)A E SR 85 - VERRADO (EB) RR(4"TL, 3" PL) & AR-ACFC FEB 14 12414 FY1L 10 MA 162.0 IM -010-C(204)T E WILD HORSE PASS TO SR 347 (QUEEN CREEK ROAD) ROADWAY WIDENING TBD FY 14 12314 YD1L 10 MA 144.9 IM -010-C(209)T E 3RD AVENUE TO 3RD STREET, DECK PARK TUNNEL DRAINAGE IMPROVEMENTS TBD FY 14 12714 AZ1M 10 PM 268.0 IM -010-D(215)T T I-19 TO CRAYCROFT ROAD IN TUCSON SIGN REHABILITATION AUG 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 8 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: HB1M 10 PN 209.9 H861401C IM -010-D(217)T T LA PALMA RD TO PICACHO HWY DESIGN PAVEMENTPRESERVATION PROJECT DESIGN FY 13 12814 NB1K 10 PM 283.6 H805201C IM -010-E(208)A T DAVIDSON CANYON - COUNTY LINE MILL AND REPLACE NOV 13 11815 NA1L 10 PM 284.4 IM -010-E(213)A T DAVIDSON CANYON WB BRIDGE, STR #598 SUPERSTRUCTURE REPLACEMENT TBD FY 15 12213 SQ1K 10 CH 318.8 H815101C IM -010-F(216)T S DRAGOON RD - WEST WILLCOX TI (WB) PAVEMENT PRESERVATION APR 13 13214 RC1L 10 CH 333.0 IM -010-F(218)A S US 191 TO EAST WILLCOX TI RR (5" TL, 3" PL) & AR-ACFC JAN 14 12015 WD1L 10 CH 306.7 IM -010-F(219)A S SAN PEDRO RIVER BRIDGE EB #1530 & WB #1531 DECK REPLACEMENT & SCOUR RETROFIT TBD FY 15 13614 SO1K 17 YV 269.2 IM -017-B(218)A P DUGAS TI - CHERRY ROAD RR (5" TL, 3" PL) & AR-ACFC DEC 13 13814 MT1L 19 SC 0.3 IM -019-A(216)A T INTERNATIONAL BORDER - JCT B-19 RR AR-ACFC JUN 13 QP1J 40 MO 66.5 IM -040-B(208)A K I-40, BLAKE RANCH RD TI IMPROVEMENTS TBD FY 13 14114 SM1K 40 MO 57.0 IM -040-B(213)A K RATTLESNAKE WASH - JCT US 93 RR(5" TL, 3" PL) & AR-ACFC TBD FY 14 13015 CI1M 40 MO 87.0 IM -040-B(217)T K WILLOW RANCH ROAD TO MP 92, EB RR (5" TL, 3" PL) + AR-ACFC WITH SHOULDERS E TBD FY 15 16413 IW1L 40 CN 180.8 IM -040-C(208)A F EAST OF PARKS ROCKFALL MITIGATION JUN 13 14514 EE1K 40 NA 254.6 IM -040-D(213)A H RUBY WASH BRIDGE - E WINSLOW TI OP BRIDGE REHABILITATION JUL 13 14614 SJ1K 40 NA 290.2 H813101C IM -040-D(219)A H HOLBROOK - SUN VALLEY RR (5"TL, 3"PL) & AR-ACFC JUL 13 12813 ZY1J 40 NA 303.1 H785901C IM -040-E(214)T H BIG LITHODENDRON-PETRIFIED FOREST NATIONAL PA PAVEMENT PRESERVATION MAR 13 13115 WT1L 40 YV 144.0 IM -089-B(214)T K ASHFORK RR BR - JCT SR 89, #807,#440, #1760,#1761 BRIDGE DECK REHABILITATION TBD FY 15 40616 EV1M 303L MA 103.2 IM -303-A(216)S E I-10/303L TI, PHASE II CONSTRUCT NEW FREEWAY TBD FY 16 12815 CE1M 40F MO 47.8 IM -999-A(398)T K SOUTH OF KINGMAN ROCKFALL MITIGATION TBD FY 15 45314 EQ1M 202L MA 0.0 NH - E 24TH ST - 17TH AVE, SEGMENT 2 DESIGN NEW FREEWAY DESIGN FY 14 44811 ZN1J 85 MA 153.2 H800601C NH - E WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE TBD FY 14 12216 LY1C 260 GI 258.0 NH - P LION SPRINGS SECTION RECONSTRUCT TO A 4-LANE DIVIDED TBD FY 16 14515 FP1L 89 CN 525.0 NH - F JCT US 89A - BIG CUT EP (PIPE) DROP-OFF MITIGATION TBD FY 15 20513 EB1M 260 GI 262.0 NH - P VARIOUS BRIDGE APPROACHES REPAIR BRIDGE APPROACHES TBD FY 13 40216 EN1M 60 MA 192.0 NH - E CRISMON RD - MERIDIAN RD DESIGN HOV/GPL DESIGN FY 16 16615 XT1K 87 GI 226.0 H820701C NH - P SLATE CREEK ROAD REPAIR TBD FY 15 11207 QK1C 19 PM 58.7 NH - T AJO WAY TI (JCT SR 86) RECONSTRUCT TI TBD FY 17 16814 HG1L 89 CN 551.0 NH - F PAGE MAINTENANCE YARD WIDENING FOR TURN LANES TBD FY 14 11515 QQ1H 89 CN 452.6 H705601C NH - F SOUTH OF GRAY MOUNTAIN PASSING LANES (NB AND SB) TBD FY 15 16714 FD1L 89 CN 523.9 NH - F BITTER SPRINGS INSTALL INTERSECTION LIGHTING TBD FY 14 14213 DN1M 89 CN 420.0 NH - F FLAGSTAFF CITY LIMITS - LENOX PARK FEASIBILITY REPORT FOR ACCESS MGT PLANNI DESIGN FY 13 12716 FG1M 202L MA 0.0 NH - E PUMP STATION FLOOD EROSION CONTROL TBD FY 16 19413 WY1L 95 LA 142.0 NH - Y SR 95 AT MOHAVE ROAD PE PH 1 & 2 DESIGN FY 13 10015 VH1L 10 PM 252.0 NH - T RUTHRAFF ROAD TI RECONSTRUCTION FOR WIDENING TBD FY 15 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 9 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 40913 CM1J 10 MA 122.0 H770901C NH - E PERRYVILLE ROAD TI CONSTRUCT TI APR 13 11514 QN1C 40 AP 357.5 NH - H WINDOW ROCK TI PE PH 1 DESIGN FY 14 11312 CQ1J 10 PM 264.0 NH - T COUNTRY CLUB ROAD TI DESIGN TRAFFIC INTERCHANGE (PE PH 1) DESIGN FY 16 13016 TL1L 101L MA 50.7 NH - E RED MOUNTAIN - CHANDLER BLVD SIGN REHABILITATION TBD FY 16 10216 DO1M 93 MO 109.0 NH - K CANE SPRINGS PE PH 1 & 2 DESIGN FY 16 17413 CP1M 40 AP 322.0 NH - H CHAMBERS PORT OF ENTRY PE PH 1 & 2 DESIGN FY 13 15710 NN1F 10 LA 3 H616101C NH - Y EHRENBERG PORT OF ENTRY RECONSTRUCT EB PORT OF ENTRY TBD FY 16 10208 PJ1F 10 PM 248.0 NH -010-D T INA ROAD TI RECONSTRUCT TI & MAINLINE TBD FY 16 40613 NM1L 60 MA 194.0 NH -060-C(207)T E MERIDIAN ROAD. HALF TI CONSTRUCT TI TBD FY 14 YJ1L 69 YV 292.1 H854001C NH -069-A(211)T P SUNRISE BLVD TO PRESCOTT CANYON DR PAVEMENT PRESERVATION (AR-ACFC) MAR 13 10412 DA1J 89 CN 464.5 H791501C NH -089-D(201)T F SR-64 TO LITTLE COLORADO RIVER CONSTRUCT 4-LANE URBAN, SR64 INTERSECTIO JAN 13 13812 AH1K 89 CN 510.0 NH -089-D(202)A F GRAY SPOT WASH - NORTH RED HILL 3" AC + FR NOV 13 10312 LE1G 93 MO 101.8 H738801C NH -093-B(204)T K ANTELOPE WASH CONSTRUCT 4-LANE DIVIDED HIGHWAY FEB 13 19313 DP1M 93 MO 125.0 NH -093-B(211)T K MEDLIN CROSSOVER DESIGN AND CONSTRUCT NEW CROSSOVER DESIGN FY 13 10416 NW1L 95 YU 34.0 H459901C NH -095-B(201) Y FORTUNA WASH BRIDGE CONSTRUCT NEW BRIDGE TBD FY 16 11710 RJ1C 160 NA 375.2 H512001C NH -160-A(201)T H JCT SR 564 - TSEGI, PH I CONSTRUCT DUAL PASSING LANES FEB 13 17314 FN1L 160 CN 343.4 NH -160-A(203)A F TONALEA INSTALL INTERSECTION LIGHTING TBD FY 14 14513 PA1K 260 NA 310.0 H801201C NH -260-B(209)A G PIERCE WASH BRIDGE (STR # 1373) SCOUR RETROFIT JAN 13 18214 SH1K 260 NA 321.4 NH -260-B(216)A G COTTONWOOD WASH - SHOW LOW RR 3" AC & AR-ACFC TBD FY 14 45713 EU1M 303L MA 120.0 NH -303-A(215)T E EL MIRAGE RD DESIGN TI DESIGN FY 13 MZ1H 303L MA 5.0 NH -303-A(ASO) E I-10, MC 85 TO I-10 NEW 303 EXTENSION SOUTH TBD FY 14 40317 EP1M 101L MA 11.2 NH -888-A(217)T E AGUA FRIA I-10 TO I-17 CONSTRUCT FMS TBD FY 17 22013 VX1K 999 MA 0.0 NH -999-A(215)T E VARIOUS LOCATIONS ON SR 101L AND I-17 PUMP STATION IMPROVEMENTS JAN 13 NG1L 0000 MA PHX PHX-0(266)A E BLACK MOUNTAIN BLVD, SR 51/SR 101 NEW ROADWAY FY 14 43514 WZ1K 202L MA 0.0 RARF- E 17TH AVE TO 51ST AVE, SEGMENT 3 CONSTRUCT NEW FREEWAY TBD FY 15 40415 UF1H 202L MA 0.0 RARF- E SALT RIVER - BUCKEYE ROAD SEGMENT 8 CONSTRUCT NEW FREEWAY TBD FY 17 45613 UU1L 10 MA 129.5 RARF- E DYSART ROAD TO SR 101L (AUGA FRIA FWY) LANDSCAPE CONSTRUCTION JUN 13 45212 OF1L 303L MA 114.0 RARF- E WADDELL ROAD TO MOUNTAIN VEIW ROAD CONSTRUCT LANDSCAPE JUN 13 45113 OC1L 303L MA 109.0 H860301C RARF- E GLENDALE AVE TO PEORIA AVE CONSTRUCT LANDSCAPE JUN 14 43015 EW1M 303L MA 0.0 RARF- E US 60 GRAND AVE / SR 303L TI, INTERIM LANDSCAPE CONSTRUCTION TBD FY 15 44913 OE1L 303L MA 105.0 H850401C RARF- E THOMAS ROAD TO CAMELBACK ROAD CONSTRUCT LANDSCAPE TBD FY 14 41213 YR1K 202L MA 9.0 RARF- E SR 101 TO GILBERT ROAD DESIGN GENERAL PURPOSE LANES DESIGN FY 14 80899 S9SP 101L MA 73.0 H387501C RARF-101-B E PIMA ROAD EXTENSION, JPA CONSTRUCT ROADWAY IGA FY 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 10 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: HY1L 66 MO 56.4 H809401X SB -AZ09(002) K KINGMAN POWERHOUSE VISITOR CENTER IMPROVEMENTS IGA FY 13 45913 EO1M 101L MA 6.0 STAN- E MARYLAND AVENUE CONSTRUCT DIRECT HOV RAMP (DESIGN BUILD) FEB 13 15515 JC1H 286 PM 20.0 H690701C STP - T SR 286 (SASABE - ROBLES RANCH HWY) REPAIR HEADCUTTING PROBLEMS AT LW WATE TBD FY 15 14115 GP1G 82 SC 40.5 STP - T SR-82 AT MP 40.6 EXTEND CBC & ELIMINATE GUARDRAIL TBD FY 15 15914 GR1G 82 SC 36.5 STP - T SR-82, MP 36.5 - 36.9 EXTEND 2 CBC'S AND ELIMINATE GUARDRAIL TBD FY 14 11116 YF1K 40 SW 235.0 H821401C STP - H PAINTED CLIFFS & METEOR CRATER REST AREAS SYSTEM PRESERVATION - RESTORATION/REHAB TBD FY 16 12416 BU1L 999 SW 0.0 H826301C STP - K HAVILAND & MARBLE CANYON REST AREAS STRUCTURAL REHABILITATION TBD FY 16 14915 ZA1J 191 CH 331.0 STP - S I-10/ US 191 TI AT MP 331 CONSTRUCT IMPROVEMENTS TBD FY 15 11616 GQ1G 82 SC 39.0 STP - T ELGIN TURNOFF EXTEND CMP'S, FLATTEN SLOPE & ELIMINATE G TBD FY 16 15615 YC1K 999 SW 0.0 H821301C STP - T SACATON & CANOA RANCH REST AREAS WATER/WASTEWATER, STRUC & ELECTICAL RE TBD FY 15 18213 DE1M 80 CH 317.0 STP - S TOMBSTONE REMOVE PEDESTRIAN BRIDGE TBD FY 13 10717 FF1M 92 CH 351.0 STP - S MELODY LANE - NACO RD WIDEN TO 3 LANES TBD FY 17 20713 EF1M 266 GH 104.0 STP - S JCT 191 - BONITA CHIP SEAL & GR RENEWAL JUN 13 18414 EE1M 264 AP 446.0 STP - H GANADO SECTION WIDENING TO 3 LANES & TL TBD FY 14 18514 EG1M 288 GI 260 STP - G ROOSEVELT - YOUNG CBC EXTENSION OCT 13 19514 DT1M 188 GI 240.0 STP - G WINDY HILL INSTALL DRAINAGE FACILITY CBC SEP 13 12016 IS1L 191 GH 120.3 STP - S RELATION ST TO JCT US70 INTERSECTION IMPROVEMENT TBD FY 16 16512 DV1M 191 GH 104.0 STP - S SR 266 TO US 70 (REALIGNMENT) SCOPING DESIGN FY 13 13213 RN1K 88 MA 204.0 STP - E APACHE JCT - TORTILLA FLATS MILL 2" & 3" AC & CHIP SEAL JAN 14 13515 CQ1M 60 MA 189.0 STP - E SOSSAMAN - MERIDIAN DRAINAGE IMPROVEMENTS TBD FY 15 16914 AE1K 264 AP 459.0 H786301C STP - H CROSS CANYON - SUMMIT 2" AC & AR-ACFC TBD FY 14 20013 YU1L 180 AP 426.0 STP - G EAGER ALPINE INSTALL DRAINAGE FACILITY JUN 13 16614 HO1L 89 CN 403.0 STP - F JCT SR 89A / PLAZA WAY (FLAGSTAFF) DRAINAGE IMPROVEMENTS TBD FY 14 10617 DI1M 87 CN 324.0 STP - P CLOVER CREEK ROCKFALL MITIGATION TBD FY 17 17713 CZ1M 68 MO 20.0 STP - K MP 19, TURN LANES DESIGN & CONSTRUCT 3 EB TURN LANES DESIGN FY 13 12116 DW1M 191 AP 345.0 STP - H SANDERS - WITCH WELLS FENCING & CATTLE GUARDS TBD FY 16 11416 MW1L 74 MA 30.0 H840301C STP - E I-17 AND LAKE PLEASANT PKWY CONSTRUCT DRAINAGE IMPROVEMENTS TBD FY 16 14715 SF1K 180 AP 386.3 STP - G GENERATING STATION ROAD - JCT US 60 RR 3" & CHIP SEAL TBD FY 15 18013 ZS1H 77 NA 367.0 STP - H FIVE MILE WASH BRIDGE PE PH 1 & 2 (WIDEN ROADWAY TO 4 LANES) DESIGN FY 13 14815 SG1K 180 AP 407.0 STP - G JUAN CARILLO - FH275 RR 3" AC & AR-ACFC TBD FY 15 13914 CC1M 19 SC 9.0 STP - T I-19 FRONTAGE ROAD, NB DRAINAGE REPAIR TBD FY 14 16715 EA1M 260 YV 220.0 STP - P SR 260 AT INDUSTRIAL DRIVE IN CAMP VERDE ROUNDABOUT DEC 14 16315 UZ1J 89A CN 525.0 STP - F JCT US 89 - COLORADO RIVER EXTEND PIPES AND CULVERTS TBD FY 15 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 11 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 14415 SP1K 89 YV 258.3 STP - P JCT US 93 - JCT SR 71 RR 3" & AR-ACFC TBD FY 15 ZP1K 0000 YU YYU SS86101C STP - Y S. FRONTAGE ROAD - AVENUE 9E TO AVENUE13E PAVEMENT PRESERVATION FY 13 16215 DL1M 89A YV 343.0 STP - P SOUTH OF JEROME ROCKFALL MITIGATION TBD FY 15 16314 DM1M 89 YV 349.0 STP - P JCT SR 260 (COTTONWOOD) CONSTRUCT DUAL RIGHT TURN LANES TBD FY 14 16815 SL1K 264 AP 441.0 STP - H BURNSIDE - CROSS CANYON 2" AC & AR-ACFC TBD FY 15 20213 OT1F 188 GI 254.0 STP - G ROOSEVELT - JAKES CORNER INSTALL DRAINAGE FACILITY CBC TBD FY 13 17814 SK1K 191 AP 482.0 H813201C STP - H ROUND ROCK - JCT. US 160 3" AC & AR-ACFC FEB 14 10616 XD1K 260 YV 218.5 STP - P THOUSAND TRAILS TO I-17 CONSTRUCT INTERIM IMPROVEMENTS TBD FY 16 15815 QH1L 999 MA 0.0 STP - E VARIOUS LOCATIONS DRAINAGE TUNNEL IMPROVEMENTS TBD FY 15 13113 FF1G 73 NA 342.3 STP - G WHITERIVER TO COAL MINE CANYON 2" AC + FR FEB 14 10517 DD1M 79 PN 122.5 STP - T MP 122.5 EXTEND PIPES AND CULVERTS TBD FY 16 11216 CV1M 60 PN 232.0 STP - G WEST OF PINTO CREEK BRIDGE ROCKFALL MITIGATION TBD FY 16 10114 DU1M 191 GH 101.0 STP - S MP 100.7 TO SR 266 DESIGN PARALLEL ROADWAY DESIGN FY 14 15015 DX1M 191 AP 418.0 STP - H BURNSIDE - CHINLE FENCING & CATTLE GUARDS TBD FY 15 15315 ED1M 264 AP 441.0 STP - H BURNSIDE - SUMMIT FENCE & CATTLE GUARD TBD FY 15 12916 DC1M 77 NA 384.0 STP - H 5 MILE WASH - JCT 377 CBC EXTENSION TBD FY 16 13913 QE1K 387 PN 0.0 STP - T JCT SR 84 / SR 287 TO SANTA CRUZ RIVER BRIDGE RR 4" TL, 3" PL & FOG COAT JUN 13 12516 LP1K 89A CN 538.0 STP - F COLORADO RIVER TO HOUSE ROCK (PHASE II) EXTEND PIPES AND CULVERTS TBD FY 16 11716 DJ1M 87 NA 346.0 STP - H I-40 TO JCT SR 264 CBC EXTENSIONS TBD FY 16 14113 DK1M 89A YV 330.0 STP - P FAIN ROAD TO SR-169 CORRIDOR LOCATION REPORT FOR RTE EVALU DESIGN FY 13 17914 DZ1M 260 YV 211.2 STP - P THOUSAND TRAILS ROAD NEW TAPERS TO STANDARD TBD FY 14 12316 EH1M 288 GI 289.0 STP - G SOUTH OF YOUNG ROCKFALL MITIGATION TBD FY 16 20313 CX1M 210 PM 1.0 STP - T AVIATION CORRIDOR IN TUCSON SIGN REHABILITATION TBD FY 13 11916 KZ1K 180 CN 216.1 STP - F NAVAJO RD - FLAGSTAFF CITY LIMITS WIDENING, C&G & DRAINAGE IMPROVEMENTS TBD FY 16 WK1L 940 MA 0.0 SR19101C STP -000-6(171)T E UNIVERSITY DR (TEMPE) 741-561J AT-GRADE RAILROAD CROSSING DESIGN AUG 13 17610 SX1J 10 PN 208.8 H769601C STP -010-D(205)A T SR 87 TI TO TOWN OF PICACHO CAPACITY ADDITIONS - ENGINEERING TBD FY 13 10313 GS1H 60 PN 222.0 STP -060-D(208)A G SILVER KING SECTION & SUPERIOR STREETS RECONSTRUCT TO 4 LANE RDWY W/CNT TURN L TBD FY 15 11008 EX1F 60 PN 230.0 STP -060-D(211)A G OAK FLAT - MIAMI CONSTRUCT PASSING/CLIMBING LANE FEB 14 17613 XI1J 60 GI 305.0 H778601C STP -060-E(211)A G FLYING V CANYON TO SQUAW DRESS RIDGE SLOPE STABILIZATION JUN 13 13615 CW1M 60 GI 302.0 STP -060-E(214)T G MP 302 - 311 RR 3" AC + AR-ACFC TBD FY 15 15913 WC1L 74 MA 22.4 STP -074-A(204)T E PICACHO WASH TRAIL TO JCT I-17 RR(5" TL, 3" PL) + AR ACFC SEP 13 15614 UB1J 77 AP 362.1 STP -077-B(208)A H NORTH SNOWFLAKE BOX CULVERT EXTENSION TBD FY 14 11508 AZ1G 86 PM 159.5 H680601C STP -086-A(210)T T VALENCIA RD - KINNEY RD CONSTRUCT ROADWAY WIDENING TO 4 LANES TBD FY 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 12 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 10116 TE1J 89 YV 320.4 H803901C STP -089-B(203)A P DEEP WELL RANCH ROAD TO SOUTH CHINO VALLEY CONSTRUCT ROADWAY WIDENING AUG 13 25113 FS1M 89 YV 327.0 STP -089-B(213)T P SR 89 @ ROAD 1 NORTH IN CHINO VALLEY DESIGN DESIGN FY 13 13313 RR1K 89 CN 476.6 H811601C STP -089-D(203)T F MOENKOPI WASH - HIDDEN SPRINGS 2.5" AC OVERLAY AND 1/2" AR-ACFC NOV 13 10012 KM1K 95 YU 0.0 H800301C STP -095-A(204)A Y INTERNATIONAL BORDER - JUAN SANCHEZ BLVD INFRASTRUCTURE IMPROVEMENTS FEB 13 19613 EJ1L 95 MO 250.0 STP -095-D(207)T K AVIATION WAY - BULLHEAD CITY PARKWAY PE PH 1 & 2 TO CONSTRUCT CONCRETE MEDIAN DESIGN FY 13 17414 DS1M 169 YV 4.8 STP -169-A(203)S P CHERRY ROAD CONSTRUCT TURN LANES / BOX EXTENSION TBD FY 14 YT1L 169 YV 5.1 H853601C STP -169-A(204)T P E OLD CHERRY RD - W CHERRY CREEK RD PAVEMENT PRESERVATION (MICRO-SURFACING MAR 13 15214 DR1M 169 MA 4.0 STP -169-A(205)S P PASSING LANES CONSTRUCT TURN AND PASSING LANES TBD FY 14 13513 RT1K 180 CN 216.2 H811801C STP -180-(202)T F COLUMBUS AVENUE - SNOW BOWL RR 3" & AR-ACFC & TURN LANES NOV 13 17514 MQ1J 180 AP 338.0 H752001C STP -180-B(204)A G BEAVER DAM - RANCH (EB & WB) 3" CIPR & FR AUG 13 IX1L 180 NA 307.3 H831801C STP -180-B(205)T H EAST OF SR 77 NEAR HOLBROOK PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13 17614 ST1K 186 CH 328.2 STP -186-A(200)A S WILLCOX TO KANSAS SETTLEMENT R & R 3" AC & CHIP SEAL APR 14 NF1L 191 GE 184.5 H841201C STP -191-C(215)T S GREY PEAK TO JUAN MILLER ROAD PAVEMENT PRESERVATION (DOUBLE CHIP SEAL APR 13 12010 EB1E 191 AP 446.3 H543801C STP -191-E(205) H CHINLE - SOUTH ROADWAY WIDENING TBD FY 13 15115 DY1M 191 AP 462.5 STP -191-E(212)T H MANY FARMS - APACHE CO. RD 508 FENCING WIDENING JUN 14 17714 QC1L 191 AP 477.9 STP -191-E(213)T H JCT N12 TO JCT US-160 REPLACE FENCE AND CATTLE GUARDS JUN 14 LL1L 999 CH 0.0 H832801C STP -999-A(328)T S SR 186 & B-10, COCHISE COUNTY WIDE PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13 18814 YJ1K 999 SW 0.0 H821701C STP -999-A(351)T Y BURNT WELL AND EHRENBURG REST AREAS WATER,STRUCTURAL,MECH & ELECTRICAL REH NOV 13 10810 IV1A 89A CN 399.0 H413401C STP -A89-B(009)A F SR 89A JW POWELL BLVD CONSTRUCT INTERSECTION IMPROVEMENTS JUN 13 16514 SE1K 89A CN 386.6 STP -A89-B(210)A F PUMPHOUSE WASH - OVERLOOK RR (3"AC, 2.5" AC + AR-ACFC) FULL WIDTH DEC 13 13714 MS1L 19B SC 0.1 STP -B19-A(201)A T INTERNATIONAL BORDER - MARIPOSA/SR189 RR 2" AC DEC 13 OD1K 0000 MO CLC SS87801C STP -CLC-0(201)A F JOHNSON AVENUE PAVEMENT PRESERVATION FY 13 MB1K 0000 PN CLG SS87301C STP -CLG-0(200)A T COOLIDGE AVENUE DESIGN / RECONSTRUCTION FY 14 QM1L 0000 CN FLA SZ01901C STP -FLA-0(213)D F SITGREAVES ST, MILTON TO SANTE FE CONSTRUCTION OF ADA RAMPS FY 13 OB1K 0000 MA MMA SS88101C STP -MMA-0(217)A E MCKELLIPS ROAD - SR101L TO ALMA SCHOOL ROADWAY RECONSTRUCTION FY 15 OA1K 0000 MA MMA SS87901C STP -MMA-0(218)A E GILBERT ROAD BRIDGE OVER THE SALT RIVER CONSTRUCT BRIDGE FY 15 PG1K 0000 MA MMA SS89401C STP -MMA-0(225)A E MCKELLIPS ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 16 PH1K 0000 MA MMA SS89301C STP -MMA-0(226)A E DOBSON ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 15 UK1K 0000 PN PPN STP -PPN-0(205)A T HUNT HIGHWAY - SYSTEM PRESERVATION - ENGINEERING FY 13 KQ1H 0000 MA MMA STP -QCR-0(001)A E RIGGS RD,ELLSWORTH TO MERIDIAN CONSTRUCT NEW ROADWAY FY 13 WU1J 0000 PM TUC SS73001C STP -TUC-0(226)A T PANTANO BOULEVARD PAVEMENT RECONSTRUCTION FY 13 PU1K 0000 PM TUC SS86501C STP -TUC-0(233)A T KOLB ROAD CONNECTION TO SABINO CANYON ROADWAY AND SIDEWALK IMPROVEMENTS FY 14 HS1K 0000 YU 0.0 SL64401C TEA -SOM-0(200)A Y US 96 BETWEEN SOMERTON AND BINGHAM AVENUES SYSTEM ENHANCEMENT-OTHER ENHANCEMENT FY 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 2ND SORT: FEDERAL ID # Page 13 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: PW1H 0000 PM TUC SS63201C TEA -TUC-0(203)B T CAMPBELL AVE - MAIN STREET MAIN STREET REVITALIZATION FY 13 HV1L 0000 MA WBG SL69001C TEA -WBG-0(201)D P 1962 HASSAYAMPA RIVER BRIDGE PEDESTRIAN/BICYCLE IMPROVEMENT FY 13 GA1L 0000 NA WIN SL71101C TEA -WIN-0(203)A H THE STATION AT LA POSADA REHAB OF STATION AND LANDSCAPE FY 14 EP1K 0000 PM TUC SS73601C TUC-0(227)A T TUCSON BOULEVARD MULTI-USE PATH MULTI-USE PATH FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 1 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 18713 MS1K 89 YV 333.1 H791901C 089-B(208)T P DEL RIO RANCH BRIDGE #20046 BRIDGE REPLACEMENT JAN 13 18313 MI1K 89 YV 335.9 H797601C 089-B(204)T P BIG CHINO WASH BRIDGE #979 DECK REPLACEMENT / WIDENING JAN 13 10412 DA1J 89 CN 464.5 H791501C NH -089-D(201)T F SR-64 TO LITTLE COLORADO RIVER CONSTRUCT 4-LANE URBAN, SR64 INTERSECTIO JAN 13 14513 PA1K 260 NA 310.0 H801201C NH -260-B(209)A G PIERCE WASH BRIDGE (STR # 1373) SCOUR RETROFIT JAN 13 22013 VX1K 999 MA 0.0 NH -999-A(215)T E VARIOUS LOCATIONS ON SR 101L AND I-17 PUMP STATION IMPROVEMENTS JAN 13 ZP1K 0000 YU YYU SS86101C STP - Y S. FRONTAGE ROAD - AVENUE 9E TO AVENUE13E PAVEMENT PRESERVATION FY 13 12013 SW1K 10 LA 63.0 H815901C 010-A(217)T Y GAS LINE RD - COUNTY LINE RR (1/2" TL, 4" PL) & AR-ACFC FEB 13 12513 IG1K 40 YV 132.1 H785701C K WEIGH STATION TO ASH FORK (WB) RR (5" TL, 3" PL) + FR FEB 13 OR1K 60 GI 290.0 H808301C 060-E(206)T G MP 290, 296 AND 320 AT HAGEN HILL ROCKFALL CONTAINMENT FEB 13 22413 YC1L 64 CN 0.0 H817202C FA - F RURAL INTELLIGENT TRANSPORTATION SYSTEMS - PH CONSTRUCT FEB 13 HY1L 66 MO 56.4 H809401X SB -AZ09(002) K KINGMAN POWERHOUSE VISITOR CENTER IMPROVEMENTS IGA FY 13 10312 LE1G 93 MO 101.8 H738801C NH -093-B(204)T K ANTELOPE WASH CONSTRUCT 4-LANE DIVIDED HIGHWAY FEB 13 10012 KM1K 95 YU 0.0 H800301C STP -095-A(204)A Y INTERNATIONAL BORDER - JUAN SANCHEZ BLVD INFRASTRUCTURE IMPROVEMENTS FEB 13 MO1K 95 YU 0.6 H801701C Y US95, 'A' ST TO JUAN SANCHEZ BLVD, SAN LUIS ROAD & PEDESTRIAN ENHANCEMENTS FEB 13 45913 EO1M 101L MA 6.0 STAN- E MARYLAND AVENUE CONSTRUCT DIRECT HOV RAMP (DESIGN BUILD) FEB 13 VS1L 101L MA 60.0 H848801C 101-C(201)A E GALVESTON DRAINAGE BASIN G (THUDE PARK) DRAINAGE IMPROVEMENT & PUMP STATION IGA FY 13 14413 RU1K 160 NA 358.1 H811901C F COUNTY LINE - BLACK MESA RR 3" & AR-ACFC FEB 13 11710 RJ1C 160 NA 375.2 H512001C NH -160-A(201)T H JCT SR 564 - TSEGI, PH I CONSTRUCT DUAL PASSING LANES FEB 13 QM1L 0000 CN FLA SZ01901C STP -FLA-0(213)D F SITGREAVES ST, MILTON TO SANTE FE CONSTRUCTION OF ADA RAMPS FY 13 VK1J 0000 GI GGI HPP -GGI-0(204)A G TONTO CREEK BRIDGE DESIGN BRIDGE APPROACHES FY 13 OC1K 0000 MA MES SS87701C CM -MES-0(216)A E LOCAL AGENCY WIDE - FIBER-OPTIC COMMUNICATION FIBER OPTICS FY 13 JN1L 0000 MA MMA SS97201C E UPGRADE RADS REGIONWIDE SYSTEM UPGRADE FY 13 JO1L 0000 MA MMA SS97301C E WEST VALLEY DMS INSTALL ARTERIAL DMS FY 13 ZS1J 0000 MA PHX CM -PHX-0(223)A E SALT RIVER PATHWAY - 24TH ST TO I-10 TEMPE DRAIN PATHWAY IMPROVEMENTS FY 13 UK1K 0000 PN PPN STP -PPN-0(205)A T HUNT HIGHWAY - SYSTEM PRESERVATION - ENGINEERING FY 13 XY1K 0000 MA QCR SS87601C CM -QCR-0(207)A E TOWNWIDE - ITS DEVELOPMENT SYSTEM ENHANCEMENT - TRAFFIC MGMT AND E FY 13 BX1L 0000 MA TMP SS95301C CM -TMP-0(217)A E SALT RIVER MUP: I-10/TEMPE DRAIN TO PRIEST DRIVE PATHWAY IMPROVEMENTS FY 13 PW1H 0000 PM TUC SS63201C TEA -TUC-0(203)B T CAMPBELL AVE - MAIN STREET MAIN STREET REVITALIZATION FY 13 15513 KV1L 10 CH 381.0 H837101C BR - S SAN SIMON RIVER BR (STR #1167,1168 & 230) SCOUR RETROFIT MAR 13 16713 KW1L 40 NA 271.0 H837201C BR - H MANILA WASH BRIDGES STR #851,852 & 2080 SCOUR RETROFIT MAR 13 12813 ZY1J 40 NA 303.1 H785901C IM -040-E(214)T H BIG LITHODENDRON-PETRIFIED FOREST NATIONAL PA PAVEMENT PRESERVATION MAR 13 12913 RX1K 69 YV 271.6 H812201C P BIG BUG 4 TO POLAND JCT RR 3" TL, RR AR-ACFC FULL WIDTH MAR 13 YJ1L 69 YV 292.1 H854001C NH -069-A(211)T P SUNRISE BLVD TO PRESCOTT CANYON DR PAVEMENT PRESERVATION (AR-ACFC) MAR 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 2 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: YT1L 169 YV 5.1 H853601C STP -169-A(204)T P E OLD CHERRY RD - W CHERRY CREEK RD PAVEMENT PRESERVATION (MICRO-SURFACING MAR 13 IX1L 180 NA 307.3 H831801C STP -180-B(205)T H EAST OF SR 77 NEAR HOLBROOK PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13 LL1L 999 CH 0.0 H832801C STP -999-A(328)T S SR 186 & B-10, COCHISE COUNTY WIDE PAVEMENT PRESERVATION (DOUBLE CHIP SEAL MAR 13 OD1K 0000 MO CLC SS87801C STP -CLC-0(201)A F JOHNSON AVENUE PAVEMENT PRESERVATION FY 13 40913 CM1J 10 MA 122.0 H770901C NH - E PERRYVILLE ROAD TI CONSTRUCT TI APR 13 12213 SQ1K 10 CH 318.8 H815101C IM -010-F(216)T S DRAGOON RD - WEST WILLCOX TI (WB) PAVEMENT PRESERVATION APR 13 12413 RW1K 17 YV 245.0 H812101C P BLACK CANYON HILL (NB) RR (5" TL, 3" PL) & AR-ACFC APR 13 12613 NQ1L 40 CN 146.0 H840201C IM - F EAST ASHFORK TI TO WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC APR 13 NF1L 191 GE 184.5 H841201C STP -191-C(215)T S GREY PEAK TO JUAN MILLER ROAD PAVEMENT PRESERVATION (DOUBLE CHIP SEAL APR 13 HZ1L 0000 MA SCT SS96701C E PAVEMENT PRESERVATION PHASE 3 PAVEMENT PRESERVATION FY 13 UH1K 0000 MA SCT SS91301C CM -SCT-0(211)A E DYNAMITE BLVD - PIMA TO ALMA SCHOOL ROAD INSTALL CURB AND GUTTER FY 13 HV1L 0000 MA WBG SL69001C TEA -WBG-0(201)D P 1962 HASSAYAMPA RIVER BRIDGE PEDESTRIAN/BICYCLE IMPROVEMENT FY 13 17610 SX1J 10 PN 208.8 H769601C STP -010-D(205)A T SR 87 TI TO TOWN OF PICACHO CAPACITY ADDITIONS - ENGINEERING TBD FY 13 24013 BH1M 15 MO 15.0 H857401C 015-A(208)S F VIRGIN RIVER BRIDGE #6 (STR #1619) CMAR BRIDGE REHABILITATION CONSTRUCTION TBD FY 13 45313 TR1H 17 MA 215.0 H844501C CM -017-A(230)A E SR 101L (AGUA FRIA) TO ANTHEM WAY CONSTRUCT FMS MAY 13 QP1J 40 MO 66.5 IM -040-B(208)A K I-40, BLAKE RANCH RD TI IMPROVEMENTS TBD FY 13 16313 PY1E 40 YV 102.0 IM - K CROSS MT - JOLLY RD UPGRADE EXISTING ROCKFALL PROTECTION TBD FY 13 12613 RP1K 40 YV 146.2 F EAST ASHFORK TI - COUNTY LINE RR 3" & 2" AC & AR-ACFC TBD FY 13 12713 RQ1K 40 CN 158.6 F PINE SPRINGS - WEST WILLIAMS TI RR 3" & 2" AC & AR-ACFC TBD FY 13 16913 CL1M 40 NA 290.0 IM - H HOLBROOK - SUN VALLEY FENCING AND CATTLE GUARDS TBD FY 13 YQ1L 70 GH 347.0 H853801C S HAEKEL RD TO US 191 SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13 18113 NY1K 79 PN 101.8 H807501C BR -079-A(205)T T CORONADO WASH BRIDGE STRUCTURE #222 BRIDGE REPLACEMENT MAY 13 18213 DE1M 80 CH 317.0 STP - S TOMBSTONE REMOVE PEDESTRIAN BRIDGE TBD FY 13 18413 DF1M 83 SC 12.0 H850101C T MP 12 - MP 14 MILL AND PAVE TBD FY 13 14313 SB1K 87 GI 236.2 H812301C P JCT 188 - RYE RR 3" TL & AR-ACFC FULL WIDTH MAY 13 13409 TQ1H 87 GI 263.0 H718301C P TONTO NATURAL BRIDGE STATE PARK CONSTRUCT NEW ROAD TBD FY 13 JN1M 89 YV 345.7 H863601C K HELL CANYON BRIDGE DECK REHABILITATION TBD FY 13 13413 RS1K 89A CN 609.3 F FREDONIA - STATE LINE RR 3" & AR-ACFC TBD FY 13 XT1H 180 AP 402.0 G JCT SR 260 / US 180 & RODEO GROUNDS INTERSECTIO REALIGN INTERSECTION TBD FY 13 20213 OT1F 188 GI 254.0 STP - G ROOSEVELT - JAKES CORNER INSTALL DRAINAGE FACILITY CBC TBD FY 13 13613 SC1K 191 CH 38.2 HSIP- S JCT SR 181 - PEARCE ROAD 3" AC & AR-ACFC MAY 13 12010 EB1E 191 AP 446.3 H543801C STP -191-E(205) H CHINLE - SOUTH ROADWAY WIDENING TBD FY 13 YM1L 202L MA 9.0 H854301C E L101 TO MCDOWELL ROAD SYSTEM PRESERVATION (RESTORATION/REHAB/ TBD FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 3 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 43208 ST1H 202L MA 44.0 CM - E LINDSAY ROAD TO GILBERT ROAD DESIGN & CONST MULTI-USE PATH TBD FY 13 20313 CX1M 210 PM 1.0 STP - T AVIATION CORRIDOR IN TUCSON SIGN REHABILITATION TBD FY 13 20513 EB1M 260 GI 262.0 NH - P VARIOUS BRIDGE APPROACHES REPAIR BRIDGE APPROACHES TBD FY 13 14013 RO1K 587 PN 218.8 H811301C E SR 87 - JCT I-10 RR 3" & AR-ACFC MAY 13 23913 ZC1L 999 SW 0.0 HSIP-999-A(377)S F I-17 AND I-40, INLAID PAVEMENT MARKERS, SEGMENT I INLAID PAVEMENT MARKINGS TBD FY 13 XX1K 0000 MA CHN SS93201C E CONSOLIDATED CANAL MULTI-USE PATH PATHWAY/TRAIN IMPROVEMENTS FY 13 ZQ1F 0000 MA GDY SS54401C STP-GDY-0(008)A E YUMA RD @ BULLARD WASH CONST BOX CULVERTS FY 13 PI1K 0000 MA MES SS89101C CM -MES-0(217)A E ITS TRAFFIC SIGNAL CONVERSIONS - PHASE 5 FIBER-OPTIC COMMUNICATIONS NET FY 13 BB1L 0000 MA MMA SS83001C CM -MMA-0(214)A E OLIVE AVE: LITCHFIELD ROAD TO LOOP 101 INSTALL FIBER OPTIC CONDUIT FY 13 KQ1H 0000 MA MMA STP -QCR-0(001)A E RIGGS RD,ELLSWORTH TO MERIDIAN CONSTRUCT NEW ROADWAY FY 13 CC1L 0000 MA MMA SS95701C CM -MMA-0(231)A E 88TH AVE: DEER VALLEY TO WILLIAMS RD PAVE UNPAVED ROAD FY 13 PL1K 0000 MA MMA SS89901C CM -MMA-0(228)A E 87TH AVENUE PAVING DIRT ROAD FY 13 JQ1L 0000 MA SUR SS95801C E DOVE VALLEY ROAD,18TH AVE-203RD AVE ROADWAY IMPROVEMENTS FY 13 WU1J 0000 PM TUC SS73001C STP -TUC-0(226)A T PANTANO BOULEVARD PAVEMENT RECONSTRUCTION FY 13 BA1L 0000 YU YYU SB43701C BR -YYU-0(201)T Y COUNTY 19TH ST BRIDGE OVER MAIN DRAIN (AVE F 1/2 BRIDGE REPLACEMENT FY 13 15413 HJ1J 8 YU 7.2 HSIP- Y I-8 AND ARABY ROAD PE PH 1 AND 2 DESIGN FY 13 14913 YG1L 8 YU 125.0 Y GILA BEND TO I-10 SIGN REHABILITATION DESIGN FY 13 HC1J 10 LA 1.0 Y EHRENBERG EXIT 1 ROUNDABOUT JUN 13 45613 UU1L 10 MA 129.5 RARF- E DYSART ROAD TO SR 101L (AUGA FRIA FWY) LANDSCAPE CONSTRUCTION JUN 13 HB1M 10 PN 209.9 H861401C IM -010-D(217)T T LA PALMA RD TO PICACHO HWY DESIGN PAVEMENTPRESERVATION PROJECT DESIGN FY 13 10117 BY1M 15 MO 0.0 F SCENIC TO STATE LINE PE PH 1 & 2 DESIGN FY 13 15613 RH1L 17 MA 238.6 BR - P MOORES GULCH BRIDGE SB #339 DESIGN BRIDGE REPLACEMENT DESIGN FY 13 HT1M 17 YV 287.0 017-B( )T P VERDE RIVER BRIDGE NB #1731 DESIGN BRIDGE REHABILITATION DESIGN FY 13 13814 MT1L 19 SC 0.3 IM -019-A(216)A T INTERNATIONAL BORDER - JCT B-19 RR AR-ACFC JUN 13 HV1M 40 MO 83.0 040-B(220)T K WILLOW CREEK BRIDGE NO 2 EB (#1593) DESIGN BRIDGE REHABILITATION DESIGN FY 13 16413 IW1L 40 CN 180.8 IM -040-C(208)A F EAST OF PARKS ROCKFALL MITIGATION JUN 13 16613 CK1M 40 NA 226.0 IM - H EAST WINSLOW TI PE PH 1 & 2 DESIGN FY 13 GT1M 40 NA 289.0 040-D(227)T H E HOLBROOK TI OP EB#1369 & WB #1370 DESIGN BRIDGE REHABILITATION DESIGN FY 13 17413 CP1M 40 AP 322.0 NH - H CHAMBERS PORT OF ENTRY PE PH 1 & 2 DESIGN FY 13 IN1M 60 MA 109.9 060-A(207)S P US 60 @ APACHE STREET IN WICKENBURG DESIGN DESIGN FY 13 17613 XI1J 60 GI 305.0 H778601C STP -060-E(211)A G FLYING V CANYON TO SQUAW DRESS RIDGE SLOPE STABILIZATION JUN 13 HU1M 66 CN 91.0 066-A( )T K WASH BR #141 & TRUXTON WASH BR #142 DESIGN BRIDGE REHABILITATION DESIGN FY 13 17713 CZ1M 68 MO 20.0 STP - K MP 19, TURN LANES DESIGN & CONSTRUCT 3 EB TURN LANES DESIGN FY 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 4 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 15813 BX1M 69 YV 281.1 HX24201C HSIP-069-A(210)T P MP 281.1 - MP 289.7 MODIFY SIGNALS JUN 13 11413 AY1G 77 PM 82.0 H669401C 077-A(204)T T TANGERINE RD TO PINAL COUNTY LINE WIDENING TO 6 LANES - CONSTRUCTION JUN 13 18013 ZS1H 77 NA 367.0 STP - H FIVE MILE WASH BRIDGE PE PH 1 & 2 (WIDEN ROADWAY TO 4 LANES) DESIGN FY 13 GX1M 86 PM 120.6 086-A-NFA T FRESNAL TO MP 123.9 DESIGN DESIGN FY 13 FO1M 87 MA 177.8 087-B(220)T E SR87 @ MCDOWELL RD DESIGN SIGNAL IMPROVEMENT DESIGN FY 13 GG1M 87 GI 252.0 087-B(218)A P SR 87 / SR 260 SAFETY IMPROVEMENT ACCESS CONTROL, SIGNING UPGRADES, ADA, M DESIGN FY 13 16513 DH1M 87 CN 268.1 HSIP- P MP 268.1 - MP 278 PE PH 1 & 2 DESIGN FY 13 25113 FS1M 89 YV 327.0 STP -089-B(213)T P SR 89 @ ROAD 1 NORTH IN CHINO VALLEY DESIGN DESIGN FY 13 JE1L 89 YV 328.0 H833001C P PERKINSVILLE RD ROUNDABOUT SYSTEM ENHANCEMENT - ENGINEERING DESIGN FY 13 14213 DN1M 89 CN 420.0 NH - F FLAGSTAFF CITY LIMITS - LENOX PARK FEASIBILITY REPORT FOR ACCESS MGT PLANNI DESIGN FY 13 14113 DK1M 89A YV 330.0 STP - P FAIN ROAD TO SR-169 CORRIDOR LOCATION REPORT FOR RTE EVALU DESIGN FY 13 15208 NSSP 89A YV 365.0 F RED ROCK STATE PARK DESIGN DESIGN FY 13 10810 IV1A 89A CN 399.0 H413401C STP -A89-B(009)A F SR 89A JW POWELL BLVD CONSTRUCT INTERSECTION IMPROVEMENTS JUN 13 19213 LC1J 92 CH 324.3 H716701C HSIP-092-A(200)T S BUFFALO SOLDIER TRAIL TO KACHINA TRAIL RAISED MEDIAN JUN 13 19313 DP1M 93 MO 125.0 NH -093-B(211)T K MEDLIN CROSSOVER DESIGN AND CONSTRUCT NEW CROSSOVER DESIGN FY 13 FK1M 93 YV 185.3 093-B(210)T P SOUTH OF SR71 - NORTH OF SR89 DESIGN ROADWAY WIDENING DESIGN FY 13 19413 WY1L 95 LA 142.0 NH - Y SR 95 AT MOHAVE ROAD PE PH 1 & 2 DESIGN FY 13 HH1M 95 MO 239.0 095-D(208)T K SR 95 @ VALENCIA ROAD DESIGN DESIGN FY 13 SL1L 95 MO 239.5 095-D(204)T K STATE ROUTE 95 @ STERLING RD DESIGN INTERSECTION IMPROVEMENT DESIGN FY 13 19613 EJ1L 95 MO 250.0 STP -095-D(207)T K AVIATION WAY - BULLHEAD CITY PARKWAY PE PH 1 & 2 TO CONSTRUCT CONCRETE MEDIAN DESIGN FY 13 40313 DD1J 101L MA 23.5 E I-17 TO TATUM BLVD CONSTRUCT HOV LANE DESIGN FY 13 VX1L 101L MA 46.0 E SR101L, CHAPARRAL ROAD TO SR202L GP LANES DESIGN FY 13 GQ1M 180 AP 403.5 180-C(201)A G SEVERAL LOCATIONS ON US180 SYSTEM PRESERVATION - ENGINEERING DESIGN FY 13 20013 YU1L 180 AP 426.0 STP - G EAGER ALPINE INSTALL DRAINAGE FACILITY JUN 13 16512 DV1M 191 GH 104.0 STP - S SR 266 TO US 70 (REALIGNMENT) SCOPING DESIGN FY 13 GA1M 191 GE 226 H843901C G US-191, GLOBE DISTRICT, WALLOW FIRE, SIGN REPAIR SYSTEM PRESERVATION (RESTORATION/REHAB/ DESIGN FY 13 GP1M 191 AP 247.8 191-C(216)A G RIGHT OF WAY FENCE IN BOTH DIRECTIONS RIGHT OF WAY FENCING DESIGN FY 13 YL1L 202L MA 9.0 H854201C E L101 TO MESA DRIVE SYSTEM PRESERVATION (RESTORATION/REHAB/ JUN 13 BK1M 260 YV 218.9 P SR 260; INDUSTRIAL DR - HOMESTEAD PKWY DESIGN DESIGN FY 13 20613 MQ1L 260 NA 282.5 HSIP- P RIM RD TO GIBSON RD, SEGMENTS 1, 2 & 3 SHOULDER WIDENING PROGRAM, PE PH 1 & 2 DESIGN FY 13 GO1M 260 AP 385.5 260-C(205)A G RIGHT OF WAY FENCING TWO LOCATIONS EAST BOUN RIGHT OF WAY FENCING DESIGN FY 13 20713 EF1M 266 GH 104.0 STP - S JCT 191 - BONITA CHIP SEAL & GR RENEWAL JUN 13 45112 WB1L 303L MA 112.0 E PEORIA AVE - WADDELL RD LANDSCAPE CONSTRUCTION JUN 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 5 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 45212 OF1L 303L MA 114.0 RARF- E WADDELL ROAD TO MOUNTAIN VEIW ROAD CONSTRUCT LANDSCAPE JUN 13 45713 EU1M 303L MA 120.0 NH -303-A(215)T E EL MIRAGE RD DESIGN TI DESIGN FY 13 CY1M 347 PN 172.0 347-A(209)T T ALTERRA TO CASA BLANCA RD, CITY OF MARICOPA DESIGN DESIGN FY 13 13913 QE1K 387 PN 0.0 STP - T JCT SR 84 / SR 287 TO SANTA CRUZ RIVER BRIDGE RR 4" TL, 3" PL & FOG COAT JUN 13 WL1L 940 MA 0.0 SR19201C 000-6(172)A E 5TH ST (TEMPE) 741-560-C AT-GRADE RAILROAD CROSSING DESIGN JUN 13 21513 XV1K 999 SW 0.0 H820601C HSIP- E STATEWIDE TREE THINNING TREE REMOVAL FROM CLEAR ZONE, PE PH 1 & 2 DESIGN FY 13 PK1K 0000 MA GDY SS89601C CM -GDY-0(203)A E TRAFFIC SIGNAL SYSTEM ITS BACKBONE & COMMUNICATION FY 13 JP1L 0000 MA MMA SS97401C E ATIS ENHANCEMENTS REGIONWIDE ARTERIAL ATIS FY 13 CX1G 0000 PM MRN SB41301C BR-MRN-0(014)A T INA BRIDGE OVER SANTA CRUZ BRIDGE REPLACEMENT FY 13 MD1K 0000 NA PLS SS86401C HPP -PLS-0(201)A G BILLY CREEK BRIDGE @ PORTER MOUNTAIN ROAD CAPACITY ADDITIONS - MAJOR WIDENING FY 13 JM1L 0000 PM PPM SS97501C T VALENCIA ROAD: WADE RD TO MARK RD WIDEN ROADWAY FY 13 ZN1E 0000 PN PPN SB41001C BR -PPN-0-(169) G KELVIN BRIDGE - #8441 BRIDGE REPLACEMENT FY 13 HP1L 0000 MA TMP SS96401C E VARIOUS LOCATIONS:WIRELESS COMMUNICATIONS & PROCUREMENT AND INSTALLATION FY 13 UU1K 0000 PM TUC T SPEEDWAY BLVD UNDERPASS @ UPRR ROADWAY RECONSTRUCTION FY 13 EP1K 0000 PM TUC SS73601C TUC-0(227)A T TUCSON BOULEVARD MULTI-USE PATH MULTI-USE PATH FY 13 43914 XE1K 303L MA 118.0 H814501C E US 60 GRAND AVE / SR 303L TI, INTERIM CONSTRUCT INTERIM TI DEC 12 13214 RC1L 10 CH 333.0 IM -010-F(218)A S US 191 TO EAST WILLCOX TI RR (5" TL, 3" PL) & AR-ACFC JAN 14 13514 CF1L 17 MA 231.0 H826801C E NEW RIVER BRIDGES, STR # 1290 &1291 SCOUR RETROFIT JAN 14 13213 RN1K 88 MA 204.0 STP - E APACHE JCT - TORTILLA FLATS MILL 2" & 3" AC & CHIP SEAL JAN 14 17014 HL1L 92 CH 322.1 H826501C HSIP- S SR 92 @ FOOTHILLS DR INTERSECTION IMPROVEMENTS JAN 14 XD1L 0000 YU YYU SB44501C BR -YYU-0(205)A Y BRIDGE REHABILITATION OLD HWY 80 & AVE 30 1/2 E BRIDGE REHABILITATION FY 14 45309 FN1H 10 MA 96.2 H708301X Y 395TH AVE (BELMONT RD) CONSTRUCT TI IGA FY 14 44909 FM1H 10 MA 105.0 H683801X I -010-A-901 Y I-10/DESERT CREEK TI (PRIVATE FUNDS) CONSTRUCT TI IGA FY 14 12113 IP1L 10 MA 112.8 IM -010-A(216)A E SR 85 - VERRADO (EB) RR(4"TL, 3" PL) & AR-ACFC FEB 14 11008 EX1F 60 PN 230.0 STP -060-D(211)A G OAK FLAT - MIAMI CONSTRUCT PASSING/CLIMBING LANE FEB 14 QJ1L 60 NA 341.0 HX23901C G US 60 & 9TH PLACE, SHOW LOW TRAFFIC SIGNAL FEB 14 13113 FF1G 73 NA 342.3 STP - G WHITERIVER TO COAL MINE CANYON 2" AC + FR FEB 14 80899 S9SP 101L MA 73.0 H387501C RARF-101-B E PIMA ROAD EXTENSION, JPA CONSTRUCT ROADWAY IGA FY 14 17814 SK1K 191 AP 482.0 H813201C STP - H ROUND ROCK - JCT. US 160 3" AC & AR-ACFC FEB 14 PU1K 0000 PM TUC SS86501C STP -TUC-0(233)A T KOLB ROAD CONNECTION TO SABINO CANYON ROADWAY AND SIDEWALK IMPROVEMENTS FY 14 11914 CG1L 8 PN 163.0 H827001C T SANTA ROSA WASH BRIDGES, STR # 1092 & 1093 SCOUR RETROFIT MAR 14 16914 VY1L 90 CH 321.0 H849701C HSIP-090-A(205)A S SR 92 - GIULIO CESARE AVENUE LIGHTING MAR 14 43414 WY1K 101L MA 41.0 H848401C E SHEA BLVD TO CHAPARRAL ROAD CONSTRUCT GPL MAR 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 6 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 14414 EV1L 40 CN 218.7 H789001C IM - F CANYON PADRE BRIDGE, STR #1670 DECK REPLACEMENT APR 14 19414 HS1L 89 YV 330.0 H827801C P ROAD 4 NORTH CONSTRUCT ROUNDABOUT APR 14 17214 XL1L 95 LA 149.2 HSIP-095-C(216)A Y CIENEGA SPRINGS RD SB LEFT TURN LANE APR 14 17614 ST1K 186 CH 328.2 STP -186-A(200)A S WILLCOX TO KANSAS SETTLEMENT R & R 3" AC & CHIP SEAL APR 14 KJ1K 8 MA 117.0 H800001C Y I-8 TO GILLESPIE CANAL REMOVE 3", REPLACE 2.5" & ACFC TBD FY 14 12314 YD1L 10 MA 144.9 IM -010-C(209)T E 3RD AVENUE TO 3RD STREET, DECK PARK TUNNEL DRAINAGE IMPROVEMENTS TBD FY 14 12014 BR1M 10 MA 145.0 IM - E 3RD AVENUE TO 3RD STREET PUMP STATION IMPROVEMENTS TBD FY 14 12414 FY1L 10 MA 162.0 IM -010-C(204)T E WILD HORSE PASS TO SR 347 (QUEEN CREEK ROAD) ROADWAY WIDENING TBD FY 14 12514 BT1M 10 MA 164.0 IM - E WILD HORSE PASS - RIGGS RR(5" TL - 3" PL) + AR-ACFC TBD FY 14 13914 CC1M 19 SC 9.0 STP - T I-19 FRONTAGE ROAD, NB DRAINAGE REPAIR TBD FY 14 14114 SM1K 40 MO 57.0 IM -040-B(213)A K RATTLESNAKE WASH - JCT US 93 RR(5" TL, 3" PL) & AR-ACFC TBD FY 14 14714 QO1L 40 NA 303.0 IM - H ADAMANA TI DRAINAGE IMROVEMENTS TBD FY 14 NL1L 60 MA 143.0 E US60/THUNDEBIRD ROAD INTERSECTION RECONSTRUCT TI TBD FY 14 UV1L 60 MA 144.0 E US 60 / BELL ROAD TI DCR AND ENVIRONMENTAL ASSESSMENT TBD FY 14 41814 WX1K 60 MA 148.9 E SR 101L, AGUA FRIA TO VAN BUREN STREET, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 14 40613 NM1L 60 MA 194.0 NH -060-C(207)T E MERIDIAN ROAD. HALF TI CONSTRUCT TI TBD FY 14 14914 CU1M 60 GI 229.4 HSIP- G MP 229.4 - MP 232.91 SHOULDER WIDENING TBD FY 14 10311 CY1J 77 PN 100.0 H739101C T ORACLE STATE PARK CONSTRUCT PARKING TBD FY 14 15614 UB1J 77 AP 362.1 STP -077-B(208)A H NORTH SNOWFLAKE BOX CULVERT EXTENSION TBD FY 14 15914 GR1G 82 SC 36.5 STP - T SR-82, MP 36.5 - 36.9 EXTEND 2 CBC'S AND ELIMINATE GUARDRAIL TBD FY 14 NK1L 85 PM 42.0 T WELCOME ST. TO MP 42.5 SYSTEM PRESERVATION - ENGINEERING TBD FY 14 44811 ZN1J 85 MA 153.2 H800601C NH - E WARNER STREET BRIDGE CONSTRUCT NEW BRIDGE TBD FY 14 11508 AZ1G 86 PM 159.5 H680601C STP -086-A(210)T T VALENCIA RD - KINNEY RD CONSTRUCT ROADWAY WIDENING TO 4 LANES TBD FY 14 13209 A6SP 87 NA 346.0 H717901C H HOMOLOVI RUINS STATE PARK CONSTRUCT ROAD TBD FY 14 XA1L 89 YV 345.0 089-B(211)T K HELL CANYON BRIDGE #483 REPLACEMENT & WIENING TBD FY 14 16314 DM1M 89 YV 349.0 STP - P JCT SR 260 (COTTONWOOD) CONSTRUCT DUAL RIGHT TURN LANES TBD FY 14 16414 IS1J 89 CN 385.1 H741801C A89-B(204)A F OAK CREEK CANYON CREEK BANK PROTECTION TBD FY 14 16614 HO1L 89 CN 403.0 STP - F JCT SR 89A / PLAZA WAY (FLAGSTAFF) DRAINAGE IMPROVEMENTS TBD FY 14 16714 FD1L 89 CN 523.9 NH - F BITTER SPRINGS INSTALL INTERSECTION LIGHTING TBD FY 14 16814 HG1L 89 CN 551.0 NH - F PAGE MAINTENANCE YARD WIDENING FOR TURN LANES TBD FY 14 10910 DJ1G 90 CH 323.5 H655501C S CENTRAL AVE TO MOSON RD, E OF SIERRA VISTA WIDEN TO 5 LANES TBD FY 14 KK1L 93 MO 139.0 HPP -093-B(209) K US 93, SB BURRO CREEK BRIDGE SYSTEM PRESERVATION - ENGINEERING TBD FY 14 OP1L 101L MA 23.0 E SR 101L PIMA (I-17-PRINCESS DR) GP LANES DCR/ED CAPACITY ADDITIONS - ENGINEERING TBD FY 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 7 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 17314 FN1L 160 CN 343.4 NH -160-A(203)A F TONALEA INSTALL INTERSECTION LIGHTING TBD FY 14 15214 DR1M 169 MA 4.0 STP -169-A(205)S P PASSING LANES CONSTRUCT TURN AND PASSING LANES TBD FY 14 17414 DS1M 169 YV 4.8 STP -169-A(203)S P CHERRY ROAD CONSTRUCT TURN LANES / BOX EXTENSION TBD FY 14 14112 AI1K 191 CH 61.5 H788301C 191-A(203)A S COCHISE POWER PLANT - JCT I-10 RR 2" AC + 3" AC + FR TBD FY 14 41608 TY1H 202L MA 0.0 E I-10 EAST/SANTAN TI TO 51ST AVE DESIGN ROADWAY TBD FY 14 44814 TX1H 202L MA 47.8 CM -888-A(218)T E DOBSON ROAD TO I-10, MARICOPA CONSTRUCT FMS TBD FY 14 17914 DZ1M 260 YV 211.2 STP - P THOUSAND TRAILS ROAD NEW TAPERS TO STANDARD TBD FY 14 18214 SH1K 260 NA 321.4 NH -260-B(216)A G COTTONWOOD WASH - SHOW LOW RR 3" AC & AR-ACFC TBD FY 14 18414 EE1M 264 AP 446.0 STP - H GANADO SECTION WIDENING TO 3 LANES & TL TBD FY 14 16914 AE1K 264 AP 459.0 H786301C STP - H CROSS CANYON - SUMMIT 2" AC & AR-ACFC TBD FY 14 45213 NU1L 303L MA 0.0 E I-10/303L TI, PHASE I (I-10 REALIGNMENT) CONSTRUCT LANDSCAPE TBD FY 14 IZ1K 303L MA 3.8 E SR 303L, RIGGS RD - SR 801 SYSTEM ENHANCEMENT-ENGINEERING TBD FY 14 MZ1H 303L MA 5.0 NH -303-A(ASO) E I-10, MC 85 TO I-10 NEW 303 EXTENSION SOUTH TBD FY 14 44913 OE1L 303L MA 105.0 H850401C RARF- E THOMAS ROAD TO CAMELBACK ROAD CONSTRUCT LANDSCAPE TBD FY 14 JG1H 801 MA 0.0 E SR 303L TO SR 202L STUDY TBD FY 14 YH1H 801 MA 0.0 E SR 801, SR 85 TO SR 303L NEW ROADWAY CONSTRUCTION TBD FY 14 12914 EI1M 999 SW 0.0 HSIP- X STATEWIDE GUARDRAIL DELINEATORS TBD FY 14 HS1K 0000 YU 0.0 SL64401C TEA -SOM-0(200)A Y US 96 BETWEEN SOMERTON AND BINGHAM AVENUES SYSTEM ENHANCEMENT-OTHER ENHANCEMENT FY 14 22910 YS1K 0000 CH DGS SS87401C DGS-0(200)A S CHINO ROAD NEW FACILITIES - CONSTRUCTION OF NEW ROA FY 14 NG1L 0000 MA PHX PHX-0(266)A E BLACK MOUNTAIN BLVD, SR 51/SR 101 NEW ROADWAY FY 14 XZ1K 0000 YU SOM Y SOMERTON CANAL MUP:US95 TO COUNTY 17TH STRE SYSTEM ENHANCEMENT - ENGINEERING FY 14 11614 BM1M 8 YU 1.0 IM - Y WB OFF RAMP & GISS PARKWAY INTERSECTION INTERSECTION IMPROVEMENTS JUN 14 11714 BN1M 8 YU 2.0 IM - Y 16TH STREET LANDSCAPING JUN 14 11414 CU1J 17 YV 232.0 P ROCK SPRINGS TO CORDES JUNCTION PE PH2 (WIDEN ROADWAY) DESIGN FY 14 14214 CJ1M 40 CN 185.0 IM - F TRANSWESTERN - LEUPP JCT PE PH 1 & 2 DESIGN FY 14 11514 QN1C 40 AP 357.5 NH - H WINDOW ROCK TI PE PH 1 DESIGN FY 14 14310 QQ1K 40 AP 358.5 H LUPTON TI DCR AND ENVIRONMENTAL STUDIES DESIGN FY 14 15114 GN1J 70 GH 295.0 S BYLAS TWLTL & ROADWAY WIDENING JUN 14 19214 HM1L 77 PN 105.4 H826701C HSIP- T POWER LINE - SAN MANUEL ROAD DESIGN SHOULDER WIDENING DESIGN FY 14 16214 JD1L 88 PN 196.0 H830801C HSIP- E SUPERSTITION BLVD CONSTRUCT ROUNDABOUT JUN 14 19314 NC1H 88 MA 203.4 H700501C HSIP- E SR88, APACHE TRAIL GOLDFIELD TO CANYON LAKE SPOT SAFETY IMPROVEMENTS JUN 14 17114 IP1K 93 MO 17.4 HSIP- K MP 17.4 - MP 58.4 PE PH 1 & 2 DESIGN FY 14 10114 MG1E 191 GH 100.7 S SR 266 TO ARTESIA DESIGN PARALLEL ROADWAY DESIGN FY 14 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 8 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 10114 DU1M 191 GH 101.0 STP - S MP 100.7 TO SR 266 DESIGN PARALLEL ROADWAY DESIGN FY 14 15115 DY1M 191 AP 462.5 STP -191-E(212)T H MANY FARMS - APACHE CO. RD 508 FENCING WIDENING JUN 14 17714 QC1L 191 AP 477.9 STP -191-E(213)T H JCT N12 TO JCT US-160 REPLACE FENCE AND CATTLE GUARDS JUN 14 45314 EQ1M 202L MA 0.0 NH - E 24TH ST - 17TH AVE, SEGMENT 2 DESIGN NEW FREEWAY DESIGN FY 14 45414 ET1M 202L MA 0.0 IM - E I-10 PAPAGO/ SR202L SYSTEM INTERCHANGE SEGMEN DESIGN NEW SYSTEM TI DESIGN FY 14 41213 YR1K 202L MA 9.0 RARF- E SR 101 TO GILBERT ROAD DESIGN GENERAL PURPOSE LANES DESIGN FY 14 18314 HR1L 264 AP 441.1 H824601C HSIP- H US 191 TO SAWMILL ROAD SEGMENT 1 SHOULDER WIDENING PROGRAM PE PH 1 & PH 2 DESIGN FY 14 XX1G 264 AP 446.0 264-A(212)T H GANADO WASH BRIDGE #1046 DESIGN BRIDGE REPLACEMENT DESIGN FY 14 43814 OB1L 303L MA 107.0 E CAMELBACK ROAD TO GLENDALE AVENUE CONSTRUCT LANDSCAPE JUN 14 45113 OC1L 303L MA 109.0 H860301C RARF- E GLENDALE AVE TO PEORIA AVE CONSTRUCT LANDSCAPE JUN 14 12214 VX1J 10 MA 105.0 H775001C IM - E SR 85 TO DYSART (VERRADO WAY TO 85) SIGN REHABILITATION JUL 13 14514 EE1K 40 NA 254.6 IM -040-D(213)A H RUBY WASH BRIDGE - E WINSLOW TI OP BRIDGE REHABILITATION JUL 13 14614 SJ1K 40 NA 290.2 H813101C IM -040-D(219)A H HOLBROOK - SUN VALLEY RR (5"TL, 3"PL) & AR-ACFC JUL 13 15514 NH1L 77 GI 147.6 H832201C BR -077-A(207)A G DRIPPING SPRING BRIDGE #398 BRIDGE REPLACEMENT JUL 13 16114 VM1K 87 CN 323.9 BR -087-C(203)A H LIMESTONE WASH BRIDGE # BRIDGE REPLACEMENT JUL 13 WJ1L 0000 MA 0.0 SR23201C E DOBSON ROAD, AAR/DOT NO. 741-649-G SYSTEM ENHANCEMENT-SAFETY IMPROVEMENT FY 14 ZJ1K 0000 MA SUR SS85401C CM -SUR-0(210)A E BELL RD-US 60 TO 114TH AVE CONSTRUCT MULTI-USE PATH FY 14 12714 AZ1M 10 PM 268.0 IM -010-D(215)T T I-19 TO CRAYCROFT ROAD IN TUCSON SIGN REHABILITATION AUG 13 17913 LX1G 75 GE 384.0 075-A(200)T S LITTLE SANDS WASH BANK PROTECTION AUG 13 15414 JG1K 77 PN 123.5 H796901C T ARAVAIPA CREEK BRIDGE, STR #399 BRIDGE REPLACEMENT AUG 13 10116 TE1J 89 YV 320.4 H803901C STP -089-B(203)A P DEEP WELL RANCH ROAD TO SOUTH CHINO VALLEY CONSTRUCT ROADWAY WIDENING AUG 13 17514 MQ1J 180 AP 338.0 H752001C STP -180-B(204)A G BEAVER DAM - RANCH (EB & WB) 3" CIPR & FR AUG 13 WK1L 940 MA 0.0 SR19101C STP -000-6(171)T E UNIVERSITY DR (TEMPE) 741-561J AT-GRADE RAILROAD CROSSING DESIGN AUG 13 15913 WC1L 74 MA 22.4 STP -074-A(204)T E PICACHO WASH TRAIL TO JCT I-17 RR(5" TL, 3" PL) + AR ACFC SEP 13 19514 DT1M 188 GI 240.0 STP - G WINDY HILL INSTALL DRAINAGE FACILITY CBC SEP 13 WM1L 5013 MA 0.0 SR14401C 501-3(001)P E 32ND ST ( PHX) #741-536-B SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13 WN1L 7018 MA 0.0 SR09701C 701-8(003)P E 40TH ST PHOENIX 741-539-W SYSTEM PRESERVATION-MINOR BRIDGE REHABI SEP 13 18514 EG1M 288 GI 260 STP - G ROOSEVELT - YOUNG CBC EXTENSION OCT 13 ZV1L 0000 YU SLS CBI -SLS-0(201)A Y WIDENING AVE E FROM COUNTY 25TH STREET TO SR1 SYSTEM ENHANCEMENT (ENGINEERING) FY 14 GA1L 0000 NA WIN SL71101C TEA -WIN-0(203)A H THE STATION AT LA POSADA REHAB OF STATION AND LANDSCAPE FY 14 11814 SV1K 8 YU 13.7 H815801C IM - Y FOOTHILLS BLVD - DOME VALLEY RR (5" TL, 3" PL) & FR NOV 13 11913 TI1K 8 PN 170.0 IM - T BIANCO ROAD - JCT I-10 RR(5" TL, 3" PL) & AR-ACFC NOV 13 12814 NB1K 10 PM 283.6 H805201C IM -010-E(208)A T DAVIDSON CANYON - COUNTY LINE MILL AND REPLACE NOV 13 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 9 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: WQ1L 19 PM 59.0 H771401C T SAN XAVIER PEDESTRIAN BRIDGE PEDESTRIAN BRIDGE IMPROVEMENTS NOV 13 13313 RR1K 89 CN 476.6 H811601C STP -089-D(203)T F MOENKOPI WASH - HIDDEN SPRINGS 2.5" AC OVERLAY AND 1/2" AR-ACFC NOV 13 13812 AH1K 89 CN 510.0 NH -089-D(202)A F GRAY SPOT WASH - NORTH RED HILL 3" AC + FR NOV 13 13513 RT1K 180 CN 216.2 H811801C STP -180-(202)T F COLUMBUS AVENUE - SNOW BOWL RR 3" & AR-ACFC & TURN LANES NOV 13 18814 YJ1K 999 SW 0.0 H821701C STP -999-A(351)T Y BURNT WELL AND EHRENBURG REST AREAS WATER,STRUCTURAL,MECH & ELECTRICAL REH NOV 13 13614 SO1K 17 YV 269.2 IM -017-B(218)A P DUGAS TI - CHERRY ROAD RR (5" TL, 3" PL) & AR-ACFC DEC 13 13714 MS1L 19B SC 0.1 STP -B19-A(201)A T INTERNATIONAL BORDER - MARIPOSA/SR189 RR 2" AC DEC 13 14314 SD1K 40 CN 204.0 IM - F WALNUT CANYON - TWIN ARROWS RR 3" & 2" AC & AR-ACFC DEC 13 14814 RE1L 60 MA 115.5 BR -060-B(209)T P MONARCH WASH BR, STR #204 & 759 SCOUR RETROFIT DEC 13 15014 BT1L 60 GI 292.0 H826201C 060-E(207)A G SALT RIVER CANYON REST AREA REPLACE COMPOSTING TOILETS & STRUCTURA DEC 13 16514 SE1K 89A CN 386.6 STP -A89-B(210)A F PUMPHOUSE WASH - OVERLOOK RR (3"AC, 2.5" AC + AR-ACFC) FULL WIDTH DEC 13 MB1K 0000 PN CLG SS87301C STP -CLG-0(200)A T COOLIDGE AVENUE DESIGN / RECONSTRUCTION FY 14 13415 CN1M 40 NA 297.0 IM - H SUN VALLEY ROAD - WASHBOARD ROAD RR (5" TL, 3" PL) + 2"AC + FC JAN 15 17013 QD1L 40 NA 298.0 IM - H MP 298 UTILITY OVERPASS DESIGN OF CBC EXTENSION JAN 15 16006 QT1F 101L MA 53.5 E BALBOA DRIVE CONSTRUCT MULTI-USE PATH BRIDGE OVER TH IGA FY 15 15714 WH1K 80 CH 316.5 H800402C HSIP- S TOMBSTONE, MP 316.5 TO MP 318.0 LIGHTING AND SIDEWALKS MAR 15 13003 FR1C 8 YU 55.9 H206001C IM - Y MOHAWK REST AREA CONSTRUCT REST AREA TBD FY 15 40115 WU1K 10 MA 0.0 E SKY HARBOR WEST AIRPORT ACCESS CONSTRUCT ACCESS RAMPS TBD FY 15 11615 XP1L 10 LA 17.5 IM - Y WEST QUARTZSITE TI INTERSECTION IMPROVEMENTS TBD FY 15 11715 BA1M 10 LA 42.0 IM - Y MP 42 TO HOVATTER ROAD RR(4" TL, 3" PL) + AR-ACFC TBD FY 15 12407 FX1C 10 MA 161.2 H505101C E SR 202L (SANTAN) TO RIGGS ROAD CONST HOV & GEN PURPOSE LANE TBD FY 15 10015 QL1J 10 PM 247.0 H758301C T INA RD TO RUTHRAUFF RD RECONSTRUCTION FOR WIDENING TBD FY 15 10015 VH1L 10 PM 252.0 NH - T RUTHRAFF ROAD TI RECONSTRUCTION FOR WIDENING TBD FY 15 11815 NA1L 10 PM 284.4 IM -010-E(213)A T DAVIDSON CANYON WB BRIDGE, STR #598 SUPERSTRUCTURE REPLACEMENT TBD FY 15 11915 BU1M 10 CH 296.0 IM - T MESCAL ROAD TO JCT SR 90 RR(5" TL, 3" PL) + AR-ACFC TBD FY 15 12015 WD1L 10 CH 306.7 IM -010-F(219)A S SAN PEDRO RIVER BRIDGE EB #1530 & WB #1531 DECK REPLACEMENT & SCOUR RETROFIT TBD FY 15 12115 YB1K 10 CH 320.5 H821101C IM - S TEXAS CANYON REST AREA WATER, STRUCTURAL, MECHANICAL & ELECTRI TBD FY 15 12215 YI1K 10 CH 388.0 H821601C IM - S SAN SIMON REST AREA NEW WELL,WATER PUMPS,STRUC,ELECT,MECH TBD FY 15 12315 BW1M 15 MO 0.0 IM - F NEVADA STATE LINE - MP 13 RR(4" TL, 3" PL) AR-ACFC TBD FY 15 12415 VT1K 17 MA 195.0 E BUCKEYE RD,GRANT ST,ADAMS ST & JEFFERSON ST ELECTRICAL REHABILITATION TBD FY 15 12515 BZ1M 17 MA 198.0 IM - E BUCKEYE RD, GRANT,JEFFERSON & ADAMS ELECTRICAL REHABILITATION TBD FY 15 12415 HW1L 17 MA 202.3 IM - E INDIAN SCHOOL ROAD - PEORIA AVENUE SIGN REHABILITATION TBD FY 15 12615 CA1M 17 YV 279.6 IM - P SR 169 TO MIDDLE VERDE ROAD RR(5" TL, 3" PL) + AR-ACFC TBD FY 15 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 10 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 12715 SU1K 19 SC 16.0 IM - T PALO PARADO - CHAVEZ SLIDING TI RR (4" TL, 3" PL) + FR TBD FY 15 12915 CF1M 40 MO 74.0 IM - K HWY 141 JCT TO SILVER SPRINGS ROAD (WB) RR (5"TL, 3" PL) + AR-ACFC + SHOULDERS TBD FY 15 13015 CI1M 40 MO 87.0 IM -040-B(217)T K WILLOW RANCH ROAD TO MP 92, EB RR (5" TL, 3" PL) + AR-ACFC WITH SHOULDERS E TBD FY 15 13115 WT1L 40 YV 144.0 IM -089-B(214)T K ASHFORK RR BR - JCT SR 89, #807,#440, #1760,#1761 BRIDGE DECK REHABILITATION TBD FY 15 13315 JL1K 40 NA 284.3 BR -040-D(223)A H LEROUX WASH BRIDGE EB #1772 & WB #1773 BRIDGE REPAIR TBD FY 15 23701 ZY1D 40 AP 340.0 H552601C 040-E(001) H SANDERS PORT OF ENTRY RECONSTRUCT POE TBD FY 15 12815 CE1M 40F MO 47.8 IM -999-A(398)T K SOUTH OF KINGMAN ROCKFALL MITIGATION TBD FY 15 13515 CQ1M 60 MA 189.0 STP - E SOSSAMAN - MERIDIAN DRAINAGE IMPROVEMENTS TBD FY 15 10313 GS1H 60 PN 222.0 STP -060-D(208)A G SILVER KING SECTION & SUPERIOR STREETS RECONSTRUCT TO 4 LANE RDWY W/CNT TURN L TBD FY 15 16515 ZA1L 60 PN 228.8 G EAST OF QUEEN CREEK TUNNEL ROCKFALL MITIGATION TBD FY 15 13615 CW1M 60 GI 302.0 STP -060-E(214)T G MP 302 - 311 RR 3" AC + AR-ACFC TBD FY 15 23213 BM1L 64 CN 234.5 H825801C F GRAND CANYON AIRPORT- FS RD 328 SHOULDER WIDENING TBD FY 15 13715 KX1L 70 GI 259.0 H835901C G GILSON WASH BRIDGE, STR # 464 SCOUR RETOFIT TBD FY 15 13815 SR1K 75 GE 379.1 S DUNCAN BRIDGE - LITTLE SANDS WASH 3" AC & AR-ACFC TBD FY 15 14015 YZ1L 77 GI 156.8 G NEAR SUMMIT ROCKFALL MITIGATION TBD FY 15 14115 GP1G 82 SC 40.5 STP - T SR-82 AT MP 40.6 EXTEND CBC & ELIMINATE GUARDRAIL TBD FY 15 GU1M 86 PM 114.7 086-A(211)T T TOWN OF SELLS PEDESTRIAN BRIDGES CONSTRUCT PEDESTRIAN BRIDGE TBD FY 15 14215 KI1L 86 PM 115.8 T TOWN OF SELLS TO FRESNAL WIDEN SHOULDERS AND CULVERT EXTENSIONS TBD FY 15 16615 XT1K 87 GI 226.0 H820701C NH - P SLATE CREEK ROAD REPAIR TBD FY 15 14415 SP1K 89 YV 258.3 STP - P JCT US 93 - JCT SR 71 RR 3" & AR-ACFC TBD FY 15 11515 QQ1H 89 CN 452.6 H705601C NH - F SOUTH OF GRAY MOUNTAIN PASSING LANES (NB AND SB) TBD FY 15 14515 FP1L 89 CN 525.0 NH - F JCT US 89A - BIG CUT EP (PIPE) DROP-OFF MITIGATION TBD FY 15 16215 DL1M 89A YV 343.0 STP - P SOUTH OF JEROME ROCKFALL MITIGATION TBD FY 15 16315 UZ1J 89A CN 525.0 STP - F JCT US 89 - COLORADO RIVER EXTEND PIPES AND CULVERTS TBD FY 15 14615 JR1L 92 CH 340.5 BR -092-A(203)A S SAN PEDRO RIVER BRIDGE #449 BRIDGE REPLACEMENT TBD FY 15 14715 SF1K 180 AP 386.3 STP - G GENERATING STATION ROAD - JCT US 60 RR 3" & CHIP SEAL TBD FY 15 14815 SG1K 180 AP 407.0 STP - G JUAN CARILLO - FH275 RR 3" AC & AR-ACFC TBD FY 15 14915 ZA1J 191 CH 331.0 STP - S I-10/ US 191 TI AT MP 331 CONSTRUCT IMPROVEMENTS TBD FY 15 15015 DX1M 191 AP 418.0 STP - H BURNSIDE - CHINLE FENCING & CATTLE GUARDS TBD FY 15 41015 NX1L 202L MA 0.0 E BASELINE - SALT RIVER, SEGMENT 6 CONSTRUCT NEW FREEWAY TBD FY 15 43514 WZ1K 202L MA 0.0 RARF- E 17TH AVE TO 51ST AVE, SEGMENT 3 CONSTRUCT NEW FREEWAY TBD FY 15 41215 XC1K 202L MA 43.0 CM - E VAL VISTA DR. - DOBSON RD CONSTRUCT FMS TBD FY 15 15315 ED1M 264 AP 441.0 STP - H BURNSIDE - SUMMIT FENCE & CATTLE GUARD TBD FY 15 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 11 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 16815 SL1K 264 AP 441.0 STP - H BURNSIDE - CROSS CANYON 2" AC & AR-ACFC TBD FY 15 15515 JC1H 286 PM 20.0 H690701C STP - T SR 286 (SASABE - ROBLES RANCH HWY) REPAIR HEADCUTTING PROBLEMS AT LW WATE TBD FY 15 43015 EW1M 303L MA 0.0 RARF- E US 60 GRAND AVE / SR 303L TI, INTERIM LANDSCAPE CONSTRUCTION TBD FY 15 15615 YC1K 999 SW 0.0 H821301C STP - T SACATON & CANOA RANCH REST AREAS WATER/WASTEWATER, STRUC & ELECTICAL RE TBD FY 15 16115 XX1L 999 SW 0.0 FA -999-A(383)T E STATEWIDE DYNAMIC MESSAGE SIGN PHASE 10 CONSTRUCT DYNAMIC MESSAGE SIGNS TBD FY 15 15815 QH1L 999 MA 0.0 STP - E VARIOUS LOCATIONS DRAINAGE TUNNEL IMPROVEMENTS TBD FY 15 OB1K 0000 MA MMA SS88101C STP -MMA-0(217)A E MCKELLIPS ROAD - SR101L TO ALMA SCHOOL ROADWAY RECONSTRUCTION FY 15 PH1K 0000 MA MMA SS89301C STP -MMA-0(226)A E DOBSON ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 15 OA1K 0000 MA MMA SS87901C STP -MMA-0(218)A E GILBERT ROAD BRIDGE OVER THE SALT RIVER CONSTRUCT BRIDGE FY 15 11112 CO1J 10 PM 236.4 T MARANA ROAD TO CORTARO ROAD DESIGN (RECONSTRUCT & WIDEN FRONTAGE R DESIGN FY 15 10511 XQ1L 95 MO 182.0 K LAKE HAVASU STATE PARK (CONTACT POINT) PH II DESIGN PARKING DESIGN FY 15 42115 ER1M 202L MA 0.0 IM - E ELLIOT RD - BASELINE RD, SEGMENT 5 DESIGN NEW FREEWAY DESIGN FY 15 10612 QP1C 60 NA 342.0 H510701C G SHOW LOW TO LITTLE MORMON LAKE WIDEN ROADWAY JUL 14 LK1K 0000 MA TMP SS73401C CM -TMP-0(210)X E BROADWAY ROAD: RURAL TO MILL AVENUE PEDESTRIAN IMPROVEMENTS FY 15 13915 RW1L 75 GE 387.0 BR - S VARIOUS BRIDGES (STR #S 861,202,242,983,243,251) SCOUR RETROFIT DEC 14 14315 SG1L 87 PN 148.0 BR - T GILA RIVER BRIDGE, STR #635 SCOUR RETROFIT DEC 14 16715 EA1M 260 YV 220.0 STP - P SR 260 AT INDUSTRIAL DRIVE IN CAMP VERDE ROUNDABOUT DEC 14 GZ1L 0000 PM TUC HPP -TUC-0(241)A T HOUGHTON RD: UPRR TO I-10 - WIDENING ROADWAY WIDENING FY 16 15710 NN1F 10 LA 3 H616101C NH - Y EHRENBERG PORT OF ENTRY RECONSTRUCT EB PORT OF ENTRY TBD FY 16 40016 EK1M 10 MA 129.5 IM - E DYSART RD - 83RD AVE DESIGN & CONSTRUCT FMS TBD FY 16 10112 JW1K 10 PN 186.7 T EARLEY ROAD TO JCT I-8 ROAD WIDENING TBD FY 16 10208 PJ1F 10 PM 248.0 NH -010-D T INA ROAD TI RECONSTRUCT TI & MAINLINE TBD FY 16 10816 GQ1J 17 MA 216.0 IM - E I-17 @ PEORIA AND UNION HILLS DRAINAGE GRATE IMPROVEMENTS TBD FY 16 10916 CB1M 17 YV 292.0 IM - P SOUTH OF MCGUIREVILLE ROCKFALL MITIGATION TBD FY 16 11016 KH1L 40 CN 218.7 IM - F TWIN ARROWS TI, EB OFF-RAMP RAMP REMOVAL, RECONSTR & ACCESS CTRL M TBD FY 16 11116 YF1K 40 SW 235.0 H821401C STP - H PAINTED CLIFFS & METEOR CRATER REST AREAS SYSTEM PRESERVATION - RESTORATION/REHAB TBD FY 16 43016 JJ1H 60 MA 139.0 HES -060-B(ATZ) E SR 303L TO SR 101L, AGUA FRIA, PHASE 2 CONSTRUCT ROADWAY IMPROVEMENTS TBD FY 16 11216 CV1M 60 PN 232.0 STP - G WEST OF PINTO CREEK BRIDGE ROCKFALL MITIGATION TBD FY 16 11416 MW1L 74 MA 30.0 H840301C STP - E I-17 AND LAKE PLEASANT PKWY CONSTRUCT DRAINAGE IMPROVEMENTS TBD FY 16 12916 DC1M 77 NA 384.0 STP - H 5 MILE WASH - JCT 377 CBC EXTENSION TBD FY 16 10517 DD1M 79 PN 122.5 STP - T MP 122.5 EXTEND PIPES AND CULVERTS TBD FY 16 11616 GQ1G 82 SC 39.0 STP - T ELGIN TURNOFF EXTEND CMP'S, FLATTEN SLOPE & ELIMINATE G TBD FY 16 11716 DJ1M 87 NA 346.0 STP - H I-40 TO JCT SR 264 CBC EXTENSIONS TBD FY 16 PROJECT NAME AND TYPE OF WORK MAY BE TRUNCATED. ARIZONA DEPARTMENT OF TRANSPORTATION 5 YEAR BID DATE REPORT 3RD SORT: BID DATE, RTE, MP Page 12 of 13 CPSID: RTE: CO: TRACS: PROJECT ITEM #: MP: NUMBER: PROJECT NAME: TYPE OF WORK: BID DATE: DESIGN DIST: FIRM: 10512 CZ1J 89 YV 319.0 H851801C P JCT SR 89A TO DEEPWELL RANCH ROAD WIDEN THE SR 89 CORRIDOR TBD FY 16 12516 LP1K 89A CN 538.0 STP - F COLORADO RIVER TO HOUSE ROCK (PHASE II) EXTEND PIPES AND CULVERTS TBD FY 16 10413 TC1J 93 MO 116.0 K CARROW TO STEPHENS CONSTRUCT 4-LANE DIVIDED HIGHWAY TBD FY 16 10416 NW1L 95 YU 34.0 H459901C NH -095-B(201) Y FORTUNA WASH BRIDGE CONSTRUCT NEW BRIDGE TBD FY 16 13016 TL1L 101L MA 50.7 NH - E RED MOUNTAIN - CHANDLER BLVD SIGN REHABILITATION TBD FY 16 11916 KZ1K 180 CN 216.1 STP - F NAVAJO RD - FLAGSTAFF CITY LIMITS WIDENING, C&G & DRAINAGE IMPROVEMENTS TBD FY 16 12016 IS1L 191 GH 120.3 STP - S RELATION ST TO JCT US70 INTERSECTION IMPROVEMENT TBD FY 16 12116 DW1M 191 AP 345.0 STP - H SANDERS - WITCH WELLS FENCING & CATTLE GUARDS TBD FY 16 41115 WW1K 202L MA 0.0 E SALT RIVER BRIDGE, SEGMENT 7 CONSTRUCT NEW FREEWAY TBD FY 16 12716 FG1M 202L MA 0.0 NH - E PUMP STATION FLOOD EROSION CONTROL TBD FY 16 10616 XD1K 260 YV 218.5 STP - P THOUSAND TRAILS TO I-17 CONSTRUCT INTERIM IMPROVEMENTS TBD FY 16 12216 LY1C 260 GI 258.0 NH - P LION SPRINGS SECTION RECONSTRUCT TO A 4-LANE DIVIDED TBD FY 16 CD1L 260 AP 394.0 H826901C G LITTLE COLORADO RIVER BR (STR # 416) SYSTEM PRESERVATION - MINOR BRIDGE REHA TBD FY 16 12316 EH1M 288 GI 289.0 STP - G SOUTH OF YOUNG ROCKFALL MITIGATION TBD FY 16 40616 EV1M 303L MA 103.2 IM -303-A(216)S E I-10/303L TI, PHASE II CONSTRUCT NEW FREEWAY TBD FY 16 12416 BU1L 999 SW 0.0 H826301C STP - K HAVILAND & MARBLE CANYON REST AREAS STRUCTURAL REHABILITATION TBD FY 16 PG1K 0000 MA MMA SS89401C STP -MMA-0(225)A E MCKELLIPS ROAD BRIDGE CONSTRUCT BRIDGE OVER THE SALT RIVER FY 16 BP1J 0000 PM TUC HPP -TUC-0(201)A T HOUGHTON ROAD WIDENING @ UPRR ROAD WIDENING OVER RAILROAD BRIDGE FY 16 11312 CQ1J 10 PM 264.0 NH - T COUNTRY CLUB ROAD TI DESIGN TRAFFIC INTERCHANGE (PE PH 1) DESIGN FY 16 10716 BV1M 10 CH 383.0 IM - S SAN SIMON PORT OF ENTRY PE PH 1 & 2 DESIGN FY 16 12816 CM1M 40 NA 297.0 IM - H GOODWATER - YELLOWHORSE PE PH 1 & 2 DESIGN FY 16 40216 EN1M 60 MA 192.0 NH - E CRISMON RD - MERIDIAN RD DESIGN HOV/GPL DESIGN FY 16 10216 DO1M 93 MO 109.0 NH - K CANE SPRINGS PE PH 1 & 2 DESIGN FY 16 ZE1L 17 YV 287.0 017-B(224)S P VERDE RIVER BRIDGES NB & SB #1731 & #505 DESIGN DEC 15 ZI1L 80 CH 364.0 S WHITE WATER DRAW BRIDGE #1626 DESIGN DEC 15 11207 QK1C 19 PM 58.7 NH - T AJO WAY TI (JCT SR 86) RECONSTRUCT TI TBD FY 17 10217 CD1M 40 MO 40.0 IM - K CROOKTON TO TRANSWESTERN SIGN REHABILITATION TBD FY 17 10317 CG1M 40 MO 81.0 IM - K EAST OF US 93 TI ROCKFALL MITIGATION TBD FY 17 10417 CH1M 40 MO 83.0 IM - K WILLOW SPRINGS ROCKFALL MITIGATION TBD FY 17 10617 DI1M 87 CN 324.0 STP - P CLOVER CREEK ROCKFALL MITIGATION TBD FY 17 10717 FF1M 92 CH 351.0 STP - S MELODY LANE - NACO RD WIDEN TO 3 LANES TBD FY 17 40317 EP1M 101L MA 11.2 NH -888-A(217)T E AGUA FRIA I-10 TO I-17 CONSTRUCT FMS TBD FY 17 |